Project Status Report As of May 25, 2019
Project Status Report As of May 25, 2019
PROGRESS REPORT
As of May 25, 2019
PROJECT COST:74,000,000.00
ACTUAL: 13,549,085.52 Treatment Plant - 50.10% physical accomplishment
PROJECT PERSONNELS @ LMWD PROJECT SITE
Concern:
*Stud Bolts for the Sight Glass
*Air Scouring Materials Pvc S80, 1 ¼’’dia. And Fittings
Right and Left Side of Clarifier Tank Concern:
- Ongoing assembly (73% complete) *MS Plates 6mm x 6’ x 20’ -9 sheets.
- Painting done 1st & 2nd coat, for final coating *Channel Bar 2’’x 6’’x 20’- 10lengths
(blue) *Angle Bar ¼’’ x 2’’ x 2’’
*Lammella Plates.
*Angle Bar 8mm x 4’’x 6’’
*Angle Bar 6mm x 4’’ x 6’’
Front and Rear side of Flocculation Tank Concern:
- Ongoing assembly (92% complete) *B.I.Pipe 1 ¼’’dia.x 6m. S40
- Painting done 1st & 2nd coat, for final coating (blue) *Flat Bar 6mm x 1’’
*Plain Round Bar 16mm
*Pipes and Fittings 200mm size.
R.O Intake Pipe laying (Intake – Plant)
-Excavate and Backfill 100% complete
-Hydro Testing 100% complete
-Flushing and disinfection 100 complete
- Overall 87% completed
Concerns:
*200mm G.I.Pipe x 6meter ,S60
*C.I.Fittings with cement coated.
3 Units of Multi Media Filter tanks for Clarifier System mounted/fixed on its
foundation/concrete pad
D. PRODUCT TANK 1. MS Plates materials not yet served Utilize materials form other project
of possible
E. PROGRESS BILLING SUBCON 1. Slow on progress on activity Negotiate terms on local supplier
CONTRACTORS
F. PAYMENTS ON LOCAL SUPPLIER 1. We can't get materials from local supplier Payment
GENERAL REQUIREMENT
301 CALENDAR DAYS
SOURCE DEVELOPMENT 7
196 DAYS 275 352
GENERAL SOURCE
DEVELOPMENT DEMOBILIZATION
REQUIREMENT
(MOBILIZATION)
0 1 2 PIPELINES 14 15
0 0 49 DAYS 49 49
30 DAYS
79 79 273 DAYS 352 352 380 380
28 DAYS
4 CIVIL WORKS 10
79 296 56 DAYS 135 352
ELECTRO
5 MECHANICAL 11
79 296 56 DAYS 135 352
ELECTRICAL
8 WORKS 13
79 296 56 DAYS 135 352
LEGEND : ACTIVITY
ORIGINAL CONTRACT DURATION : 365 CALENDAR DAYS
CONTRACT TIME INCLUDING EXTENSION : 380 CALENDAR DAYS
CRITICAL PATH
NETWORK
0 PROJECT STARTED : DECEMBER 7, 2018
0 0 REVISED COMPLETION DATE : DECEMBER 23, 2019
DUMMY EARLY START EARLY FINISHED