Chapter 6 Project Scheduling Lagging, Crashing and Activity Networks
Chapter 6 Project Scheduling Lagging, Crashing and Activity Networks
SUPPOSE:
NORMAL ACTIVITY DURATION = 8 WEEKS
NORMAL COST = $14,000
CRASHED ACTIVITY DURATION = 5 WEEKS
CRASHED COST = $23,000
24
25
7.4. Phương pháp – kỹ thuật quản trị thời gian và tiến độ
Xác suất hoàn thành dự án với PERT
Ví dụ: CP of Project X is A-C-F-I-K-L with variance is 0-0.11-0.25-
0.03-0.11 and standard devitation is 0.7071, TE is 15.66 days.
Q: Find the probability to finish the project in 16 days?
If the probability is 95%, find the due date?
Trả lời:
Z = (16–15.66)/0.7071 = 0.48
68.44%
P= 95%=> Z = 1.65
D = 16.83 days