Phase III: Execution Phase IV: Monitoring and Control: Earned Value Analysis
Phase III: Execution Phase IV: Monitoring and Control: Earned Value Analysis
FIGURE 13.1
13–6
Project Schedule Control Chart
FIGURE 13.2
13–7
Important Concepts during Execution
Leadership
Communication
Focus
Tracking
Questions
Would you use a Cost Reimbursement contract in
a situation where the requirements are well known
and nonvolatile?
Would you use a Fixed Price contract in a situation
where the user does not know exactly what he
wants?
If the material requirements are certain, but the
time and effort entailed and requirements are
uncertain, what type of contract would you use?
Freeze Requirements???
What are the PROS?
Procurement management:
Administer Procurements
Controlling Changes to the Project
Schedule
Perform reality checks on schedules
Allow for contingencies??
Don’t plan for everyone to work at 100%
capacity all the time
Hold progress meetings with stakeholders and
be clear and honest in communicating
schedule issues
Execution
Focus and leadership are keys to success in
execution
Poor execution leads to losses in the business
world just as it does in sports
Factors leading to poor Execution
Multitasking—doing several things at once
A finishes
A finishes
B finishes
Cost Control
Project cost control includes
monitoring cost performance
ensuring that only appropriate project changes are
included in a revised cost baseline
informing project stakeholders of authorized changes to
the project that will affect costs
Earned value analysis is an important tool for cost
control
Earned Value Analysis (EVA)
EVA is a project performance measurement
technique that integrates scope, time, and cost
data
Given a baseline (original plan plus approved
changes), you can determine how well the
project is meeting its goals with EVA
You must enter actual information periodically
to use EVA. Figure 6-1 shows a sample form
for collecting information
Glossary of Terms
EV Earned value for a task is simply the percent complete times its original budget. Stated differently,
EV is the percent of the original budget that has been earned by actual work completed.
PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate
of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the
work scheduled].
AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work.
[ACWP—actual cost of the work performed].
CV Cost variance is the difference between the earned value and the actual costs for the work
completed to date where CV = EV – AC.
SV Schedule variance is the difference between the earned value and the baseline line to date where
SV = EV – PV.
BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.
VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.
13–24 TABLE 13.1
Earned Value Analysis Terms
Budgeted cost of work performed (BCWP), also
called earned value, is the percentage of work
actually completed multiplied by the budget for the
activity
Budgeted cost of work scheduled (BCWS), also called
planned value, is that portion of the approved total
cost estimate planned to be spent on an activity
during a given period
Actual cost of work performed (ACWP), also called
actual cost, are the total direct and indirect costs
incurred in accomplishing work on an activity during
a given period
Earned Value analysis--EVA
Earned value = Budgeted Cost of Work Performed
(BCWP)
Planned value = Budgeted Cost of Work
Scheduled (BCWS), and
Actual Cost = Actual Cost of Work Performed
(ACWP)
When you complete an activity, you earn the
budgeted value of that activity
Schedule Variance (SV)—ahead or behind
Defined as the difference between the budgeted
cost of work performed and the budgeted cost of
work scheduled
= BCWP – BCWS = EV - PV
Is also equal to Earned Value (EV) minus Planned
Value (PV)
Indicates the deviation between the work content
performed and the work content scheduled to be
performed for the control period
Cost Variance (CV)—over or under
Defined as the difference between the budgeted
cost of work performed and the actual cost of work
performed
= BCWP – ACWP = EV - AC
Is also equal to Earned Value (EV) minus Planned
Value (PV)
A positive CV indicates a lower actual cost than
budgeted for the control period, while a negative
CV indicates a cost overrun
Schedule Performance Index (SPI)
Defined as the ratio BCWP/BCWS = EV/PV
A value close to 1 indicates an activity that is on
schedule
Values greater than 1 suggest the activity is
ahead of schedule
Values less than 1 indicate a schedule overrun
Cost Performance Index (CPI)
Defined as the ratio BCWP/ACWP = EV/AC
A value close to 1 indicates an activity that is on
budget
Values greater than 1 suggest the activity is
below budget
Values less than 1 indicate a budget overrun
Rules of Thumb for EVA Numbers
Negative numbers for cost and schedule
variance indicate problems in those areas. The
project is costing more than planned or taking
longer than planned
CPI and SPI less than 100% or 1 indicate
problems with cost or schedule
The project is over-budget if CPI < 1
The project is behind schedule if SPI < 1
Figure 6-2. Earned Value Calculations for a
One-Year Project After Five Months
In the Figure above
Budget at Completion = BAC = original budget at the
planned completion date
Time at Completion = TAC = original completion time
In the figure above, $100,000 in month 12
Estimate at completion = EAC = BAC/CPI
Estimate at completion = $100,000/.83 = $120,455
Estimated time to complete = ETAC = TAC/SPI
Estimated time to complete = 12/.96 = 12.55 mos.
Why Earned Value Analysis??
Youcan’t tell what your true cost variance is
because you don’t know where you are relative to
schedule
Suppose you are behind schedule but also you have
spent less than what the schedule has called for. Are
you really under budget?
Updating cost estimates
BAC = Budget at completion = total budget of the
project activities based on the original project plan
Assuming the original budget (the BAC) was
$200,000 and the CPI is 1.12, what is EAC?
EAC = BAC / CPI = $200,000 / 1.12
$178,571
Updating schedule estimates
TAC = Time at completion = total time required to
complete the schedule, as determined by the CP
ETAC = Estimated (revised) time to complete
Assuming the TAC was 12 months and the SPI =
.77, what is the ETAC?
ETAC = TAC / SPI = 12 / .77
15.6 months
Project will be delayed almost 4 months
Updating, Cont’d
WR = Work Remaining = budgeted cost of the
work not yet accomplished by the end of the
reporting period
WR = BAC – BCWP = BAC - EV
EAC = updated estimate of the total project cost =
BAC/CPI = BAC/CI
ETAC = updated estimate of the total project
duration = TAC/SPI = TAC/SI
Figure 6-3. Earned Value Chart for
Project After Five Months
EAC
100,000 BAC
90,000
80,000
70,000
60,000 BCWS
50,000
$
ACWP
40,000
30,000
BWCP
20,000
10,000
-
1 2 3 4 5 6 7 8 9 10 11 12
Month
FIGURE 13.4
13–43
Earned-Value Review Exercise
FIGURE 13.5
13–44
Using Software to Assist in Cost
Management
Spreadsheets are a common tool for resource
planning, cost estimating, cost budgeting, and cost
control
Many companies use more sophisticated and
centralized financial applications software for cost
information
Project management software has many cost-
related features
Using MS Project for Execution &
Control
First,make certain your project plan is complete
and final
Second, save it as a baseline
Begin entering actual information
Actual costs
Percentage complete
Tracking: MS Project will track—
Task start dates
Task finish dates
Task duration
Task cost work
Percentage of task that is complete
Getting Earned Value Data Visible
You can go to view and replace the entry table
with the Earned Value table
Or, you can enter the earned value columns into
your existing table through the Insert Column
facility.
Thecolumns are BCWP, BCWS, ACWP, CV, SC, SPI,
CPI, etc.
You can also request the Tracking Gantt Chart off the
LHS side of MS Project
Entering actual start & Finish dates for
a task
On the view bar, click Gantt chart
In the task name field select the task to update
On the Tools menu, point to tracking and click
Update Tasks
Under Actual, type the dates in the Start and
Finish boxes
Indicating progress on a task as a
percentage
In the task name field of the Gantt Chart
Double click—this brings up the task information
sheet
Select the general tab
In the percentage complete box type a whole
number between 0 and 100
Entering actual costs for a resource
assignment
On the Tools menu, click options, then click the
calculation tab
Clear the Actual costs are always calculated by MS
Project check box
Click OK
On the view bar, click Task usage
On the view menu, point to the Table, and click Tracking
Drag the divider bar to the right to view the Activity Cost
field
In the activity cost field, type the actual cost for the
assignment for which you want to update costs
The End…..
Earned Value analysis--EV An Example
= Budgeted Cost of Work
Performed (BCWP)
Budget
Also uses Budgeted Cost of Work
Scheduled (BCWS), and
Actual Cost of Work Performed Overrun???
(ACWP)
When you complete a milestone, Actual
TIME
James R. Burns, Texas Tech Univeresity James R. Burns, Texas Tech Univeresity
James R. Burns, Texas Tech Univeresity James R. Burns, Texas Tech Univeresity
Recitation
What are two of the four Myers/Briggs
dimensions?
What are the other two?
To what Myers/Briggs category do most IT
professionals belong?
Who is the motivation guru?
What are his five levels?
Who gave us Theory X and Theory Y??