Ch.06 - FIN 322
Ch.06 - FIN 322
1
Chapter Outline
6.1 Why Use Net Present Value?
6.2 The Payback Period Method
6.3 The Discounted Payback Period Method
6.4 The Internal Rate of Return
6.5 Problems with the IRR Approach
6.6 The Profitability Index
6.7 The Practice of Capital Budgeting
2
6.1 Why Use Net Present Value?
Accepting positive NPV projects benefits shareholders.
NPV uses cash flows
NPV uses all the cash flows of the project
NPV discounts the cash flows properly
3
The Net Present Value (NPV) Rule
Net Present Value (NPV) =
Total PV of future CF’s + Initial Investment
Estimating NPV:
1. Estimate future cash flows: how much? and when?
2. Estimate discount rate
3. Estimate initial costs
Minimum Acceptance Criteria: Accept if NPV > 0
Ranking Criteria: Choose the highest NPV
4
Calculating NPV with Spreadsheets
Spreadsheets are an excellent way to compute NPVs,
especially when you have to compute the cash flows as well.
Using the NPV function:
The first component is the required return entered as a
decimal.
The second component is the range of cash flows beginning
with year 1.
Add the initial investment after computing the NPV.
5
6.2 The Payback Period Method
How long does it take the project to “pay back” its initial
investment?
Payback Period = number of years to recover initial costs
Minimum Acceptance Criteria:
Set by management
Ranking Criteria:
Set by management
6
The Payback Period Method
Disadvantages:
Ignores the time value of money
Ignores cash flows after the payback period
Biased against long-term projects
Requires an arbitrary acceptance criteria
A project accepted based on the payback criteria may not have
a positive NPV
Advantages:
Easy to understand
Biased toward liquidity
7
6.3 The Discounted Payback Period
How long does it take the project to “pay back” its initial
investment, taking the time value of money into account?
Decision rule: Accept the project if it pays back on a
discounted basis within the specified time.
By the time you have discounted the cash flows, you might as
well calculate the NPV.
8
6.4 The Internal Rate of Return
IRR: the discount rate that sets NPV to zero
Minimum Acceptance Criteria:
Accept if the IRR exceeds the required return
Ranking Criteria:
Select alternative with the highest IRR
Reinvestment assumption:
All future cash flows are assumed to be reinvested at the IRR
9
Internal Rate of Return (IRR)
Disadvantages:
Does not distinguish between investing and borrowing
IRR may not exist, or there may be multiple IRRs
Problems with mutually exclusive investments
Advantages:
Easy to understand and communicate
10
IRR: Example
0 1 2 3
-$200
0% $100.00 $150.00
4% $73.88
8% $51.11 $100.00
12% $31.13
16% $13.52 $50.00 IRR = 19.44%
NPV
20% ($2.08)
24% ($15.97) $0.00
28% ($28.38) -1% 9% 19% 29% 39%
32% ($39.51) ($50.00)
36% ($49.54)
40% ($58.60) ($100.00)
44% ($66.82) Discount rate
12
Calculating IRR with Spreadsheets
You start with the same cash flows as you did for the NPV.
You use the IRR function:
You first enter your range of cash flows, beginning with the
initial cash flow.
You can enter a guess, but it is not necessary.
The default format is a whole percent – you will normally
want to increase the decimal places to at least two.
13
6.5 Problems with IRR
Multiple IRRs
Are We Borrowing or Lending
Two (or more) mutually exclusive
projects
o The Scale Problem
o The Timing Problem
14
Multiple IRRs
There are two IRRs for this project: Which one should we use
0 1 2 3
80
60
40
100% = IRR2
20
0
-50% -20 0% 50% 100% 150% 200%
Discount rate
-40
-60 0% = IRR1
-80
-100
16
Modified IRR – An Example
Assume a project with the following CFs: (R=15%)
Year CFs Year CFs MCFs FV(Cash Inflows)
0 -15,000 0 -15,000 -16315.0
1 4,000 1 4,000 0 6,996.03
2 5,000 2 5,000 0 7,604.38
3 -2,000 3 -2,000 0
4 7,000 4 7,000 0 8,050.00
5 7,000 5 7,000 29,650.40 7,000.00
MIRR= 12.69%
Cash outflow year 3 (CFs<0) is discounted to the present using the borrowing rate.
All cash inflows (CFs>0) are compounded to the last year using the investing rate.
We assume borrowing and investment rates are equal to required return
We compute MIRR using the following formula:
18
The Scale Problem
Would you rather make 100% or 50% on your investments?
What if the 100% return is on a $1 investment, while the 50% return is on
a $1,000 investment?
Example: If you are given the choice between the two following investment
opportunities, which one would you chose? Why?
― AED1 dirham now and getting AED1.5 and hour later or
― AED10 and getting AED11 an hour later.
2 1,000 1,000 0
0% 10% 20% 30% 40% 50% 60%
3 1,000 12,000 -2,000
IRR 16.0% 12.9%
-4,000
-6,000
r NPVA NPVB NPVA NPVB
0% 2,000.0 4,000.0
10% 668.7 751.3 For A, Largest CF appears in year 1. For B,
15% 109.3 -484.1 largest CF appears in year 3, which explains
20% -393.5 -1,527.8 why B has higher NPV for lower r, while A has
25% -848.0 -2,416.0 higher NPV for higher r. Timing of CFs affects
30% -1,260.8 -3,177.1 NPV, hence their attractiveness.
35% -1,637.5 -3,833.3
40% -1,982.5 -4,402.3 The preferred project in this case depends
45% -2,299.8 -4,898.5 on the discount rate, not the IRR.
21
50% -2,592.6 -5,333.3
The Timing Problem
$5,000.00 Project A
$4,000.00 Project B
$3,000.00
$2,000.00 10.55% = crossover rate
$1,000.00
NPV
$0.00
($1,000.00) 0% 10% 20% 30% 40%
($2,000.00)
($3,000.00)
($4,000.00)
($5,000.00) 12.94% = IRRB 16.04% = IRRA
Discount rate
22
Calculating the Crossover Rate
Compute the IRR for either project “A-B” or “B-A”
Year CFA CFB CFA - CFB CFB - CFA
0 -10,000 -10,000 0 0
1 10,000 1,000 9,000 -9,000
2 1,000 1,000 0 0
3 1,000 12,000 -11,000 11,000
IRR 16.0% 12.9% 10.55% 10.55%
0
0% 5% 10% 15% 20%
-1,000
-2,000
-3,000
Discount rate
A-B B-A
23
NPV versus IRR
NPV and IRR will generally give the same decision.
Exceptions:
Non-conventional cash flows – cash flow signs change more
than once
Mutually exclusive projects
Initial investments are substantially different
Timing of cash flows is substantially different
24
6.6 The Profitability Index (PI)
Ranking Criteria:
Select alternative with highest PI
25
The Profitability Index
Disadvantages:
Problems with mutually exclusive investments
Advantages:
May be useful when available investment funds are limited
Easy to understand and communicate
Correct decision when evaluating independent projects
26
6.7 The Practice of Capital Budgeting
Varies by industry:
Some firms use payback, others use accounting rate of return.
The most frequently used technique for large corporations is
either IRR or NPV.
27
Example of Investment Rules
Compute the IRR, NPV, PI, and payback period for the
following two projects. Assume the required return is 10%.
0 ($200) ($150)
1 $200 $50
2 $800 $100
3 ($800) $150
28
Example of Investment Rules
Project A Project B
CF0 -$200.00 -$150.00
PV0 of CF1-3 $241.92 $240.80
29
Example of Investment Rules
Payback Period:
Project A Project B
Time CF Cum. CF CF Cum.
CF
0 -200 -200 -150 -150
1 200 0 50 -100
2 800 800 100 0
3 -800 0 150 150
31
NPV Profiles
$400
NPV
$200
$100
$0
-15% 0% 15% 30% 45% 70% 100% 130% 160% 190%
($100)
($200)
Project A
Discount rates
Cross-over Rate Project B
32
Practice of Kl Budgeting
33
Summary – Discounted Cash Flow
Net present value
Difference between market value and cost
Accept the project if the NPV is positive
Has no serious problems
Preferred decision criterion
Internal rate of return
Discount rate that makes NPV = 0
Take the project if the IRR is greater than the required return
Same decision as NPV with conventional cash flows
IRR is unreliable with non-conventional cash flows or mutually exclusive projects
Profitability Index
Benefit-cost ratio
Take investment if PI > 1
Cannot be used to rank mutually exclusive projects
May be used to rank projects in the presence of capital rationing
34
Summary – Payback Criteria
Payback period
Length of time until initial investment is recovered
Take the project if it pays back in some specified period
Does not account for time value of money, and there is an
arbitrary cutoff period
Discounted payback period
Length of time until initial investment is recovered on a
discounted basis
Take the project if it pays back in some specified period
There is an arbitrary cutoff period
35
Quick Quiz
Consider an investment that costs $100,000 and has a
cash inflow of $25,000 every year for 5 years. The
required return is 9%, and payback cutoff is 4 years.
What is the payback period?
What is the discounted payback period?
What is the NPV?
What is the IRR?
Should we accept the project?
What method should be the primary decision rule?
When is the IRR rule unreliable?
36