Design of Drainage System Based On MSMA
Design of Drainage System Based On MSMA
BASED ON MASMA
-COURSE OUTCOMES-
17/04/2018
CONTENTS
1. INTRODUCTION
Guidelines to be used
2. DESIGN CONSIDERATION
Time of concentration
Inlet Time to
Manning’s roughness
Channel Flow Time tf
Minimum tc
Rainfall intensity
Return period
Short duration storm
Runoff coefficient
Calculation worksheet – example
3. DESIGN PROCEDURES
4. ANALYSIS/CALCULATION – EXAMPLES
5. DETAIL DRAWINGS
INTRODUCTION
GUIDELINES TO BE USED :
Manual Saliran Mesra Alam Malaysia
Urban Stormwater Management Manual for M’sia
http://www.water.gov.my
MASMA
1. 40 CHAPTERS
• OPEN DRAN
• CULVERT
• DRAINAGE PIPE
• SILT TRAP
• DETENTION POND
• ETC
DESIGN OF DRAINAGE (SCOPE OF WORK)
1. Site visit : to know the existing site condition
• existing drainage system (type, size, material), existing levels, existing slopes, existing
structures, condition on surrounding area, maximum/minimum flood level, etc
2. Information to be used during site visit :
• key plan, location plan, site plan, architectural plan, survey plan
3. Liaison with local authority/ (Basic data required from local authority for planning &
design of drainage system :
• requirements on submission or guidelines to be followed
• available master plan of the development area, history on the flood level, maximum &
minimum flood level, rainfall intensity, enquiring for existing suitable discharge point with an
appropriate level,
4. Design : use all the information from above for detail design
Refer architectural plan/site plan/location plan/survey plan :
• is there any drainage system stated around the building or outside building?
• identify the possibility of discharge point (check the level)
• identify the starting point of the drainage system, proposed the most suitable alignments of
the drainage system so that the water from the proposed building/project/surrounding area can
be discharged or connected to the proposed discharge point. (check the proposed
platform/road level)
• refer design consideration
• prepare drainage calculation
• prepare drainage layout plan
• prepare drainage detailing
DESIGN CONSIDERATIONS
Time of Concentration
tc = t0 + tf Refer MSMA Sec.14.4
Upstream divide
t0
• t0 = overland flow time (inlet time)
• tf = channel flow time tf
(MSMA Sec.14.4.2(C))
In urban drainage, inlet time is primarily roof drainage
flow time which is very small and considerably uncertain
– hence, a minimum of 5min may be adopted.
Manning’s roughness
Channel Flow Time tf
MSMA Eq. 14.4 a & b (Manning’s eq.)
Fc L
tc
A1/10 S 1/ 5
where t = tc
a,b,c,d are constants obtained from Appendix 13.A
MSMA Appendix 13.A
Return Period
(Annual Recurrence Interval, ARI)
Short Duration Storm
MSMA Section 13.2.7
Table 13.3
2
P24 (mm)
Duration
(min) West Coast East Coast
<100 120 150 >180 All
5 2.08 1.85 1.62 1.40 1.39
10 1.28 1.13 0.99 0.86 1.03
15 0.80 0.72 0.62 0.54 0.74
20 0.47 0.42 0.36 0.32 0.48
30 0.00 0.00 0.00 0.00 0.00
1.0
0.9
Runoff Coefficient
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0.9
0.8
0.7
0.6
0.5
0.1
0
200 300 400
tcritical = (tc)max Refer MSMA Sec.14.4.2
1. Estimate tc
2. Determine I
3. Determine C
4. Calculate Qp A
5. Design drain tf
t0
B tc = t0
tf
C t0
D
tf tf
tc1 , tc2
E t0 = tcritical
tc
Qp = C I A
Moving downstream,
tc (hence t) , I , A A
tf = 4min
Qp
t0 = 5min
B
t0t=
c =9min
9min
tf = 4min
t0 = 5min
D C
tf = 6min tf = 4min
tc1 = 13min
E tc2 = 9min
tc = 19min t0 = tcritical = 13min
DEPTH OF OPEN DRAIN
CLAUSE 26.3.3 (MSMA)
The maximum depth for lined open drain shall be as follows:
[1]
m
Length
[2]
Location
Return Period
yr
[3]
Sub-area
ha
Catchment
Overland flow
[6]
min
Drain time
[7]
min
Time of
Flow time
[8]
min
concentration
Critical Time of
[9]
min
Concentration
Intensity
[10]
mm/h
Runoff Coefficient
[11]
Equivalent Runoff
[12]
Coefficient
Total Equivalent
Rational Method
ha
[13]
Area
Discharge
[14]
m 3/s
Drain Section
MSMA Appendix 16.A.2
[15]
Calculation Worksheet (I)
Gradient
[16]
1 in
Capacity
[17]
m 3/s
Actual Velocity
[18]
m/s
Drain Design
Flow Time
[19]
min
m
Invert Level
[20]
DESIGN PROCEDURES
DESIGN PROCEDURES
The processes generally involve the following steps:
Select the design ARI for minor and major drainage system
Divide sub-catchments into segments of homogeneous land use or
surface slope.
Estimate overland flow time
Estimate flow times for all other flow components within the sub-
catchments such as Kerb gutters, pipe and channels, etc
Calculate yIt, for design ARI of y years and duration t equal to the time
of concentration, from IDF data for area of interest, by using this
equation:-
Ln (yIt) = a + bln t + c(lnt)2 + d (ln t)3
DESIGN PROCEDURES
Calculate yIt, for design ARI of y years and duration t equal to the time
of concentration, from IDF data for area of interest, by using this
equation:-
Ln (yIt) = a + bln t + c(lnt)2 + d (ln t)3
Where yIt = average rainfall intensity (mm/hour) for y ARI and t duration
y = average return interval (ARI)
t = duration (min)
a to d = IDF fitting constant dependent on ARI
Estimate C values for each segment if there are different land covers
by from the design chart 14.3
DESIGN PROCEDURES
Derive design rainfall intensities down to limit 30 minutes. The design rainfall depth
Pd for a storm duration d minute is given:
Pd = P30 –Fd (P60 –P30)
Where, P30 and P60 are rainfall depth for storm duration 30 min and 60 min,
respectively. Fd is the adjustment factor for the storm duration.
(EXAMPLE CALCULATION)
STORMWATER DRAINAGE DESIGN TO MASMA
-EXAMPLE MANUAL CALCULATION-
I= Pd
d
Pd = I x d
= 49.494 mm/hr
For tc = 60 minutes
P60 = I60 x 60/60
= 64.780 x 1.0
= 64.780 mm/hr
TIME OF CONCENTRATION, tc = to (overland) + tch (drain)
= 5.393 minutes
From proposed section;
H = 0.5 m H
B = 0.45 m
S = 1: 250
R = wetted perimeter B
R = A/P
A = 0.5 x 0.45
= 0.225 m²
P = 0.5 m + 0.5 m + 0.45 m
= 1.45 m
R = A/P
= 0.225/1.45
= 0.155 m
TIME OF CONCENTRATION, tc = to (overland) + tch (drain)
V = R⅔ S½ Equation 14.4a
n
= (0.155)⅔ (0.004)½
0.015
= 1.218 m/s
tch = n Lch
60 R⅔ S½
= 0.015 x 120
60 x (0.155)⅔ (0.004)½
= 1.643 minutes
TIME OF CONCENTRATION, tc = to (overland) + tch (drain)
t
Say c = 7 minutes
I = Pt / t
Using tc = 7 minutes, from Table 13.3,by interpolating,
Fd = 1.76
1.28
2.08 x
5 7 10
x = 1.28 – 2.08
7-5 10-5
X = - 0.320
Fd = 2.08 -0.32
= 1.76
Pt = P30 – FD (P60 – P30)
For t = 5 minutes
For t = 7 minutes
Q=CIA
360
= 0.95 X 192.93 X 0.2
360
= 0.102 m³/s
Proposed drain section
Freeboard = 150 mm
H = 0.55 m
(EXAMPLE CALCULATION)
MSMA Section 14.5.3
Assumptions of Rational Method:
• Peak flow occurs when entire catchment is contributing to flow
• Rainfall intensity is the same over the entire catchment
• Rainfall intensity is uniform over a time duration equals to tc
• ARI of the computed flow is the same as ARI of the rainfall intensity
• Catchment area less than 80 Hectares
Solution:
From Table 4.1, minor system (medium density) design ARI = 5
years
Step 1 : Determine, tc
From Design Chart 14.1 for paved surface,
to = 8 minutes
td = L/V
= 400/1.0
= 400 second
= 6.7 minutes (say 7 minutes)
Therefore tc = to + td
= 8 minutes + 7 minutes
= 15 minutes.
STORMWATER DRAINAGE DESIGN TO MASMA
-EXAMPLE CALCULATION-
Step 2 : Determine I and C
For ARI of 5 years, from Table 13.A1, using equation 13.1
for t = 30 minutes;
a = 5.1068, b = 0.5037, c = -0.2155, d = 0.0112
ln I(30) = 5.1086 + 0.5037 ln (30) – 0.2155 (ln 30)2 + 0.0112 (ln 30)3
ln I(30) = 4.7698
I(30) = 117.9 mm/hr
For t = 60 minutes;
ln I(60) = 5.1086 + 0.5037 ln (60) – 0.2155 (ln 60)² + 0.0112 (ln 60)³
ln I(60) = 4. 3271
I(60) = 75.7 mm/hr
STORMWATER DRAINAGE DESIGN TO MASMA
-EXAMPLE CALCULATION-
Intensity = Depth / Duration
I = Pd/d (Equation 13.4)
1
Q 2/3
AR S 1/ 2
n
Use n = 0.015 (Design Chart 26.1)
V = (R)⅔ (S)¹/² EQUATION 14.4a
0.015
= (0.16)⅔ (0.004)¹/²
0.015
= 1.3 m/s (0.6 m/s < V < 4.0 m/s)
Q = VxA
= 1.3 m/s x 0.2475 m²
= 0.3 m³/s (< Q5 = 4.4 m³/s)
Therefore the proposed drain section is not sufficient. Try new drain
section.
DRAINAGE LAYOUT PLAN
EARTHWORK
EARTHWORK LAYOUT PLAN
PROPOSED CONSTRUCTION OF KOLEJ SAINS KESIHATAN AT TANJUNG
RAMBUTAN MUKIM ULU KINTA IPOH PERAK