SP40-Steel Portal Frame
SP40-Steel Portal Frame
Er.T.RANGARAJAN,B.E,M.Sc(struct.engg),F.I.
E,FACCE,LACI,LISSE,LIASE
According to USA President Herbert Hoover, who was an
engineer before he became a politician, said:
The great liability of the engineer …compared to men of
other professions……is that his works are out in the open
where all can see them.
His acts …..step by step …are in hard substances.
He cannot bury his mistakes in the grave like the
DOCTORS.
He cannot argue them into thin air…..or blame the
judge…..like the LAWYERS.
He cannot, like the ARCHITECT, cover his figures with
trees and vines.
He cannot, like the politicians, screen his shortcomings
by blaming his opponents….and hope the people will
forget. The ENGINEER simply cannot deny he did it.
If his works do not work……he is damned.
A design engineer’s responsibility should include
assuring the structural safety of the design,
details, checking shop drawing.
Detailing is as important as design since proper
detailing of engineering designs is an essential
link in the planning and engineering process as
some of the most devasting collapses in history
have been caused by defective connections or
DETAILING. There are many examples explained
in the book" DESIGN AND CONSTRUCTION
FAILURES by Dov Kaminetzky.
Detailing is very important not only for the
proper execution of the structures but for the
safety of the structures.
Detailing is necessary not only for the steel
structures but also for the RCC members as it is
the translation of all the mathematical
expression’s and equation’s results.
GOOD DETAILING IS AS IMPORTANT AS
DESIGN AND PLANNING.
For the RCC members for most commonly used for buildings we can
divide the detailing for
1. SLABS-WITH OR WITHOUT OPENINGS.(RECTANGULAR,CIRCULAR,NON-
RECTANGULAR-PYRAMID SLAB,TRIANGULAR ETC)
-BALCONY SLAB,LOFT SLAB,CORNER SLAB etc
2. BEAMS- WITH OR WITHOUT OPENIGS.(SHALLOW & DEEP BEAMS)
3. COLUMNS.(RECTANGULAR,L-SHAPE,T-SHAPE,
CIRCULAR,OCTAGONAL,CROSS SHAPE etc)
4. FOUNDATIONS.
Detailing for gravity loads is different from the lateral loads specially for
the SEISMIC FORCES.
Apart from the detailing for the above there is a different detailing
required for the Rehabilitation and strengthening of damaged structures.
We will now dwell on the DETAILING OF MEMBERS FOR THE GRAVITY
AND SOME CODAL DETAILINGS AS PER IS CODE IS 13920 AND IS 4326
AS REQUIRED FOR SEISMIC FORCES.
DO’S-GENERAL
1. Prepare drawings properly & accurately if possible label each bar
and show its shape for clarity.
12”
I ¼”dia@12”c/c
1- ¼”dia@12”c/c
Cross section of retaining wall which collapsed immediately after placing of soil
backfill because ¼” rather than 1-1/4” dia. were used. Error occurred because
Correct rebar dia. Was covered by a dimension line.
2. Prepare bar-bending schedule , if necessary.
3. Indicate proper cover-clear cover, nominal
cover or effective cover to reinforcement.
4. Decide detailed location of opening/hole and
supply adequate details for reinforcements
around the openings.
5. Use commonly available size of bars and
spirals. For a single structural member the
number of different sizes of bars shall be kept
minimum.
6. The grade of the steel shall be clearly stated in
the drawing.
7. Deformed bars need not have hooks at their
ends.
8. Show enlarged details at corners, intersections
of walls, beams and column joint and at similar
situations.
9. Congestion of bars should be avoided at points where
members intersect and make certain that all rein. Can
be properly placed.
10. In the case of bundled bars, lapped splice of bundled
bars shall be made by splicing one bar at a time; such
individual splices within the bundle shall be staggered.
11. Make sure that hooked and bent up bars can be placed
and have adequate concrete protection.
12. Indicate all expansion, construction and contraction joints
on plans and provide details for such joints.
13. The location of construction joints shall be at the point of
minimum shear approximately at mid or near the mid
points. It shall be formed vertically and not in a sloped
manner.
DO’S – BEAMS & SLABS:
1. Where splices are provided in bars, they shall be , as far
as possible, away from the sections of maximum stresses
and shall be staggered.
2. Were the depth of beams exceeds 750mm in case of beams
without torsion and 450mm with torsion provide face rein.
as per IS456-2000.
3. Deflection in slabs/beams may be reduced by providing
compression reinforcement.
4. Only closed stirrups shall be used for transverse rein. For
members subjected to torsion and for members likely to
be subjected to reversal of stresses as in Seismic forces.
5. To accommodate bottom bars, it is good practice to
make secondary beams shallower than main beams, at
least by 50mm.
Do’s –COLUMNS.
1. A reinforced column shall have at least six bars of
longitudinal reinforcement for using in transverse
helical reinforcement.-for CIRCULAR sections.
2. A min four bars one at each corner of the column in the
case of rectangular sections.
3. Keep outer dimensions of column constant, as far as
possible , for reuse of forms.
4. Preferably avoid use of 2 grades of vertical bars in the
same element.
DONOT’S-GENERAL:
1. Reinforcement shall not extend across an expansion
joint and the break between the sections shall be
complete.
2. Flexural reinforcement preferably shall not be
terminated in a tension zone.
3. Bars larger than 36mm dia. Shall not be bundled.
4. Lap splices shall be not be used for bars larger than
36mm dia. Except where welded.
5. Where dowels are provided, their diameter shall not
exceed the diameter of the column bars by more than
3mm.
6. Where bent up bars are provided, their contribution
towards shear resistance shall not be more than 50% of
the total shear to be resisted. USE OF SINGEL BENT UP
BARS(CRANKED) ARE NOT ALLOWED IN THE CASE OF
EARTHQUAKE RESISTANCE STRUCTURES.
The building plan DX-3 shows the
slabs in different levels for the
purpose of eliminating the inflow of
rainwater into the room from the
open terrace and also the sunken
slab for toilet in first floor.
The building plan DX-A3 is one in
which the client asked the architect
to provide opening all round.
Refer the 3d
elevation
Different shapes of slabs used in the
buildings. 6”depression for OT &
9” for sunken slabs.
19’-6”
SLABS:
It is better to provide a max spacing of 200mm(8”) for main
bars and 250mm(10”) in order to control the crack width
and spacing.
crack
INCORRECT
Ldt
CLOSE
STIRRUPS
Ldt/2
Ld/2 Ld/2
CORRECT
Ld
NON PRISMATIC BEAM
crack
INCORRECT
Ldt
CLOSE
STIRRUPS
Ldt/2
Ld/2 Ld/2
Ld CORRECT
GRID BEAM
INCORRECT
Close rings
1.5d 1.5d
300
300
d
Main beam
INCORRECT
Secondary beam
Close rings
1.5d 1.5d
300
300
d
60degree
1/4OR INCORRECT
1/5 SPAN
Ld
Ld
LINE OF CRACK
d/2
t
t d/2
1.5d d/2+d/2Cot(t)
CORRECT
continuous beam Span/4 Span/4
Span/4
Span/4 Span/4
incorrect
Span/4 Span/4
1.5d
1.5d 1.5d
correct
CONTINUOUS BEAM
SPAN/4 SPAN/4
SPAN/4
INCORRECT
L1 .15L1 L2
.15L2
CORRECT
NONPRISMATIC
SECTION OF BEAM
CRACK
D
D
D
INCORRECT
CLOSE RING
D
CORRECT
D
CLOSE RING
CANTILEVER BEAM PROJECTING
FROM COLUMN
COLUMN
INCORRECT
NOT LESS
THAN 0.5Ast NOT LESS THAN GREATER OF 0.5L OR Ld
50mm
Ld
0.25Ast
COLUMN
CORRECT Ld/3
SLOPING BEAM
CRACK
Ld
Ld
CORRECT
HAUNCH BEAMS
CRACK CRACK
INCORRECT
Ld Ld
CORRECT
Ld L/8 TO Ld
L/10 L/8 TO
L L/10
STRESSES AT CORNERS C-COMPRESSION
T-TENSION
C CRACK
t
CRACK
c
t
c
SHEAR AND TORSION REIN. IN
BEAMS
Stirrups taken round outermost
bars spacing<=x1
<=(x1+y1)/4
<=300mm
Min 0.2%bd to control deflection as
well as for seismic requ.
INCORRECT
d y1
Skin rein.10dia is D
required when depth 100 to D-n>500mm
exceeds 450mm(0.1% 200mm
x1 CORRECT
b
CANTILEVER BEAM WITH
POINT LOAD
Shear rein.
INCORRECT
2/3d
d Ld
CORRECT
Ld
Extra ties
INCORRECT
opening
crack crack
Closed stps
Closed stps
for d/2
for d/2
Ld
INCORRECT
2”max
CLOSED STPS
U TYPE BARS
Ld
IN TENSION-Ld
CORRECT
SPLICE DETAIL FOR COLUMN
COVER
CLOSE
TIES @S/2 SLOPE 1:6
S-SPACING
CORRECT
INCORRECT
REDUCTION
COLUMN BOTH
SIDES
INCORRECT
SPLICE
SLOPE 1:8 FROM
BEAM BOTTOM 3NO.CLOSE TIES
CORRECT
TERMINATION OF COLUMN BARS INSIDE BEAM
INCORRECT
Ld
CORRECT
*COL.CORE HAS TO
BE CONFINED BY
EQ REGION-BEAM-COL JN-EXTERIOR CIRCULAR OR
RECTANGULAR TIES
IN ACCORDANCE
WITH END REGION
SPACING OF
LATERAL
TIES <=d/2
COL.
END REGION
CORE*
SPACING OF
LATERAL
TIES
<=100mm
END REGION
BEAM COL. JUNCTION-EQ
REGION
INCORRECT CORRECT
SPACING OF
LATERAL
TIES <=d/2 BEAM COL. JUNCTION-EQ
REGION
COLUMN DETAILS IN EQ REGIONS
incorrect
First stirrups correct
50mm from beam
face
END
REGION END REGION-h/6 or D or
450MM whichever is
greater
h
b d
END
REGION END
REGION
INCORRECT
Ld
stp@maxd/2 2d 2d stp@maxd/2
2d Stirrup spacing=d/4 or
100mm or 8dia which
ever is the least
FOOTING-DETAILS(INDEPENDENT)
INCORRECT COLUMN
BARS
STARTER
NATURAL
BARS
G.L
COVER TO
STARTER
Lb
3” SIDE COVER Ldt
Min.300
COVER50mm
Ldt
IF p.c.c below
CORRECT or 75mm
TYPICAL REIN DETAILS OF
INCORRECT HAMMER FOUNDATION BLOCK
CORRECT
Ld
Ld
SECTION OF TRENCH
INCORRECT
CRACK
CORRECT
Ld
Ld
Ld
STAIRCASE-WITH WAIST SLAB
INCORRECT
Extra bar
Ld(min)
Ld(min)
Ld(min)
CORRECT
SLABLESS STAIRCASE
Dist.
Alternate 1
Main bar
Main bar
SLABLESS STAIRCASE
Main bar
L=horizontal span
Alternate 2
A=0.25L
DEVELOPMENT LENGTH OF BARS
FOR A CONCRETE GRADE M20 &STEEL STRENGTH Fy=415
2 10 470.0 376.0
3 12 564.0 451.0
4 16 752.0 602.0
5 20 940.0 752.0
6 22 1034.0 827.0
7 25 1175.0 940.0
8 28 1316.0 1053.0
9 32 1504.0 1203.0
Flange Width
Reinforcement:
• Minimum reinforcement:
• 0.25% of the gross area in longitudinal & transverse direction
• It shall be provided in two curtains, if
• Shear stress > 0.25 √fck
• Wall thickness > 200mm
Diameter:
• Shall not exceed 1/10th of thickness of wall
Maximum Spacing:
Lw/5 or
3 tw or
450mm whichever is less
Where,
Lw =Horizontal length of wall
tw =Thickness of wall web
Reinforcement detail:
• Vertical reinforcement
Shall not be < 0.8%
Shall not be > 6%
Practical upper limit = 4%
Anchorage:
• Anchor near the edges (or)
• Anchor in the confine core of boundary element
Splicing:
• Should be avoided as far as possible in yielding zone
Lateral Ties:
Spacing:
• Shall not exceed 150mm c/c
Seismic inertia forces are transferred through various beams and columns to the ground.
Note
• IS 4326:1976 – Code of practice for earthquake resistant design and
construction of buildings.
Provide adequate toughness and ductility to RCC
buildings
• To resist severe earthquake shocks without collapse.
Steel
provided at each of the top and
bottom face of the member, (Cl.6.2.4)
• At least equal to one-fourth of max. negative moment steel provided at the face
Ast1 Asc3 Ast2
of either joint.Column Column
Beam
Ast3
Top and bottom bars of beam (in an
external joint) – Cl.6.2.5
• Crossties with 900 hook at one end and 1350 hook at other end will be sufficient.
Shear Design by Va Vb Stirrups Spacing of stirrups required Spacing specified Spacing provided
Max. Spacing Min. Spacing
IS 456 (from analysis) 222 kN 219 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 220 mm
Sv = = 220 mm
Vus 0.75d = 414 mm -
300 mm
IS 13920 (from analysis) 222 kN 219 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 135 mm
Sv = = 220 mm
' Vu' Calculation not Vus d / 4 = 138 mm 100 mm
Considered 8 db = 200 mm
IS 13920 329 kN 353 kN 2L- 8 mm 0.87 fy Asv d Not more than Not less than 100 mm
Sv = = 101 mm
' Vu' Calculation Vus d / 4 = 138 mm 100 mm
Considered 8 db = 200 mm
Thespacing of hoops over a length of ‘2d’ at
either end of beam shall not exceed
• d/4
• 8 times the dia. Of smallest longitudinal bar, but not less than 100mm.
First hoop
• At a distance not exceeding 50mm from the joint face.
300mm
Splicing
• Provided only in the central half of the member length.
• Proportioned as a tension splice.
• Hoops provided over the entire splice length at spacing not exceeding 150mm
c/c.
• Not more than 50 % of bars shall be spliced at one section.
Rectangular hoops
• Closed stirrup having 1350 hook with a 10 times dia. extension (but not <
75mm).
Spacing between parallel legs <300mm
• Parallel legs of rectangular hoops shall be provided.
Design
shear force of
columns (Cl.7.3.4)
• Shall be the max. of
Calculated factored shear force as per analysis
and
Factored shear force M ubR
bL
M uby
given
Vu 1.4 , lim , lim
hst
Special confining reinforcement (Cl.7.4)
• Larger amount of transverse reinforcement
required from shear strength considerations.
• Shall be provided
i. Over a length ‘l0’ from each joint face,
towards mid span.
iii. 450mm.
When column terminates into a footing or mat
(Cl.7.4.2)
• Special confining reinforcement shall extend at least 300mm into the footing or
mat.
Whencolumn is
supported on a wall
• Special confining reinforcement shall be
provided over the full height of the
column.
• This reinforcement shall be provided
above the discontinuity for a length =
development length of largest
longitudinal bar.
When column has
significant variation in
stiffness along its height,
(Cl.7.4.5)
• Special confining reinforcement shall be
provided over the full height of the column.