Power System Reliability: Adequacy-Long Term Planning, Procurement Security, Planning Criteria, States of Power System
Power System Reliability: Adequacy-Long Term Planning, Procurement Security, Planning Criteria, States of Power System
PSTI Bengaluru
16th June 2011
Outline of presentation
Adequacy Security
• Protection system
– Selectability: should operate for the conditions intended and
should not for which not intended.
– Dependability: Number of correct operation devided by number of
incorrect operations
in security analysis
Local plant modes Inter area modes Control modes Torsional modes
Load forecasting------long term
• Electric Power Survey (EPS) reports are brought out by CEA once in
five (5) years.
High deviation in peak load estimates for the last two years!!
Electric Power Survey (contd/-)
Load should be unserved in hours when the cost of serving it would exceed
Value Of Lost Load (VOLL). Put algebraically, outage makes sense so long as
VOLL × (Outage Hours) < FA + (VA × (Outage Hours)),
and solving this gives us the answer.
Peaking capacity versus mid-load plant?
2.7 The evacuation system for sensitive power stations viz., Nuclear Power
stations, shall generally be planned so as to terminate it at large load
centres to facilitate islanding of the power station in case of contingency.
2.8 Where only two circuits are planned for evacuation of power from a
generating station, these should be ( as far as possible) two single circuit
lines instead of a double circuit line.
CEA Transmission planning criteria (4)
2.9 Reactive power flow through ICTs shall be minimal. Normally it
shall not exceed l0% of the rating of the ICTs. Wherever voltage
on HV side of ICT is less than 0.975 pu no reactive power shall
flow through ICT.
3.2.1 The profile of annual and daily demands will be determined from past data.
These data will usually give the demand at grid supply points and for the
whole system identifying the annual and daily peak demand.
The system peak demands shall be based on the latest reports of Electric
Power survey (EPS) Committee. ln case these peak load figures are more
than the peaking availability, the loads will be suitably adjusted substation-
wise to match with the availability. The load demands at other periods
(seasonal variations and minimum loads) shall be derived based on the
annual peak demand and past pattern of load variations. From practical
considerations the load variations over the year shall be considered as
under:
• Annual Peak Load
• Seasonal variation in Peak loads (corresponding to high thermal and high hydro
generation)
• Minimum load.
• Off -Peak Load relevant where Pumped Storage Plants are involved or inter-
regional exchanges are envisaged.
CEA Transmission planning criteria (6)
3.2.3 Reactive power (MVAR)
Reactive power plays an important role in EHV transmission system planning and
hence forecast of reactive power demand on an area-wise or substation-wise
basis is as important as active power forecast. ……………………
4.1 Permissible line loading limit depend on many factors such as voltage
regulation, stability and current carrying capacity (thermal capacity) etc.
While Surge Impedance Loading (SIL) gives a general idea of the loading
capability of the line, it is usual to load the short lines above SIL and long
lines lower than SIL (because of the stability limitations). SIL at different
voltage levels is given at Annex -II. Annex-II also shows line loading (in
terms of surge impedance loading of uncompensated line )as a function of
line length assuming a voltage regulation of 5% and phase angular
difference of 30 degree between the two ends of the line. In case of shunt
compensated lines, the SIL will get reduced by a factor k, where
For lines whose permissible line loading as determined from the curve
higher than the thermal loading limit, permissible loading limit shall be
restricted to thermal loading limit.
CEA Transmission planning criteria (9)
Annex-II
CEA Transmission planning criteria (10)
4.2 Thermal loading limits……………………..Annex-III
CEA Transmission planning criteria (11)
5.0 Steady state voltage limits
Note: The step change in voltage may exceed the above limits where
simultaneous double circuit outages of 400 kV lines are considered. In such
cases it may be necessary to supplement dynamic VAR resources at
sensitive nodes.
CEA Transmission planning criteria (12)
5.0 Steady state voltage limits
CEA Transmission planning criteria (13)
6.0 Security Standards
6.2 Steady state operation
iii. In case of large load complexes with demands exceeding 1000 MW the
need for load shedding in the event of outage of a 400 kV Double circuit
line shall be assessed and kept minimum. System strengthening
required, if any, on account of this shall be planned on an individual
case-to-case basis.
iv. The maximum angular separation between any two adjacent buses
shall not normally exceed 30 degrees.
CEA Transmission planning criteria (15)
6.0 Security Standards
6.3 Stability considerations
A. Transient Stability
i. The system shall remain stable under the contingency of outage of single
largest unit.
ii. The system shall remain stable under the contingency of a temporary
single-phase-to-ground fault on a 765 s/c kV line close to the bus
assuming single pole opening of the faulted phase from both ends in 100
msec (5 cycles) and successful reclosure (dead time I sec).
CEA Transmission planning criteria (16)
6.0 Security Standards
6.3 Stability considerations
iii) The system shall be able to survive a single phase-to-ground fault on a
400 kV line close to the bus as per following criteria:
B. Voltage stability
Each bus shall operate above knee point of Q-V curve under normal as
well as the contingency conditions as discussed above in para 6.2.
CEA Transmission planning criteria (17)
6.0 Security Standards
6.3 Stability considerations
8.2 The maximum fault level on any new substation bus should not
exceed 80% of the rated rupturing capacity of the circuit breaker.
The 20% margin is intended to take care of the increase in short-
circuit levels as the system grows. The rated breaking current
capability of switchgear at different voltage levels may be taken as
CEA Transmission planning criteria (22)
8. Sub-Station Planning Criteria
8.4 The capacity of any single sub-station at different voltage levels
shall not normally exceed :
765 kV 2500 MVA
400 kV 1000 MVA
220 kV 320 MVA
132 kV 150 MVA
8.6 A stuck breaker condition shall not cause disruption of more than
four feeders for 220kV system and two feeders for 400 kV
system and one feeder for 765 kV system.
Power system operating states
Normal
Restorative Alert
In extremis Emergency
Power system operating states (2)
• Normal state
– All system variables are in the normal range
and no equipment is being overloaded. The
system operates in a secure manner and is
able to withstand a contingency without
violating any of the constraints.
Power system operating states (3)
• Alert state
– Security level falls below a certain limit of adequacy or if the
possibility of a disturbance increases due to adverse weather
conditions such as the approach of severe storms. All system
variables are still within the acceptable range and all constraints
are satisfied. However the system has weakened to a level
where a contingency may cause equipments to get overloaded
and reach an emergency state. If the contingency is very severe
we could land up directly in the in extremis state (extreme
emergency).
4. Brainstorming session and agenda for the first meeting of 18th EPS
Committee on 27th August 2010 available at CEA website
http://www.cea.nic.in
Discussion………