2, Hoisting System 1.1 by Azka Roby Antari
2, Hoisting System 1.1 by Azka Roby Antari
2. Making a trip
When the bit is worn or when total borehole depth has been reached, all of the drill string must be pulled out of the hole to
change bits or run in casing pipe.
• The first step is to disconnect the swivel from the hook and place the kelly and the swivel – which is still connected to the
mud pumps by the hose – in a sheath called the rathole (Fig. 1.6a).
• The crew latches the elevator under the tool joint of the first length of drillpipe and the driller hoists the drill string to a
height of three joints of pipe with the draw works.
• The fourth length of pipe is clamped in the rotary table by the slips and the connection is unscrewed with the tongs (Fig.
1.6b). A stand of three lengths of pipe is then hanging from the elevator. The crew pushes the lower end of the stand so
that is rests on the setback. Then the derrickman, who stands on the monkey board, unlatches the elevator, holds the
stand and places the upper end of the stand in the pipe rack (Figs. 1.6c and 1.7).
• The operation continues down to the drill collars that are also stacked vertically in threes.
• The stand length depends on how high the derrick is. The largest rigs handle stands in threes, lightweight rigs in twos
and the smallest ones can manage only singles. The running in or tripping in, operation is carried out in the same way.
• During a round trip both rotation and circulation are at a standstill. If either is needed, the kelly is taken out of the rathole
and screwed back onto the drill string.
2 KOMPONEN UTAMA
1. SUPPORTING
HOISTING STRUCTURE
SYSTEM :
(I.Rangka Pendukung )
SUPORTING
1.1.STRUCTURE
MAST / DERRICK
1.2.( SUBSTRUCTURE
Rangka Pendukung )
1.3. RIG FLOOR
- MAST
- SUSTRUCTURE
2. HOISTING EQUIPMENT
- RIG FLOOR
( Peralatan Pengangkat )
II. HOISTING EQUIPMENT
2.1. OVERHEAD TOOLS aka
( BLOCK
Peralatan
ANDPengangkat
TACKLE:
) a) Crown block
HOISTING SYSTEM - b)
DRAWWORK
Travelling block
- c)
OVERHEAD
Hook TOOLS
d)BLOCK
ElevatorASSEMBLY
2.2. DRAWWORK
DRILLING LINE
2.3. DRILLING LINE
Interesting past of the term
“derrick”
The term “derrick” comes from Thomas Derick, a hangman from
Tyburn, England (today sub-urban of London), who invented a type of
gallows using a movable beam and pulley system during the
Elizabethan era (1600s). During his lifetime, Derick executed over
3,000 people, many of them with his modified gallows device. his
gallows and the supporting framework were so distinctive that
everyone began calling any towerlike structure with cross braces and
girders a “Derick.” By the 19th century, scholars had added a the extra
“r.”
1.1. Menara Bor
A semipermanent structure of square or rectangular cross-section having members that
are latticed or trussed on all four sides. This unit must be assembled in the vertical or
operation position, as it includes no erection mechanism. It may or may not be guyed.
2. PORTABLE MAST :
CANTILEVER MAST :
Box Style Substructure
Raised Floor Catwork Suport
Raised Floor Drawwork Elevator
Sling Shot Rig Floor Elevator
BOOTSTRAP MAST
FULL VIEW MAST
TELESCOPIC MAST
Free Standing Mast
Guyed Mast
Skid Mounted
Truck mounted
Trailer Mounted
Self Propeled :
Back in drive
Drive in
Model-model Menara bor :
Derrick
Di desain untuk dapat
mengakomodir kebutuhan : Crownblock
Raising
Track
A Frame
Drawworks
Raising
leg Engines
a. Standart b. Portable
(front view) (side view)
Model-model Menara bor :
Portable Derrick
Portable derrick banyak digunakan
untuk pemboran menengah (kapasitas
escoping
500 – 750HP) dan untuk pekerjaan mast
workover dan well services. Pada saat hydrolic
instalasi, portable mast dilengkapi ram
Stand In
Packed
Model-model Menara bor :
Mast
CANTILEVER MAST
Cantilever mast atau jack-knife
mast memberikan pandangan
yang cukup luas dan lantai bor
yang cukup lapang sehingga dapat
meningkatkan keselamatan kerja.
Model-model Menara bor :
Full View Mast Design (A mast)
Full View Mast pada dasarnya
adalah struktur “A” frame yang
dipegang oleh sepasang kaki yang
juga merupakan bagian dari
mekanisme untuk mendirikan mast.
Mast ini memberikan pandangan
yang luas, lantai bor yang lapang
sehingga dapat meningkatkan
keselamatan kerja.
Model-model Menara bor :
Full View Mast Design (A mast)
Special advantages :
1. The driller has a very good visibility to the monkey man and the hook.
2. The drill floor is empty, what means that various sizes of drawworks
can be used.
3. Free space around the catheads, and the support beams are
mounted in the front.
4. Big stability by due to the wide support distances.
5. Massive framework construction.
6. Easy assembly and disassembly.
7. The rope stays reeved in the pulleys during the transport.
8. Different possibilities of transport :
• Mounted to skids and movable with fold legs
• Transport of disassembled simple parts
Model-model Menara bor : TELESCOPIC MAST
A semipermanent structure
of square or rectangular
cross-section having
members that are latticed
or trussed on all four sides.
This unit must be
assembled in the vertical or
operation position, as it
includes no erection
mechanism. It may or may
not be guyed. GUYED TELESCOPIC MAST
Model-model Menara bor : GUYED MAST
E
Bagian penting
gine pole sisi water table
crown block
water table
pada menara
A : Tinggi menara, dari
monkey
puncak lantai bor sampai
board
tinggi
menara A dasar dari crown block
F girt beams atau water table.
B : Base Square, jarak
G cross
bracing
antara kedua kaki
rig floor menara.
C C : V-door opening, disebut
sub tinggi
structure lantai bor
juga window opening
B sisi lantai bor
D : Water table opening,
Tampak Belakang
(sebelah pompa lumpur) lebar bukaan terkecil
pada menara.
E : Gin-pole clearance, jarak
antara crown block floor
dengan pulley block.
F : Girt, sekur mendatar.
G : Brace, sekur diagonal.
Tampak Samping Tampak Depan Tampak Samping
(sebelah pipe rack) (seberang pompa) (sebelah drawwork)
Desain dan ukuran menara bor
10 80 20 5 6 23 8 8
11 87 20 5 6 23 8 8
12 94 24 5 6 23 8 8
16 122 24 5 6 23 8 8
18 136 26 5 6 23 8 12
18A 136 30 5 6 23 8 12
19 140 30 7 6 26 6 17
20 147 30 6 6 26 6 17
25 189 37 7 6 26 6 17
Maintenance menara bor
Secara garis besar prinsip-prinsip pemeliharaan dan pemakaian portable derrick dapat
diuraikan sebagai berikut (untuk lebih detail harus diperiksa dalam instruction manual) :
a. Sebelum menegakkan mast, check manufacturer load distribution diagram, untuk
meyakinkan bahwa tanah atau fondasi pendukung cukup kuat
b. Demikian juga guy line diagram dan yakinkan bahwa jangkar yang terpasang telah di
design mempunyai kekuatan mampu menahan beban
c. Beberapa pengecekan rutin yang harus dilakukan setiap waktu tertentu :
- Cek tempat-tempat yang dilas pada mekanisme untuk menegaskan apakah ada
retak-retak atau tanda-tanda lainnya;
- Buang udara dari hydraulic ram setiap sebelum menurunkan menara dan
yakinkan bahwa suply hidrolic dari reservoir cukup;
- Wire rope, termasuk operating line, raising line dan guy line harus diperiksa
adakah tekukan, kawat-kawat putus atau lain-lain kerusakan;
- Check safety latches dan guides telescopic mast untuk memastikan telecoping
beroperasi bebas sebelum menurunkan dan menaikkan. Pelihara bersih dan
lumasi
- Check unit, atas kerataan (level) dan yakinkan kerataan fondasi dan pendukung
lainnya setelah setiap pendirian
- Check pelumasan pada crown, sheave dan sheaves-sheaves lainnya
- Check tangga-tangga sebelum operasi menurunkan
- Check anchor kembali bila akan menarik beban berat
- Sebelum memulai rig up, periksa dan pelajari instruction manual untuk
keperluan itu secara teliti
1.2. Substructure
Konstruksi baja yang besar yang
dibangun untuk menjadi dasar dan
menunjang menara bor yang
tingginya ditentukan oleh kebutuhan
pencegah semburan liar (BOP).
1. For use with derrick (or mast) having static hook load capacity
2. Maximum pipe setback capacity
3. Maximum rotary-table supporting capacity irrespective of
setback load
4. Corner loading capacity (for derricks only)
5. Loads imposed by tensioning devices
6. Additional loads
Model-model Substructure:
MEMILIH LUAS & TINGGI
LANTAI BOR
• Lantai bor berbentuk bujur sangkar atau segi
empat, sedang panjang sisi dan tingginya
disesuaikan dengan menaranya.
• Secara ringkas, ukuran, luas dan inggi lantai
bor, dapat dilihat pada Tabel dibawah ini :
Tinggi Menara Sisi Lantai Bor Tinggi Lantai Bor
(inch) (inch) (inch)
94' 24' 7'3"
122' 24' 7'3"
136' 26' 7'3"
140' 30' 10'
147' 30' 14'
189' 37'6" 14'
Substructure height :
Substructure plate :
1.3. Rig Floor
Rig Floor
Ditempatkan di atas substructure,
yang memberikan ruangan yang
diperlukan untuk melakukan
berbagai aktifitas pemboran.
1. Rotary table,
2. Drawwork,
3. Rotary drive,
4. Drilling Console,
5. Make-up & Break-out Tong,
6. Rat hole & Mouse hole,
7. Dog house
2.1. Block and Tackle
Overhead tools
• Travelling block;
Hook
• Hook;
• Elevator.
Overhead tools
Crown block
An assembly of sheaves or pulleys
mounted on beams at the top of the
derrick. The drilling line is run over
the sheaves down to the hoisting
drum.
Drilling line dililitkan pada sheaves
atas yang ada pada crown block dan
pada sheaves bawah yang ada pada
traveling block. Jumlah sheaves pada
crown block selalu satu buah lebih
banyak (untuk dead line) dari sheaves
pada travelling block.
Crown block menghubung drawwork
ke travelling block.
Overhead tools
Travelling
block
An arrangement of
pulleys or sheaves
through which
drilling cable is
reeved, which
moves up or down
in the derrick or
mast.
Overhead tools
Pemeriksaan Block
Periksa keausan dari groove root radii dari traveling block dan
hook bail, bila terjadi keausan berarti kapasitas akan turun
(lihat table & gambar E 5-1, API 8A, hal21)
Pemeriksaan
Pemeriksaan Block
Tread Diameter
Load capacity
Contoh :
Link Elevator
Rated
Part No.* Size–in. Size–mm Capacity/Set Weight/Set
Tons lb kg
37355-1036 1-3/4 x 36 44.45 x 914.4 150 125 56.7
37355-1048 1-3/4 x 48 44.45 x 1219.2 150 160 72.6
37355-1060 1-3/4 x 60 44.45 x 1524.0 150 190 86.2
37355-1072 1-3/4 x 72 44.45 x 1828.8 150 230 104.3
37355-1084 1-3/4 x 84 44.45 x 2133.6 150 270 122.5
37355-1096 1-3/4 x 96 44.45 x 2438.4 150 310 140.6
37355-1120 1-3/4 x 120 44.45 x 3048.0 150 390 177.3
Overhead tools
Elevator
Drill Pipe Elevator dipakai khusus untuk Drill Pipe, demikian juga
lainnya dibuat spesifik. Macam elevator telah dibahas pada
introduksi di depan. Elevator digantung pada elevator link, yang
dipasang disamping hook.
• Untuk collar type elevator harus dicek squareness, dan uniformity dan
kedalaman aus. Apabila permukaan fitting lebih dari 1/16 inch, harus
direcondition.
• Untuk 18º taper elevator harus lebih sering diperiksa dari pada collar
type, yaitu taper dan conical bore harus dicek keausannya.
• Disamping itu sudut kemiringannya dari taper dan hard bond tool joint
posisinya.
• Semua bagian yang bergerak harus dilumasi setiap round trip .
• Pada waktu yang sama pula periksa latch dan mekanisme latch spring
apakah sudah bekerja dengan benar.
• Check hang pin, kalau aus akan dapat slack in (melonggar) lubang
elevator.
• Link block bolt dan nut harus dikunci agar tidak lepas.
• Setiap tahun 2 kali drill pipe elevator harus telah diperiksa keausannya
dengan calibrated instruments untuk mengetahui keausan dan
berubahnya ukuran.
PROSEDUR MEMERIKSA DC ELEVATOR
Auxiliary
Drawwork Brake
Hoisting Drum
Komponen-komponen utama yang terdapat
pada drawwork terdiri dari :
– Revolving drum,
Merupakan suatu drum untuk penggulung kabel bor.
– Breaking system,
Terdiri dari mechanical main break dan auxiliarydraulic atau
electric, berfungsi untuk memperlambat atau menghentikan
gerakan kabel bor.
– Rotary drive,
Berfungsi untuk memindahkan tenaga dari drawwork ke rotary
table.
– Catheads,
Berfungsi untuk mengangkat atau menarik beban-beban kecil
pada rig floor dan juga berfungsi sebagai pelepas atau
penyambung sambungan pipa bor.
Hoisting Drum
Output RPM x jumlah gigi sproket output = input RPM x Jumlah gigi
srocket input
– Dead line
drilling line
6x7 6 7
6 x 19 6 16 sampai 26
6 x 37 6 27 sampai 49
8 x 19 8 16 sampai 26
6 x 19
Seale constructions with fiber core.
Rotary and cable tool drilling line
and casing line
6 x 19
Seale with independent wire rope core.
Deep or "big rig" rotary drilling
and casing lines.
6 x 25
Filler wire with fiber core.
Sucker rod and tubing lines or
coring rig drilling lines.
6 x 25
Filler wire with independent wire rope core.
Winch lines.
6x7
Fiber core.
Sand and coring line.
Design (Arah pintalan)
LRL
RLL
e. Grade of Steel
LLL=left lang lay
- MPS = Mild Plow Steel
- PS = Plow Steel
- IPS = Iprove plow steel
- Eips = Extra Improve Plow Steel
Grade of Steel
Pada saat ini sebagian besar grade dari steel wire rope adalah :
- IPS : Improved Plow Steel
- EIPS : Extra Improved Plow Steel
Disamping itu terdapat grade wire rope yang lainnya yang dipakai
di perminyakan :
- PS : Plow Steel
- MPS : Mild Plow Steel
1. Fibre Core (FC) adalah core dari tali dengan bahan dari serat
sisal/manila atau fiber buatan seperti polypropylene. Wire rope
dengan core ini akan lebih lentur dan lebih murah, tetapi dari
segi kekuatan /normal capacity dari wire rope inii lebih rendah.
Type ini banyak dipakai untuk swab line.
2. Independent Wire Rope Core (IWRC), adalah core yang berupa
wire rope. Type ini yang paling banyak di pakai di operasi
perminyakan, mempunyai nominal strength lebih besar
dibanding yang lainnya, tetapi harganya lebih mahal.
f. CORE :
- Fibre Core ( FC)
- Independent Wire Rope Core (IWRC)
- Strand Core (SC)
CARA IDENTIFIKASI
1”. 5000’ . 6x19. S. PRF. RRL.IPS.IWRC
1” – Diameter drilling line
5000’ – Panjang drilling line
6 - Jumlah strand setiap Line.
19 - Jumlah wire/kawat per Strand
S - Seal Pattern
PRF – Preformed Strands
RRL – Right Regular Lay
IPS - Improved Plow Steel
IWRC- Independen Wire Rope Core
Identifikasi Drilling Line (kabel pemboran)
Drilling line diidentifikasikan dengan angka dan singkatan-singkatan, hal ini penting untuk Saudara pahami.
Kabel bor ini berdiameter 1 inci, panjangnya 5000 ft, terdiri dari 6 jalinan
besar kawat (strand), dimana setiap strand dibelit oleh 19 tali kawat yang
dipilin (wire rope). “S” berarti terdapat material yang diisikan dengan pola
tertentu pada rongga antara inti kabel ini dengan strand-nya. “PRF” berarti
penjalinan dilakukan dengan proses pendahuluan didalam pabrik, sehingga
jalinan itu membentuk profil helix, tidak mudah terurai, celah antar strand
kecil dan. “RRL” berarti jalinan strand dipilin mengarah ke kanan, tetapi
wire yang membelit masing-masing strand dipilin mengarah ke kiri. “IPS”
menunjukkan grade of steel, kawat tersebut terbuat dari baja berkualitas
tinggi, “IWRC” berarti diantara jalinan kawat tersebut terdapat sebuah tali
kawat inti yang tersendiri (core) dengan nominal strenght yang tinggi.
Tugas ; buatlah jalinan kawat RRL, LRL, LLL, dan RLL !, (masing2 kelompok)
Panjang Wire ropes
Panjang wire rope yang harus dipesan disesuaikan dengan tinggi
menara dan jumlah lilitan (no line strung), seperti pada tabel
berikut:
Derrick Minimum Suggested
Height Lines Length length
strung
ft ft ft
Pemotongan Drilling
Line
PENANGANAN WIRE ROPE
Umur pakai (service life) wire rope dievealuasi dengan suatu nilai yang disebut
“Ton-miles”. Nilai ton-mile tergantung pada jumlah tali (strung). Wire rope yang
telah mencapai nilai ton-miles-nya harus digeser dan dipotong.
5 TYPE OF TON-MILES CALCULATIONS to obtain the total service received
from a rotary drilling line
4 Coring ton-miles.
BF = 1 – (ρ mud/ ρ steel)
M. A. Mian :
1 x reaming
Td = 3(TR at d2 – TR at d1)
The actual ton-miles of work performed by drilling line during drilling operation by drilling
down a length of a section of a drill pipe, plus picking up, connecting, and starting to drill with
the next section, from depth d1 to depth d2 is given by :
No reaming
Td = 1/2 (TR2 – TR1)
1 x reaming
Td = 3/2 (TR at d2 – TR at d1)
Tc = 2 (TR2 – TR1)
M. A. Mian :
Norton J. Lapeyrouse :
CH : effective weight of drill Collar and Heavy Walled Drill Pipe assembly
less the effective weight of the same length of drillpipe.
7
The Design Factor for a wire rope is applied to compensate for wear and
shock loading. API recommended a minimum ;
1. DF = 3 ; for hoisting operations and
2. DF = 2 ; for setting casing or when pulling on stuck pipe.
DESIGN FACTOR
Design factor
• - Sand line 3
• - Rotary drilling line 3,5
• - Mast raising dan lowering line 2,5
• - Hoisting service diluar pemboran 3
• - Rotary drilling line ketika running casing 2,5
• - Mencabut pipa terjepit atau pekerjaan serupa 2,5
DESIGN FACTOR
Example ton-miles 1
Example ;
BF = 0.8534
MD = 4000 ft Solution :
DC length = 300 ft
Block assy = 15.000 lb Result :
DRUM DIAMETER
Derrick or mast 11 13 14 16 18 20 22 24 26 28 30 32 34 36
height (ft) CUT OFF LENGTHS (METER/LAPS)
187 15 ½ 14 1/2 13 1/2 12 1/2 11 1/2
34.6 34.7 34.5 33.9 33
142-143-147 13 1/2 12 1/2 11 ½ 11 1/2 10 1/2
25.9 25.9 25.7 27.5 26.8
133-136-138 15 1/2 14 1/2 12 1/2 11 1/2 11 ½ 10 1/2 9 1/2
24.7 25.5 23.9 23.9 25.7 25.1 24.3
126-129-131 17 1/2 15 1/2 14 1/2 12 1/2 12 1/2 11 1/2 10 ½ 9 1/2 9 1/2
22.3 22.3 23.1 21.9 23.9 23.9 23.5 22.7 24.3
94-96-100 19 1/2 17 1/2 14 1/2 12 1/2 11 1/2 10 1/2 9 1/2 9 1/2 8 1/2
20.2 19.6 18.5 18 18.4 18.4 18.2 19.7 19
87 17 1/2 14 1/2 12 1/2 11 1/2
18.2 16.2 16 16.5
66 12 1/2 11 1/2
11 12
Menggeser dan memotong (Slipping and Cut off)
Pi = Ff vf Ph = W vb
Where : Where :
Pi = input power of the Ph = output power/ hook
block and tackle power (HP)
(HP) W = travelling block
Ff = drawwork load load (lbf)
(lbf) vb = velocity of the
vf = velocity of the fast travelling block
line (ft/min) (ft/min)
1 HP ≈ 33.000 ft-lbf/min
output power pada kondisi ideal
(frictionless)
Ph = W vb
Dimana:
Fd = load applied to the derrick
W = hook load
Fs = tension in the dead line
Ff = tension in the fast line
Jika beban W diangkat dengan menarik fast line, friksi pada sheaves
menahan gerakan fast line ke arah yang berlawanan , tegangan pada tali
meningkat dari W/n pada sheave pertama (dead line) hinggs W/En pada
sheave terakhir (fast line)
PT PERTAMINA (PERSERO)
PERTAMINA Page 156
Excercise
PT.PDSI’s N80UE rig has rated hook load capacity of 500,000
lbf. The drawworks National N80 can provide an input power to
block and tackle system as high as 1000 HP. Ten lines are
strung between the crown block and traveling block. Calculate :
1. The static tension in the fast line when upward motion is
impending (lbf).
2. The maximum horsepower available (HP).
3. The maximum hoisting speed (ft/min).
4. The time needed to pull a 90-ft stand (min).
5. The actual derrick load (lbf).
6. The maximum equivalent derrick load (lbf).
7. The derrick eficiency factor (%).
8. Minimum hook power the driller must have to pull up a load,
if safety factor = 2.0.
Rig N80UE-Main Component
17. BOP Equipment :
8. Drawwork Type : National • 20” –2.000 psi Type MSP Hydrill
80 UE/1.000 HP • 13 5/8” – 5.000 psi Annular Type Hydrill GK
9. Mast Type : • 7 1/16” – 5.000 psi Annular TypeHydrill GK
Lee C. Moore Cantilever • 13 5/8” – 5.000 psi Ram TypeCameron “U”
142 ft/100 MPH • 7 1/16” – 5.000 psi Ram TypeKoomey
769.000 lbs Static Hook Load • 11” – 10.000 psi GK Hydrill
10. Substructure Type : 18. Accumulator : Koomey 35140 S
Lee C. Moore 21.98 ft SN.5053-280 gall
H 8.7 M (H) x 9.6M (W) x 19.5M (L) 19. Choke : 4 1/16” –5.000 psi
11. AC Generator Set : 20. Drill Pipe : 5” DP, 3 ½” DP, 5” HWDP
Cylon 575KVA, 460KW, 590A, 400V, 50Hz 21. Drill Collar : 8”, 6 ¼”, 4 ¾”
1500Rpm with Engine Cat D 3412 (2 set) 262 KVA, 22. Mud tank volume : 5 x 261.65 bbl
210KW, 379A, 400V, 50Hz,1500 Rpm with Engine 23. Solid Control :
Cat D 343 (2 set) Shale Shaker : 3 Brandt –Cobra,Cap. 600 Gpm
12. DC Generator Set : Model 5 GE 752 T5A with
Engine Cat D 398 (3 unit)
13. Water Pump : National K-180 Douplex
with Engine Cat D 343.
14. Slush Pump Type:
1. National 8P80 / 800 HP with electric motor GE
752
2. National 9P100 / 1.000 HP with Engine Cat D
3512
3. Ideco T.1000 / 1000 HP with Engine Cat D 399.
15. Swivel : National P-400
PT PERTAMINA (PERSERO)
PERTAMINA
16. Rotary Table Type : National C-275 Page 158