Developing Project Plan
Developing Project Plan
PLAN
DEVELOPING A PROJECT PLAN
• OBJECTIVES
– UNDERSTAND HOW TO DEVELOP A
PROJECT NETWORK
– UNDERSTAND NETWORK COMPUTATION
PROCESS
– BE ABLE TO USE FORWARDS AND
BACKWARDS PASS INFORMATION
DEVELOPING THE PROJECT NETWORK
• TERMINOLOGY:
– Activity – what has to be completed to complete the
project
– Merge activity – more than activity preceding it
– Parallel activities – occur at the same time if need be
– Path – sequence of connected dependent activities
– Critical path – longest path on the network
– Event – point in time when an activity is started or
completed
– Burst activity – more than one activity immediately
following it
CONSTRUCTING A PROJECT NETWORK
TABLE 6.1
Koll Business Center—Partial Network
FIGURE 6.3
Koll Business Center—Complete
Network
FIGURE 6.4
Network Information
TABLE 6.2
Activity-on-Node Network
FIGURE 6.5
Activity-on-Node Network Forward Pass
FIGURE 6.6
Activity-on-Node Network Backward Pass
FIGURE 6.7
Activity-on-Node Network with Slack
FIGURE 6.8
NETWORK COMPUTATION PROCESS