Tutorial Chapter 5 Location and Layout Decisions
Tutorial Chapter 5 Location and Layout Decisions
Location Decisions
1.Factor-Rating Method
► Six steps in the method
1. Develop a list of relevant factors called key
success factors
2. Assign a weight to each factor
3. Develop a scale for each factor
4. Score each location for each factor
5. Multiply score by weights for each factor for
each location
6. Make a recommendation based on the highest
point score
Totals 1.00
© 2014 Pearson Education, Inc. 8-6
1. Factor-Rating Example
Calculates the total weighted scores for each location.
TABLE 8.4 Weights, Scores, and Solution
SCORES
(OUT OF 100) WEIGHTED SCORES
KSF WEIGHT FRANCE DENMARK FRANCE DENMARK
Labor availability
.25 70 60 (.25)(70) = 17.5 (.25)(60) = 15.0
and attitude
Education and
.21 60 70 (.21)(60) = 12.6 (.21)(70) = 14.7
health
Totals 1.00 70.4 68.0
The French location (with weighted scores of 70.4 points) is preferable as the total
weighted scores are higher than Denmark (with weighted scores of 68 points)
© 2014 Pearson Education, Inc. 8-7
2. Locational
Cost-Volume Analysis
► Three steps in the method
1. Determine fixed and variable costs for each
location
2. Plot the cost for each location
3. Select location with lowest total cost for
expected production volume
Athens:
Total Cost Athen = 30,000 + 75(x)
Brussels:
Total Cost Brussels= 60,000 + 45(x)
Lisbon
Total Cost Lisbon= 110,000 + 25(x)
–
$110,000 –
–
–
$80,000 –
–
$60,000 –
–
– Athens Lisbon
$30,000 – Brussels
lowest lowest cost lowest
– cost cost
$10,000 |– | | | | | |
0– 500 1,000 1,500 2,000 2,500 3,000
© 2014 Pearson Education, Inc. 8 - 13
Volume
2. Locational Cost-Volume Analysis Example
3. Identified the significance crossover/intersection points
Crossover point – Athens/Brussels
30,000 + 75(x) = 60,000 + 45(x)
30(x) = 30,000
(x) = 1,000
Crossover point – Brussels/Lisbon
60,000 + 45(x) = 110,000 + 25(x)
20(x) = 50,000
(x) = 2,500
For volume of less than 1,000 units Athens would be preferred. For Volume
between 1,000 and 2,500 units Brussels would be preferred. For volume more
than 2,500 units Lisbon would be preferred. Therefore, since the expected
volume is 2,000 units per year, Brussels would be selected as it provides the
lowest cost location with the expected profit of $90,000 per year.
Expected Profit
© 2014 Pearson (Brussels)
Education, Inc. = $120(2,000) - [$60,000 + ($45 x 2,000)]-$90,000
8 - 14
3. Center-of-Gravity Method
► Place existing locations on a
coordinate grid
► Grid origin and scale is arbitrary
► Maintain relative distances
► Calculate x and y coordinates for
‘center of gravity’
► Assumes cost is directly proportional
to distance and volume shipped
åd Q iy i
y-coordinate of the = i
center of gravity åQ i
i
60 – d1x = 30
d1y = 120
30 – Q1 = 2,000
Atlanta (60, 40)
–
| | | | | |
East-West
30 60 90 120 150
Arbitrary
origin
© 2014 Pearson Education, Inc. 8 - 18
3. Center-of-Gravity Method
30 –
Atlanta (60, 40)
–
| | | | | |
East-West
30 60 90 120 150
Arbitrary
origin
Therefore, the new warehouse should be located at coordinates (66.7,93.3) as
illustrated above.
© 2014 Pearson Education, Inc. 8 - 20
Chapter 8 & 9 of Heizer and Render (2014)
Layout Decisions
4. Process Layout Example
Walters Company management want to
arrange the six departments of its factory in
a way that will minimise interdepartmental
material handling cost. They make an initial
assumption that each department is 20 x 20
feet and the building is 60 feet long and 40
feet wide.
Walters Company assumes that a forklift
carries all interdepartmental loads. The
cost of moving one load between adjacent
departments is estimated to be $1. Moving
a load between non-adjacent departments
costs $2.
© 2014 Pearson Education, Inc. 9 - 22
4. Process Layout Example
Procedures:
1. Construct a “from-to matrix”
2. Determine the space requirements
3. Develop an initial schematic diagram
4. Determine the cost of this layout
5. Try to improve the layout
6. Prepare a detailed plan
Painting (2) 30 50 10 0
Receiving (4) 50 0
Shipping (5) 0
Testing (6)
40’
Receiving Shipping Testing
Department Department Department
(4) (5) (6)
Area
© 2014 Pearson Education, Inc. D 60’E
Area Area F 9 - 25
* Called as the initial layout
4. Process Layout Example:
initial layout
Interdepartmental Flow Graph (sequence of parts move)
Figure 9.6
100
10
100
50 100
40’
Receiving Shipping Testing
Department Department Department
(4) (5) (6)
30
20
10
Figure 9.10
0
Assemble Paint Test Label Pack for
shipment
© 2014 Pearson Education, Inc. Operations 9 - 34
5. Staffing Work Cells
Example
600 Mirrors per day required
Mirror production scheduled for 8 hours per day
From a work balance
chart total operation
time = 140 seconds
E 11 A
F 3 C, D
G 7 F
H 11 E
I 3 G, H
Total time 65
5
C
10 11 3 7
A B F G
4 3
D I
11 11
E H
G 7 F
A B F G
4
3
H 11 E D
11 11 I
I 3 G, H
E H
Total time 65
3/26/2018
TABLE 9.2 Component per day
ASSEMBLY TASK MUST
TIME FOLLOW TASK
40 units required
TASK (MINUTES) LISTED BELOW Cycle time = 12 mins
A 10 –
Minimum
B 11 A
workstations = 5.42 or 6
Figure 9.12
C 5 B
5
D 4 B
∑ Task times C
E
Efficiency = 11 A 10 11 3 7
(Actual number of workstations) x (Largest Assigned cycle time)
(of the balanced line) A B F G
F 3 C, D 4
3
= 65 minutes / ((6 stations) x (12 minutes))
G 7 F D I
11 11
= 90.3%
H 11 E E H
Or 1- %Idle Time (of the balanced line)
I 3 G, H
Therefore, 6 workstations recomended with expected efficiency of 90.3%
Total time 65
The End