Total Qty Scheduled Actual (31.08.2016) Actual (15.10.2016) : Payments (Rs. CR.) Remarks

This document provides a status update for repair and maintenance work being conducted at two substations - Gaighat GSS and Rajgir GSS. It lists the name of work, project cost, agency responsible, letter of intent date, scheduled date of completion and project team for each site. It then provides a table comparing scheduled versus actual progress updates for various work components like equipment supply and installation, boundary wall repair, cable trench repair and yard work. Current work status is also noted for each site.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
15 views

Total Qty Scheduled Actual (31.08.2016) Actual (15.10.2016) : Payments (Rs. CR.) Remarks

This document provides a status update for repair and maintenance work being conducted at two substations - Gaighat GSS and Rajgir GSS. It lists the name of work, project cost, agency responsible, letter of intent date, scheduled date of completion and project team for each site. It then provides a table comparing scheduled versus actual progress updates for various work components like equipment supply and installation, boundary wall repair, cable trench repair and yard work. Current work status is also noted for each site.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 2

State Plan (GSS)

1. Name Of Work - R&M of 132/33KV GSS at Gaighat(NIT-48/PR/BSPTCL/2015).


2. Project Cost (Rs Cr) - 18.50
3. Agency - M/s GEPDEC INFRATECH LIMITED, Noida
4. LOI Date - 28.08.2015
5. SDOC -27.08.2016 GAIGHATGSS

6. Likely Date of Completion -30.11.2016


7. Project Team -Sri Chittranjan Roy (ESE) ,Sri Ravi Shankar(EEE) & Sri M.K.Sharma(A.Ex.E)

Total Scheduled Actual Actual Payments ( Rs. Cr.) Remarks


Qty (30.09.2016) (31.08.2016) (15.10.2016)

Fund Fund
Released Pending for
payment
Supply of 100% 100% 80% 95%
Equipments (%)
Repair of boundary 100% 100% 60% 70%
wall(%)
Erection of 100% 100% 55% 60% .
Equipment (%)
Repair of Cable 100% 100% 15% 25%
trench (%)
Yard Levelling work 100% 100% 60% 80%
& PCC
1 Civil Gang at site (PCC done, Gravelling to be done ,Control building under progress)
State Plan (GSS)
1. Name Of Work - R&M of 132/33KV GSS at Rajgir(NIT-48/PR/BSPTCL/2015)
2. Project Cost (Rs Cr) - 18.50
3. Agency - M/s GEPDEC INFRATECH LIMITED, Noida
4. LOI Date - 28.08.2015 RAJGIRGSS
5. SDOC -27.08.2016
6. Likely Date of Completion -30.11.2016
7. Project Team -Sri Chittranjan Roy (ESE) ,Sri Ravi Shankar(EEE) & Sri M.K.Sharma(A.Ex.E)

Total Scheduled Actual Actual Payments ( Rs. Cr.) Remarks


Qty (30.09.16) (31.08.16) (15.10.16)

Fund Fund
Released Pending for
payment
Supply of Equipments (%) 100% 100% 85% 95%

Repair of boundary wall(%) 100% 100% 0% 0% New construction


boundary wall is not in
scope of work.

Erection of Equipment (%) 100% 100% 50% 70%

Repair of Cable trench (%) 100% 100% 5% 5%

Yard Levelling work &PCC 100% 100% 5% 5% .

Civil work 100% 100% NIL 02 %

3 Civil Gang & 1 Electrical Gang at site. (Control Extension Civil Work started for Extension for ULDC Building)