Project Status Report As of May 25, 2019

This progress report provides an update on the construction of a water supply system for resettlement sites in Tacloban North, Philippines, as of May 25, 2019. The project is 50.10% complete physically and has spent 13,549,085.52 of its 74,000,000 budget. It lists project personnel and photos showing ongoing construction of the water treatment plant, including the perimeter fence, reverse osmosis system components, filter tanks, and clarifier and flocculation tanks. Concerns include needing materials and addressing subcontractor billing and payments.

Uploaded by

Davy Aglipa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views

Project Status Report As of May 25, 2019

This progress report provides an update on the construction of a water supply system for resettlement sites in Tacloban North, Philippines, as of May 25, 2019. The project is 50.10% complete physically and has spent 13,549,085.52 of its 74,000,000 budget. It lists project personnel and photos showing ongoing construction of the water treatment plant, including the perimeter fence, reverse osmosis system components, filter tanks, and clarifier and flocculation tanks. Concerns include needing materials and addressing subcontractor billing and payments.

Uploaded by

Davy Aglipa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 23

DESIGN AND BUILD OF WATER SUPPLY SYSTEM FOR ‘’YOLANDA’’ NHA

RESETTLEMENT SITES (TACLOBAN NORTH)

PROGRESS REPORT
As of May 25, 2019

PROJECT COST:74,000,000.00
ACTUAL: 13,549,085.52 Treatment Plant - 50.10% physical accomplishment
PROJECT PERSONNELS @ LMWD PROJECT SITE

RICARDO OBENIETA 1) CAMILO QUIAO


RONALD LASTIMOSO 2) REY PAUL MAGUINSAY
DAVY AGLIPA 3) RICARDO BACAT
RON DIAZ 4) JUNILADO A.PAT
JUNILO NOYNAY 5) EMERITO M.LAMPAUG
FELIX BALANSAG 6) DIOSDADO D.TAGAILO JR.
7) JERRY C.COGAY
BWRO WATER INTAKE
Water treatment plant showing perimeter fence
86% overall completed.
Pending Activity: Concerns:
*Steel Matting Installation *Subcontractor Progress Billing.
*Painting *Perimeters Lighting Matl’s.
*Entrance and Exit Gate
Rear and Front side of perimeter fence
Rear and Left side of perimeter fence
40 Footer Van for Brackish Water Reverse
Osmosis System
- Foundation 100% completed *Pending Activity:
- 100% mounted on its designated area *Framing of Glass Door and Window.
- 1 out of 2 Vans completed Red Brown *Painting of RO Van
Application *Roofing of RO Van.
30 Units of Pressure Vessels and 8 Bag Filters for R.O System with R.O Skid
- ongoing installation of pipes and headers for RO System
Concerns:
*PVC Fittings 6’’dia.x 2 ½’’dia.
*SS Victualic Coupling 2 ½’’dia.
*SS Flange 6’’dia.(Fabricated Materials @ Manila Supplier)
*PVC Elbows 6’’dia.S80
2 Units of High Pressure Pumps for R.O System
100% Installed/mounted
One High Pressure Pump and 4 Bag filters C.I.P SYSTEM
-100% mounted/installed - 3 Bag filters and 1 INCA Drum for CIP System
Concerns: with CIP Skid 100% mounted/installed
PVC Bushing Reducer
Victualic Coupling
30 Units of Pressure Vessels with 210 membranes One INCA Drum and 3 Bag filters for CIP System
for Reverse Osmosis System 100% installed
Concerns:
C.I.P Pump & Motor
Pipes & Fittings
3 MMF Tanks with Manifolds and Concrete Pad/Foundation for R.O System
- Concrete Pad Foundation 100% completed
- Mounting of tanks 100% completed
- 3 sets of manifolds already installed
Rear side of 3 units Multi Media Filter Tanks
Concern:

*PVC Elbow 6’’dia.S80


*Pvc Pipe 6’’dia. S80
*Pebbles 12-18mm
*Pebbles 9-12mm
*Pebbles 4-6mm
MMF pipeline header to RO System 100% completed
3 Sets of laterals for Multi Media Filter tanks
100% installed for R.O. System

Concern:
*Stud Bolts for the Sight Glass
*Air Scouring Materials Pvc S80, 1 ¼’’dia. And Fittings
Right and Left Side of Clarifier Tank Concern:
- Ongoing assembly (73% complete) *MS Plates 6mm x 6’ x 20’ -9 sheets.
- Painting done 1st & 2nd coat, for final coating *Channel Bar 2’’x 6’’x 20’- 10lengths
(blue) *Angle Bar ¼’’ x 2’’ x 2’’
*Lammella Plates.
*Angle Bar 8mm x 4’’x 6’’
*Angle Bar 6mm x 4’’ x 6’’
Front and Rear side of Flocculation Tank Concern:
- Ongoing assembly (92% complete) *B.I.Pipe 1 ¼’’dia.x 6m. S40
- Painting done 1st & 2nd coat, for final coating (blue) *Flat Bar 6mm x 1’’
*Plain Round Bar 16mm
*Pipes and Fittings 200mm size.
R.O Intake Pipe laying (Intake – Plant)
-Excavate and Backfill 100% complete
-Hydro Testing 100% complete
-Flushing and disinfection 100 complete
- Overall 87% completed
Concerns:
*200mm G.I.Pipe x 6meter ,S60
*C.I.Fittings with cement coated.
3 Units of Multi Media Filter tanks for Clarifier System mounted/fixed on its
foundation/concrete pad

- On-going fabrication of its manifolds, pipes and fittings.


Raw & Product tank pad foundation 100% completed
- For Raw and Product tanks mounting
Project Management Unit
OFFICE
CONCERNS:

CONCERNS PROBLEMS ACTION PLANS COMMITMENTS AND DELIVERABLES

1. ECC Application Follow up, and put dedicated


A. CLIENT ASKING ON PERMITTING 2. Water Permit Application person to comply this
3. Construction Permi requirements.
4. Building Permit

B. PRIMARY POWER LINE SUPPLY FOR THE


1. 750 KVA, 3 Phase Transformer
TREATMENT PLANT Provide funds for this items
2. Primary Power Accessories
3. Payment to Leyeco (AP)

C. RAW WATER TANK MATERIALS Utilize materials form other project


1. MS Plates materials not yet served of possible

D. PRODUCT TANK 1. MS Plates materials not yet served Utilize materials form other project
of possible

E. PROGRESS BILLING SUBCON 1. Slow on progress on activity Negotiate terms on local supplier
CONTRACTORS

F. PAYMENTS ON LOCAL SUPPLIER 1. We can't get materials from local supplier Payment

1. Can't withdraw material from pier because of


G. NO HOWLERS high rentals Provision of boom truck
REVISED PERT - CPM
2018 2019 2020
DEC. JAN. FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

GENERAL REQUIREMENT
301 CALENDAR DAYS

SOURCE DEVELOPMENT 7
196 DAYS 275 352

GENERAL SOURCE
DEVELOPMENT DEMOBILIZATION
REQUIREMENT
(MOBILIZATION)
0 1 2 PIPELINES 14 15
0 0 49 DAYS 49 49
30 DAYS
79 79 273 DAYS 352 352 380 380

28 DAYS

SUSPENDED 3 BRIDGE CROSSING 12


79 296 247 352
168 DAYS

4 CIVIL WORKS 10
79 296 56 DAYS 135 352

ELECTRO
5 MECHANICAL 11
79 296 56 DAYS 135 352

ELECTRICAL
8 WORKS 13
79 296 56 DAYS 135 352

LEGEND : ACTIVITY
ORIGINAL CONTRACT DURATION : 365 CALENDAR DAYS
CONTRACT TIME INCLUDING EXTENSION : 380 CALENDAR DAYS
CRITICAL PATH
NETWORK
0 PROJECT STARTED : DECEMBER 7, 2018
0 0 REVISED COMPLETION DATE : DECEMBER 23, 2019
DUMMY EARLY START EARLY FINISHED