Scheduling and Risk Analysis
Scheduling and Risk Analysis
RISK ANALYSIS
(CPM, PDM, PERT, GERT)
SCHEDULING AND RISK ANALYSIS
2
SCHEDULE RISK ANALYSIS
3
SCHEDULE RISK ANALYSIS
4
SCHEDULE RISK ANALYSIS
5
SCHEDULE RISK ANALYSIS
6
SCHEDULE RISK ANALYSIS
▪ Once you have determined the early and late start and finish dates, you
can determine float. Float is equal to the difference between the late
finish and early finish dates, or the difference between the late start
and early start dates.
9
CRITICAL PATH METHOD
10
CRITICAL PATH METHOD
11
2. PDM
PRECEDENCE DIAGRAM METHOD
PRECEDENCE DIAGRAM METHOD
13
FOUR TYPES DEPENDENCIES
15
DEPENDENCIES DIAGRAM
16
3. PERT
PROGRAM EVALUATION AND REVIEW TECHNIQUE
PROGRAM EVALUATION AND REVIEW
TECHNIQUE
▪ PERT is similar to critical path in that they are both used to
visualize the timeline and the work that must be done for a
project.
18
DURATION ESTIMATES
▪ Realistic time estimate (m): This is the most likely time in which
the activity can be completed under normal circumstances
20
4. GERT
GRAPHICAL EVALUATION AND REVIEW TECHNIQUE
GRAPHICAL EVALUATION AND REVIEW
TECHNIQUE
▪ GERT essentially outdoes limitations associated with PERT/CPM
and allows loops between tasks. GERT is useful particularly in
experiments which demand higher degree of pre-planning and
rescheduling capabilities to maximize the return from the
experimental facilities available.
24
EXAMPLE
25
THANKS!
26