Construction Accounting and Financial Management

The document discusses various methods for managing costs on construction projects including purchasing materials, tracking labor costs, managing subcontracts, equipment costs, and other expenses. It also covers budgeting, tracking actual costs, and calculating metrics to measure schedule and cost performance such as SPI, CPI, and estimates of total costs.

Uploaded by

Wajdi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
750 views25 pages

Construction Accounting and Financial Management

The document discusses various methods for managing costs on construction projects including purchasing materials, tracking labor costs, managing subcontracts, equipment costs, and other expenses. It also covers budgeting, tracking actual costs, and calculating metrics to measure schedule and cost performance such as SPI, CPI, and estimates of total costs.

Uploaded by

Wajdi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 25

Construction Accounting and

Financial Management

Chapter 7
Managing Costs

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Material Purchases

 Purchase orders approved by project


manager
 Supervisor has limited authority to approve
small purchase orders

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Materials Purchases

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Materials Purchases

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Labor Costs

 Hard to control
 Tracked by timecards
 Must be processed quickly

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Labor Costs

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Subcontracts

 Often requires progress payments


 Hard to determine percent complete

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Subcontracts

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Subcontracts

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Equipment

 Hard to control
 Controlled like labor
 Use equipment time cards

 Be sure equipment is returned as soon as the


project is done with it

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Other Costs

 Where possible, use purchase orders


 When a purchase order has not been used,
approval by project manager is required
 For example, for utility bills

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
General Overhead Costs

 Must be managed as aggressively as


construction costs

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Job Profitability

 Update weekly
 Cost to complete
 Estimated cost at completion
 Estimated profit

 Include committed costs even if not tracked in


the accounting system

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Cost Loaded Schedule

 Prepare schedule
 Assign cost to the tasks
 Determine the weekly or monthly costs

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Earned Value

 Measures performance with regards to


 Schedule
 Cost

 Ignores items which do not have a cost


 For example, submittals

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Budgeted Cost of Work Scheduled
(BCWS)
 The expected cost of the work that is
scheduled to be performed during a specific
period of time

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Budgeted Cost of Work Performed
(BCWP)
 The expected cost of the work that is actually
performed during a specific period of time

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Actual Cost of Work Performed
(ACWP)
 The actual cost of the work that is performed
during a specific period of time
 Hard to calculate in a timely matter because
of lag in receiving and processing invoices

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Schedule Performance Index (SPI)

 SPI = BCWP/BCWS
 Measures progress of work
 Results
>1 : Ahead of schedule
=1 : On schedule
<1 : Behind schedule

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Cost Performance Index (CPI)

 CPI = BCWP/ACWS
 Measures control of budget
 Results
>1 : Under budget
=1 : On budget
<1 : Over budget

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Labor Cost Performance Index (LCPI)

 Same as CPI except it only looks only at in-


house labor
 LCPI = BCLP/ACWP
 BCLP = budgeted cost of labor performed
 ACLP = actual cost of work performed

 Measures control of in-house labor costs

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Labor Cost Performance Index (LCPI)

 Results
>1 : Under budget
=1 : On budget
<1 : Over budget

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Total Estimate Cost at Completion

 TEC at C = Total Estimate/CPI


 Assumes CPI will not change

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
SPI/CPI Target levels

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved
Project Closeout Audit

 Validate data
 Find areas where performance was better
than expected
 Learn how to repeat it

 Find areas where performance was worse


than expected
 Learn how to avoid it

Construction Accounting & Financial Management, 3/e © 2013 by Pearson Higher Education, Inc
Steven Peterson Upper Saddle River, New Jersey 07458 • All Rights Reserved