Estimation & Quantity Surveying: by - Prof. Ravindra Shrivastava School of Distance Education NICMAR, Delhi NCR
Estimation & Quantity Surveying: by - Prof. Ravindra Shrivastava School of Distance Education NICMAR, Delhi NCR
SURVEYING
DRAWINGS
SPECIFICATION
RATES
DRAWING
Fully dimensioned and to the scale drawings are
required for finding dimensions while doing
measurements
PLAN
AT A SCALE OF 1 CM = 1 METRE
DETAILED DRAWINGS
AT A SCALE OF 1 CM = 20 CM
SPECIFICATION
GENERAL SPECIFICATIONS
DETAILED SPECIFICATIONS
RATES
CARRAIGES
MEASUREMENT
UNITS OF MEASUREMENTS
Sub heads :
Earth work
Concrete
Brick work
Steel and Iron work
Stone masonry
Roofing
Flooring
Wood work
Finishing
painting
Dismantling and demolishing works
HEAD : BUILDING
EARTH WORK : (L X B X H = M3)
Measurement of earth work is done in M3.
Measurement shall be taken as the area of the bottom of
foundation trench multiplied by depth of foundation as give
in plans.
When excavation is in fairly level ground than depth can be
measured from “Dead Man” or “Tell Tales” left out during
excavation.
G PLAN L
TELL TALE
ROCK
CONCRETE : (L X B X H = M3)
e. No deduction shall be made for following :
1. Volume occupied by reinforcement
2. Opening up to 0.1 m2
3.Volume occupied by pipes, conduits etc not
exceeding (100)cm2 in cross section.
4. Small voids not exceeding 40 cm2 in cross section.
5. Chamfers, moldings, grooves up to 10 cm in width
and 15 cm in depth
f. columns shall be measured from top of column base to
underside of first floor slab and then top of floor to
underside of floor slab above.
H
g. Beam shall be measured from face to face of column
1. Depth of beam shall be measured from bottom of
slab to bottom of beam.
2. For inverted beams depth shall be measured from
top of slab to top of beam
NORMAL BEAM
DEPTH OF BEAM
INVERTED BEAM
ROOF COVERING
TERRACE ROOFING :
Flat terrace shall be measured in square meter describing thickness,
size and quality of materials.
Tiles on chajjas and sundries may be measured in square mete
FLOORING : ( L X B = M2 )
Length and width of wooden members shall be measured to nearest 1
cm.
Area calculated to nearest 0.01 M2 and cubic contain 0.001 M3
Wood work used in doors, windows partition panel shall be measured in
superficial unit (one unit).
Doors of bigger sizes are taken separately from smaller size doors as
rate will be different.
Wood work in framed and fixing in position such as wooden battens,
beams, purling in wooden tress are measured in M3.
Boarding shall be described and measured in square meter.
Staircase landing, riser and treads are measured in M2 and hand rails
shall be measured in running meter.
WOOD WORK
Plastering
Plaster shall be classified according to material used and
each type is measured separately, as
a. mix of mortar ( 1:3, 1:4 )
b. no. of coats and thickness of coat.
c. nature of base
d. nature of surface treatment ( neeru, sand face )
Plastering of roof ceiling and walls should be measured
separately
30 cm or below width is measured in running meter and
above in square meter.
All the plaster shall be measured in M2 unless specified.
FINISHINGS : ( unit = m2 )
POINTING :
Various type and proportion of pointing shall be measured
separately.
It should be measured in M2.
Deduction are made same as plastering.
WHITE WASHING, COLOUR WASHING :
All works shall be measured in M2.
Measurement and deduction are same as plastering.
GLAZING :
measurement shall be done in m2.
Different type of glass should be measured separately.
Measurement of glazing in wood and metal is done
separately.
Holes drilled in glass shall be measured in No. stating dia
meter of hole, type of glass.
Grinding, polishing and rounding off edges are measured in
Running meter.
Shall be measured in Square meter.
Type of surface on bases of absorbent like steel ( non-
absorbent), wood (semi-absorbent), bricks, stone, plaster
( absorbent) shall be measured separately.
No deduction is made for 0.5 M2 opening.
In steel work priming coat shall be included with fabrication.
Painting bends up to 10 cm width is measured in running
meter.
Corrugated sheet surfaces are increased as follows for
painting
a. Corrugated sheets 14%
b. Asbestos cement sheet (corrugated) 20%
c. Asbestos cement sheet (semi corrugated) 10%
Painting on Eave gutters, rain water pipe soil and ventilator
and steel pole shall be measured in running meter stating
width.
PAINTING : ( SQ MT)
TYPES OF ESTIMATE
Types of Estimates
a) General Specifications.
b) Detailed specifications.
General specifications :- In general specifications, nature
and class of works names of materials and proportion that
should be used in the various items of works are described.
Only a brief description of each and every item is given. It is
useful for estimating the project.
Without going through the lengthy detailed specifications,
general information for the quantities of materials, nature and
class of work can be known from the general specifications,
but they do not form part of the contract document.
GENERAL SPECIFICATION OF A FIRST CLASS BLDG
Foundation and Plinth: Ist class brickwork in lime mortar or Cement Mortar
1:6 over lime concrete or 1:4:8 of Cement Concrete.
Damp Proof Course:Should be 2.5 cms thk cement concrete 1:11/2:3 mixed
with one kgs of Impermo per bag of cement or other standard water
proofing materials and painted with 2 coats of bitumen.
Superstructure: I st class brickwork with lime mortar or 1:6 cement mortar
. Lintels ver doors and Windows shall be of RCC
Roofing: Shall be RCC slab with an insulation layer and lime concrete
terracing above, supported over R.S.Joists or RCC beams As required. Ht
of rooms shall not be less than 3.7m.
Flooring: Drawing room and dining room floors of mosaic, Bath ,WC and
dado of mosaic (terrazo). Bed rooms coloured and polished of 2.5cms
cement concrete over7.5cms lime concrete polished. Floors of others shall
be 2.5 cms cement concrete over7.5cms lime concrete polished.
Finishing: Inside and outside shall be 12 mm cement lime plastered
.Drawing,dining and bed rooms inside shall be distempered others white
washed 3 coats. Outside shall be coloured snowcem washed two coats over
one coat of white wash.
Doors and Windows: Chaukats shall be seasoned teak wood.Shutters shall
be Teak wood 4.3 cms thk panelled glazed or partly panelled and partly
glazed as required with additional wire gauge shutters. All fittings of
brass. Doors and Windows shall be Varnished or Painted two coats with
high class enamel paint over one coat of priming.Windows shall be provided
with iron gratings or grills.
Detailed Specifications :-
The detailed specifications form a part of the contract document.
Detailed specification for a particular item specify the qualities, quantities
and proportions of materials, and the method of preparation and execution
for that particular item of work in a project.
The detailed specifications of the different items of woks are prepared
separately and they describe what the works should be and how they shall
be executed and constructed.
Physical chemical and electrical tests if any requires for then finished
work to ensure the desired strength or quality are specified in the
detailed specification.
The type of machinery, equipments and special tools and plant their method
of operation when involved during execution are described in the detailed
specification.
The method and duration of protection of finished works as required are
specified in the detailed specification.
This also specify the involvement and responsibility for auxiliary works,
incidental damages etc. during execution of the original work. While
writing the detailed specifications the same order of sequence, as the
work is to be carried out, is maintained.
Engineering departments maintain detail specifications for different
items of work those are followed to carry out works.
Standard Specifications :-
Detailed specifications for different works are drawn up by an engineering
department and printed to serve as a standard guide to the department
and also to refer it in the specification part of a tender paper to avoid
writing the lengthy specifications.
Thus, standard specifications save valuable time, labour, stationary
expenditure and above all eliminates the scope of deviations and mistakes
during preparation of huge number of tender papers through a Divisional
Office.
Special Specification :-
Some items that are covered or works not well covered by the
departmental standard specifications, special specifications for such items
are drawn up by the Engineer-in-Charge, approved and include in the
tender paper under a heading “Special Specifications”.
Open specifications or Manufacturers Specification :-
Open specification re specifications of products of manufacturers which
state both physical and chemical properties and such other information of
the product, but not description of workmanship to be achieve during
construction. The physical properties specify mainly the strength, weight,
thickness or size and such other physical properties of the product. The
chemical properties specify mainly the composition of chemical contents of
the product and precautionary measures if any required for storing the
product.
Advantages and disadvantages of open specifications :-
A) form work :- Form work shall include all forms or moulds required for forming
the concrete which is cast-in-situ, together with all temporary construction
required for their support.
1) Materials for Form work :- Form work shall be plywood, or steel approved by the
Engineer-in-Charge. Timber used for form work shall be easily workable with
nails without splitting and of light weight. It shall be stiff and strong enough
to avoid undue deflection when loaded and not liable to warp when exposed to
sun and rain or wetted casting of concrete.
Form work shall be of rigid construction true to shape an dimensions shown on
drawings. It shall be strong enough to withstand the dead and live loads and
forces caused by ramming and vibrations of concrete and other incidental loads
imposed upon it during and after casting of concrete. It shall be made
sufficiently rigid by using adequate number of braces and ties. To make up any
settlement in the form work either before or during the placing of concrete,
hard wood wedges shall be provided where required.
All form work shall be so constructed as to be removable in sections in the desired
sequence, without damaging the surface of concrete or disturbing other sections.
Forms should be easy to strip after connecting and no price should be keyed into
the concrete. The completed form work shall be approved after inspection by the
Engineer-in-Charge before the reinforcement bars are placed in position.
2) Propping and Centering :- Props used for centering shall be of steel, timber,
posts, ballies or any other material approved by the Engineer-in-Charge. In case
when ballies are used none shall be less than 100mm in diameter measured at mid
length and 80mm at thin end. Ballies shall rest on wooden sole plates of not less
than 40 mm thickness having a minimum bearing area of 0.1 square metre laid on
ground or on 40 x 40 mm thick brick masonry pillars in mud mortar of height not
exceeding 40cm. All props shall further be provided with double wedges between
the sole plates and the props so as to facilitate tightening and easing of shuttering
without causing shock to the concrete.
In case a span exceeds 4.50 metres and height exceeds 3.50 metres
suitable horizontal as well as diagonal bracings shall be provided after accounting
for all forces including action of the wind which may produce lateral forces. In
case the height of centering exceeds 3.50 metres, the props may be provided in
multi-stages. The detail of splicing the props at each stage shall be as per
approved drawing.
Before the casting of concrete is started, the props and wedges shall be
thoroughly checked to see that these are intact. While the casting of concrete is
an progress., at least one carpenter shall keep a constant watch on the props and
take immediate remedial measures, as soon as any of them gets loosened.
iii) Removal of Form Work :- The form work shall be removed avoiding
shock or vibration that may cause any damage to concrete. In a slab and
beam construction, sides of beam shall be stripped first; then the under
sides of slab and lastly the underside of the beam. The period that shall
elapse after the concrete has been laid before undertaking the work of
easing and removal roof centering and shuttering shall be as given below
according to IS 456-1978.
Parts of structure Where ordinary Portland cement is used
forms may be removed after expiry of the following periods :
In case cantilever slabs and beams, the centering shall remain till
structures for bearing down have been erected and have sufficient
strength.
c) Reinforcement :- Mild steel bars shall conform to the I.S. specification, free
from loose rust, dust, loose mill scales, coats of paints, oil or other coatings which
may destroy or reduce bond. It shall be stored in such a way so as to avoid
distortion and to prevent coorosion.
i) Bening of Overlapping :- Bars shall be bent cold, correctly an accurately to the
size and shape as shown on the detailed drawing or as directed by the Engineer-in-
Charge. Preferably bars of full length shall be used. Overlapping of bars, where
necessary, shall be done as directed by the Engineer-in-Charge. The overlaps shall
be staggered for different bars an located at points, along the span, where neither
shear nor bending moment is maximum. Overlapping of bars can be kept apart by
25mm or 1 ¼ times the maximum size of coarse aggregate whichever is greater,
with concrete between them. But where this cannot be done, the overlapping bars
shall be bound together at intervals not exceeding twice the diameter of such bars,
with two stands of annealed steel wire of 0.90 mm to 1.6 mm thickness twisted
tight. In case of mild steel the ends of rods shall be bent in to semi-circular books,
having clear diameter equal to four times the diameter of bar, with a length beyond
the bend equal to four times the diameter of the bar. In case of deformed bars
the books are not required. Welding of bars shall be permitted in lieu of overlap if
approve by the Engineer-in-Charge.
ii) Placing in position :- Reinforcement bars shall be placed ion position as shown in
the drawings. Bars at their points of intersection shall be securely tied together
with two strands of annealed steel wire 0.90 to 1.6 mm thick twisted tight to make
the skeletion of the steel work rigid so that the reinforcement does not get
displayed during the deposition o concrete. Tack welding shall be permitted in lieu
of binding with steel wire if approved by the Engineer-in-charge.
The bars shall be kept in position by the following methods as the case may
be
For beam and slab construction , precast cover blocks in cement mortar 1:2 about 4
x 4 cm section and of thickness equal to the specified cover shall be placed
between the bars and shuttering, to avoid sagging and to maintain requisite cover
of concrete.
For cantilevered and double reinforced beams or slabs the vertical distance
between the horizontal bars shall be maintained by introducing chain spacers or
support bars of steel at 1.0 metre or at shorter spacing to avoid sagging.
For columns and walls the vertical bars shall be kept in position by means of timber
templates with slots accurately cut in them; or with block of cement mortar (1:2)
suitably tied to the reinforcement.
d)Placing of Concrete :-a) Materials for concrete : Same as cement concrete
except the size of coarse aggregate shall be 20 mm unless specially mentioned in
the type of work.
i) Proportioning of concrete : Same as cement concrete 15-24 (b).
ii) Mixing : Concrete shall be mixed by mechanical mixer except or small
quantity when Engineer-in-Charge permits otherwise. Same as item no. 15-24 ©.
iii) Consistency or Workability :- The concrete, which will flow sluggishly into the
forms and around the reinforcement without any segregation of coarse aggregate
from the mortar shall be used. The consistency shall depend on whether the
concrete is vibrated or hand tamped. It shll be determined by slump tests as per
I.S. recommendation.
E ) Placing of concrete :-Pouring into moulds. Placing of concrete shall be
commenced only after the Engineer –in-Charge has inspected the centering,
shuttering and reinforcement as placed and approved the same. Shuttering shall be
taken and free from all saw dust, pieces of wood or other foreign material an shall
be treated as prescribed ion surface treatment for shuttering.
In case of casting of concrete o slabs and beams, wooden planks or cat-walks
supported directly on the centering by means of wooden blocks shall be provided to
convey the concrete to the place of deposition without disturbing the
reinforcement. Labourers shall not be allowed to walk over the reinforcement.
In deep trenches and footings, concrete shall be placed through chutes as
Directed by the Engineer-in-Charge. In case of columns and walls, the shuttering
shall be so adjusted that the vertical drop of concrete is not more than 1.5
metes at a time. During cold weather, with below 4.5 C. temperature, laying of
concrete shall not be done. During hot weather, precaution shall be taken to see
that the temperature of wet concrete does not exceed 38 C. Unless permitted by
the Engineer –in-Charge no concrete shall be laid within half an hour of the closing
time of the day. The time between mixing and placing of concrete shall not exceed
the initial setting time of cement of 30 minutes.
F ) Compaction :- Concrete shall e compacted into a dense mass immediately after
placing by means if mechanical vibrators designed for continuous operations during
the whole period occupied for placing of concrete. The vibrators shall be so
adjusted that the center of vibrations approximates to the center of the mass
being compacted at the time of placing. For certain items, such as roof slab,
depending on the thickness of the members and feasibility of vibrating the same,
the Engineer-in-Charge may permit hand compaction. Hand compaction shall be
done with the help of 16 mm dia steel tamping rod and tamping with wooden
tampers so that the concrete is thoroughly compacted and completely worked
around the reinforcement and into corners of the form work. The layers of
concrete shall be so placed that the bottom layer does not finally set before the
top layer is placed.
Compaction shall be continued until the mortar fills the spaces between the coarse
aggregate and begins to cream up to form an even surface. Needle Vibrators shall
be withdrawn slowly so as to prevent formation of loose pockers in the case of
internal vibrators. The specific instructions of the makers of the particular type
of vibrator used, shall be strictly complied with. Shaking of reinforcement for the
purpose of compaction should be avoided. Compaction shall be completed before
the initial setting starts. Overvibration or vibration of very wet mixes is harmful
and shall be avoided; under vibration is also harmful.
i) Finishing :- In case of roof slabs the top surface shall be finished even and
smooth with wooden trowel, before the concrete begins to set.
Immediately on removal of forms, the R.C.C. work shall be examined by the
Engineer-in-Charge , before any defects are made good. The work that
has sagged or contains honeycombing to an extent detrimental to
structural safety or architectural concept shall be rejected. Surface
defects of a minor nature may be accepted and shall be made good as per
direction of the Engineer-in-Charge. The R.C.C. work shall be done
carefully so that the thickness of plaster required for finishing the
surface is no more than 6mm.
J ) Testing Concrete :- Regular mandatory tests on the consistency and
workability of the fresh concrete shall be done to achieve the specified
compressive strength of concrete. Work tests and slump tests shall be
carried out as per standing practice. Three test specimens shall be made
from each sample for testing at 28 days.