This document outlines the key steps in an oilfield workover project, including: 1. Artificial lift techniques like SRP, ESP, and HPU used to boost production. 2. Use of sonolog tools to measure reservoir properties and help evaluate zones for perforation and production. 3. The planned perforation of specific zones at depths between 676-678m, 873-874m, 914-915m, and 885.5-888.5m, followed by production testing and data measurement. 4. Cementing operations like primary, squeeze, and plug cementing used to isolate zones along with the equipment and materials involved. 5. Production measurement

Uploaded by

yohanes aprinus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views

Presentasi Kerja Praktek: Sangansanga, 31 Oktober 2016

This document outlines the key steps in an oilfield workover project, including: 1. Artificial lift techniques like SRP, ESP, and HPU used to boost production. 2. Use of sonolog tools to measure reservoir properties and help evaluate zones for perforation and production. 3. The planned perforation of specific zones at depths between 676-678m, 873-874m, 914-915m, and 885.5-888.5m, followed by production testing and data measurement. 4. Cementing operations like primary, squeeze, and plug cementing used to isolate zones along with the equipment and materials involved. 5. Production measurement

Uploaded by

yohanes aprinus
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 19

PRESENTASI KERJA PRAKTEK

Sangansanga, 31 Oktober 2016


OUTLINE
1. ARTIFIAL LIFT
2. SONOLOG
3. PERFORATION
4. CEMENTING
5. PRODUCTION
1. Artificial Lift

a. SRP
b. ESP
c. HPU
SRP
ESP
Subsurface Equipment

Surface Equipment
HPU
2. Sonolog
a. Prinsip kerja sonolog/alat
b. Cara kerja Sonolog
c. Hasil yang di dapatkan
3. Perforation
Program workover sumur : ANG-1037
• Squeeze lapisan exiting PHO-4 (676-678)
• Perf menggunakan HSD 4.5” 12 SPF dan
sqeeze cementing pada interval 873-874m dan
914-915m
• Perforation lapisan PHO-15 (885.5-888.5)
dengan menggunakan HSD 4 ½ “ 12 SPF,
lakukan uji produksi dan pengukuran data
• Apabila tidak ada indicator HC pindah
kelapisan PHO-15 dan PHO- 4
4. Cementing
a. Primary cementing
b. Secondary cementing
• squeeze cementing
• cement plug
c. Cementing Equipment
d. Cementing material
Primary cementing
Secondary cementing
Cementing Materials
• Accelerators
• Retarders
• Extenders
• Dispersants
• Fluid loss additives
• Weighting agents
• Silica
• Loss circulation
• Free water control
• Antifoam
• Others special additives
Basic Cementing Calculation

• Slurry yield
• Water required
• Slurry density
Volume dasar yang dihitung
5. Produksi
Pengukuran Kandungan water pada crude oil
Pengukuran Kandungan SG (Spesifik Grafity)