EE462 Second Part
EE462 Second Part
3.1 Introduction
The primary function of a power station is to serve power to a large number of consumers.
Nevertheless, the power needs of consumers are subjected to change depending upon their
actions.
As a consequence of this variance in demand, the load on a power station is never constant,
rather it shifts with time. Due to this reason modern power plant faces a lot of complexities.
We cannot store electrical power and, consequently, the power station must create power as
and when required to meet the demands of the consumers.
On one hand, for maximum efficiency, it is important to run the alternators in the power
station at their rated capacity and on the other hand, the requirements of the consumers
have wide variances.
A device that uses electrical energy is said to impose a load on the system.
•Commercial load—lighting for shops, fans, and electric appliances used in restaurant
The load on the power station changes with time due to uncertain and variable demands of
the consumers and is known as variable load on the station.
Effects of Variable Load
Consider a steam power station. Air, coal, and water are the raw materials for this plant. In
order to produce variable power, the supply of these materials will be required to be varied
correspondingly. For instance, if the power demand on the plant increases, it must be
followed by increased flow of coal, air, and water to the boiler in order to meet the increased
demand. Therefore, additional equipment has to be installed to accomplish this job.
The variable load on the plant increases the cost of production of electrical energy. An
alternator operates at maximum efficiency near its rated capacity. If a single alternator is
used, it will have poor efficiency during period of light loads on the plant. Therefore, in actual
practice, a number of alternators of different capacities are installed so that most of the
alternators can be operated at nearly full-load capacity.
However, the use of a number of generating units increases the initial cost per kW of the plant
capacity as well as floor area required. This leads to the increase in production cost of energy.
Connected Load
Connected load is the sum of continuous ratings of all loads connected to the system.
For instance, if a consumer has connections of five 200 W lamps and plug of 600 W, then
The demand of a system is the load that is drawn from the source of supply at a receiving
terminal averaged over a suitable and specified interval of time.
The load may be given in kW, kilovar (kvar), kilovoltampere (kVA), or ampere (A).
Demand Interval
1.Instantaneous demand
Instantaneous demand is not very important because all the machines are designed for
overloads.
The sustained intervals are generally taken as 15 min, 30 min, or even longer.
Demand Factor (DF)
Ratio of the actual maximum demand of the system to the total connected load of the
system.
Average Load or Average Demand
The average load occuring on the power station in a given period (day, month or year) is
know as average load or average demand
Load Factor (LF)
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑
LF =
𝑀𝑎𝑥. 𝐷𝑒𝑚𝑎𝑛𝑑
The ratio of the individual sum of maximum demands to the maximum demand on power
station.
A power station supplies load to various types of consumers whose max demands
generally are not same at the same time. Therefore, the max. Demand on the power
station is always less than the sum of max. İndividul demands of the consumers.
Plant Capacity Factor
Ratio of actual energy produced to the maximum possible energy that could have been
produced during a given period.
The plant capacity factor is a measure of the reserve capacity of the plant. A
power station must be designed in such a way that it has some reserve capacity
for meeting the increased load demand in future. Therefore, the installed capacity
of the plant is always somewhat greater than maximum demand on the plant.
Ratio of kWh generated to the product of the plant capacity and the number of hours
for which the plant was in operation.
7.35x106
Plant Use Factor = 20x103 𝑥 2190 = 0,167 = 16,7 %
Loss Factor
Ratio of the average power loss to the peak load power loss during the specified period of
time.
Load curve is a graphical representation between load (in kW or MW) and time (in
hours).
The curve showing the variation of load on the power station wrt time is known as load
curve (daily, monthy, yearly etc.)
Information Obtained from Load Curves
• The peak load indicated by the load curve gives the max. Demand on the power stations
• The area under the load curve gives the total energy generated in the period under
consideration
• The area under the load curve divided by the total number of hours gives the average
load
• The ration of the area under the load curve to the total area of the rectangle in which it
When the load elements of a load curve are arranged in order of descending magnitudes,
the curve thus obtained is called a load duration curve.
The load duration curve is derived from the load curve and therefore, represents the same
data as that of the load curve but the ordinates are arranged in the order of descending
magnitudes.
Information Available from the Load Duration Curve
A 150 MW power station delivers 150 MW for 2 h, 75 MW for 8 h, and is shut down for the
rest of each day. It is also shut down for maintenance for 50 days each year. Calculate its
annual LF.
Example
A power station has a maximum demand of 20,000 kW. The annual LF is 40%, and plant
capacity factor is 35%. Determine the reserve capacity of the plant
Example
A power plant has maximum demand of 80 MW, an LF of 0.7, plant capacity factor of 0.5,
and plant use factor of 0.9. Find
The peak load on a power station is 60 MW. The load having maximum demand of 30, 20, 15,
and 10 MW are connected to the power plant. The capacity of the power plant is 80 MW and
the annual LF is 0.80. Estimate
Sadhu, Pradip K. Elements of Power Systems. CRC Press, 20160212. VitalBook file.