Chapter 4
Chapter 4
Project Management
Projects and Project Managers
4-9
Gantt Chart Fundamentals
List any
Enter Task
resources to
Name Adjust start
Choose task be used
duration and end times
Follow-Along Exercise
4-13
Work Breakdown Structure
• Proceed top-down
• No specific sequence of work
implied
• No need to be symmetrical
• How deep to “break down”?
• Rule: break down until you achieve the
estimation accuracy you desire
Numbering the Boxes
• Each box in the WBS should have a
unique identifier.
Project
1.1 1.2
1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.2.6 1.2.7 1.2.8 1.2.9 1.2.10
1.2.7.1
Example: Reroof a House
1.0 Reroof
House
1.1.1 Measure 1.1.2 Calculate 1.2.1 Purchase 1.2.2 Take 1.3.1 Roof 1.3.2 Roof
Roof Materials Materials Delivery Removal Application
4-18
Project Management Life Cycle
4-19
Joint Project Planning Strategy
4-20
Activity 1 – Negotiate Scope
Scope – the boundaries of a project – the
areas of a business that a project may (or
may not) address. Includes answers to five
basic questions:
• Product
• Quality
• Time
• Cost
• Resources
Milestone – an event
signifying the
completion of a major
project deliverable.
4-24
Activity 3 – Estimate Task
Durations
• Elapsed time takes into consideration:
• Efficiency - no worker performs at 100%
efficiency
• Coffee breaks, lunch, e-mail, etc.
• Estimate of 75% is common
• Interruptions
• Phone calls, visitors, etc.
• 10-50%
4-25
Activity 3 – Estimate Task
Durations
1. Estimate the minimum amount of time it would take to
perform the task – the optimistic duration (OD).
2. Estimate the maximum amount of time it would take
to perform the task – the pessimistic duration (PD).
3. Estimate the expected duration (ED) that will be
needed to perform the task.
4. Calculate a weighted average of the most likely
duration (D) as follows:
4-28
Scheduling Strategies
4-30
Activity 5 – Assign Resources
• People – includes all system owners, users,
analysts, designers, builders, external agents, and
clerical help involved in the project in any way.
• Services – includes services such as a quality
review that may be charged on a per use basis.
• Facilities and equipment – includes all rooms
and technology that will be needed to complete the
project.
• Supplies and materials – everything from pencils,
paper, notebooks to toner cartridges, and so on.
• Money – includes a translation of all of the above
4-31 into budgeted dollars!
Defining Project Resources
4-32
Assigning Project Resources
4-33
Assigning People to Tasks
4-34
Resource Leveling
4-35
Task Splitting and Task
Delaying
• Critical path – the sequence of dependent
tasks that determines the earliest possible
completion date of the project.
• Tasks on the critical path cannot be delayed without
delaying the entire project. Critical tasks can only be
split.
• Stages of Team
Maturity
(see figure to the right)
4-37
10 Hints for Project Leadership
1. Be Consistent.
2. Provide Support.
3. Don’t Make Promises You Can’t Keep.
4. Praise in Public; Criticize in Private.
5. Be Aware of Morale Danger Points.
6. Set Realistic Deadlines.
7. Set Perceivable Targets.
8. Explain and Show, Rather Than Do.
9. Don’t Rely on Just Status Reports.
4-38
10. Encourage a Good Team Spirit.
Activity 7 – Monitor and
Control Progress
• Progress reporting
• Change management
• Expectations management
• Schedule adjustments—critical path
analysis (CPA)
4-39
Sample Outline for Progress
Report
I. Cover Page
A. Project name or identification
B. Project manager
C. Date or report
II. Summary of progress
A. Schedule analysis
B. Budget analysis
C. Scope analysis
(changes that may have an impact on future progress)
D. Process analysis
(problems encountered with strategy or methodology)
E. Gantt progress chart(s)
III. Activity analysis
A. Tasks completed since last report
B. Current tasks and deliverables
C. Short term future tasks and deliverables
4-40 (continued)
Sample Outline for a Progress
Report (concluded)
IV. Previous problems and issues
A. Action item and status
B. New or revised action items
1. Recommendation
2. Assignment of responsibility
3. Deadline
V. New problems and issues
A. Problems
(actual or anticipated)
B. Issues
(actual or anticipated)
C. Possible solutions
1. Recommendation
2. Assignment of responsibility
3. Deadline
VI. Attachments
4-41 (include relevant printouts from project management software)
Progress Reporting on a Gantt
Chart
4-42
Change Management
Change management – a formal strategy in which a
process is established to facilitate changes that occur
during a project.
The least
important
4-45
Typical, Initial Expectations
for a Project
4-46
Adjusting Expectations
4-47
Changing Priorities
4-48
Schedule Adjustments -
Critical Path Analysis
1. Using intertask dependencies, determine every
possible path through the project.
2. For each path, sum the durations of all tasks in
the path.
3. The path with the longest total duration is the
critical path.
• The critical path is the sequence of tasks with the
largest sum of most likely durations. The critical
path determines the earliest completion date of
the project.
• The slack time for any non-critical task is the
amount of delay that can be tolerated between
starting and completion time of a task without
causing a delay in the entire project.
4-49
Critical Path Analysis
4-50
Activity 8 – Assess Project
Results and Experiences