Multi Rate Test
Multi Rate Test
These “tests” are applicable at any time. The data are most readily
analyzable if the well is produced at approximately constant BHP or
when BHP and flow rate are known continuously as functions of time.
Basic Equations
0 ≤ t ≤t1 ------------ q1
t1 ≤ t ≤t2 ------------ q2
t2 ≤ t ≤ t3 ------------ q3
…………..
…………..
• The result should be a straight line with slope m’ and intercept b’ from which, permeability and skin factor can be estimated.
• This analysis technique is not recommended for variable rate tests unless the variable rate results only from wellbore storage
effect in which the surface rate is constant.
TWO RATE TEST
The two-rate flow test, developed by Russell, is simply a special case of multiple rate test.
2. Lower the bottom hole pressure bomb into well( 3-4 hours prior to rate change) and
begin pressure measurement
3. Change the flow rate by adjusting the choke at the wellhead. After a short period of
transition, the rate stabilizes at its new rate, q2
Either a decreasing or increasing rate sequence may be used.
However field tests indicate that rate re-stabilization is faster for a rate reduction
than for rate increase
Above equation shows that a linear plot of Pwf vs {log[(t1 + ∆t’)/∆t’ + q2/q1 log(∆t’)} should
yield a straight line with slope m’ and intercept Pint
1. Russell Method
2. Pinson Method
3. Tiab Methods
Russell Method
q2 > q1
Once the slope m1’ and intercept Pint are known, we can calculate k ,s and P*.
P* is known as “False Pressure” and is often used to calculate average reservoir pressure(Pavg<P*<Pi)
Pinson Method
Should be used only when t1>>∆t
Pint=Pwf(∆t=1hr)
Step 1: Calculate t2R from above equation. Then plot Pwf vs t2R
on semi log graph as shown in figure
Step 2: Identify straight line of slope m1’. This line corresponds to infinite acting radial flow line
It is difficult to maintain a constant flow rate during long production periods. If the flow rate varies in cyclic or
oscillatory manner than reservoir limit testing techniques can still be used.
To analyze a variable rate reservoir limit test pressure vs time graph is plotted. Pressure points must be
segregated by the rate occurring when a pressure measurement was made.
This data plot should have a straight line section but due to flowrate variation, there is actually never a straight
line but a least squares can usually be fit to the pressure points observed at one of the rates.
The slope m* of the straight line is used to estimate reservoir drainage volume.
Problem:
The figure shows pressure data from the last 5 years of the 11 year life of an industrial
waste disposal well.
Although the data are for injection, the methods of this section can be applied by using a
negative rate.
Injection is with 1,2 or 3 pumps so the rate is -5140, -10,280, or -15,420 STB/D
Cumulative fluid injected is known accurately. The average injection rate is -9,660 STB/D.
B=1.0
-6 -1
Ct=5x10 psi
The slopes m* are 2.62x10−3 , 2.15x10−3 , 3.16x10−3 psi/hr
Deliverability testing has long been used to credit the capacity of gas well to deliver against the
specific flowing bottom hole pressure. Such type of testing can be used for oil wells.
It is particularly useful for reservoir systems operating below bubble point pressure when fluid
properties and relative permeabilities vary with distance from the well. Oil flow rate can be
obtained by
MODIFIED ISOCHRONAL
FLOW AFTER FLOW TEST
TEST
FLOW AFTER FLOW TEST
• Well q0 = oil flow rate (STB/D) occurring at bottom hole pressure Pwf
__
• Given a stabilized q0 and the corresponding p and Pwf, it is_ possible to calculate J*
Standing suggested estimating a future value of the productivity index from the present value by