PM Time Management
PM Time Management
Management
(14)
Project Time Management
.2 Activity Attributes
Activity identifier, activity code, activity
description, predecessor activities, successor
activities, logical relationships, leads and lags,
resource requirements, imposed dates,
constraints, and assumptions.
Output, (Activity Definition)
.3 Milestone List
A list of the schedule milestone (mandatory or
optional)
.4 Requested Changes
Any new activities that was approved by the
Integrated Change Control Process
Activities Sequencing 6.2
A G
Start B F Finish
C D E
Tools and Techniques , (Activities
Sequencing)
.2 Arrow Diagramming Method (ADM):.
Activities are represented by arrows (Activity on
Arrow, AOA) and the circle shows the activity
duration, uses only Finish to Start relationships,
and dummy activities
F I
2 3 1
K
A
B L E
Start 2 4 End
G N
1
C J
5
Tools and Techniques , (Activities
Sequencing)
.3 Schedule Network Templates
Standardized project schedule network diagram templates
are used to expedite the preparation of the entire network,
(sub-network are used for repetitive group of activities)
.4 Dependency Determination
Mandatory dependencies, discretionary
dependencies, and external dependencies
.5 Applying Leads and Lags
Leads and lags are applied to accurately define the logic
relationship, and are documented
Outputs
(Activities Sequencing)
.1 Project Schedule Network Diagram
See PDM and ADM, either one can be utilized for
developing the entire network
.2 Activity list (updates)
.3 Activity attributes (updates)
.4 Requested changes
Some changes to the activities may be required
during the process, they have to be documented
and approved
Activities Resource 6.3
Estimating
Inputs
Tools & Techniques Outputs
Enterprise Environmental 1. Expert Judgment 1. Activity Resource 1.
Factors Alternative Analyses 2. Requirements
Organizational Process assets 2. Published Estimating Data 3. Activity attributes (updates) 2.
Activity List 3. Project management 4. Resource Breakdown 3.
Activities Attributes 4. Software Structure
Resource Availability 5. Bottom-up Estimating 5. Resource Calendar (updates) 4.
Project management Plan 6. Requested changes 5.
Inputs, (Activities Resource Estimating)
.1 Enterprise Environmental Factors
(Covered)
.2 Organizational Process assets (Covered)
.3 Activity List (Covered)
.4 Activities Attributes (Covered)
.5 Resource Availability (Covered)
.6 Project Management Plan (Covered)
Tools & Techniques, (Activities
Resource Estimating)
.1 Expert Judgment
The experienced employees in the organization,
and out of the organization experts or
consultants
.2 Alternative Analyses
Explore different methods of construction( Hand Tools vs.
Machinery, Make or Buy decisions, resources skills, etc.)
.3 Published Estimating Data
There many information sources for unit cost,
production rates, labor cost, etc. “Means” is an
example
Tools & Techniques, (Activities
Resource Estimating)
.4 Project Management Software
There are several software packages that are
customized for project management use such as;
Microsoft Scheduler, Primavera, etc.
.5 Bottom-up Estimating
We can get better estimates when the scheduled
activities broken down to lower levels. It allows
us to estimate each activity resources
requirements separately, then we can aggregate
the estimates into a total estimate. It’s a useful
method for large scale projects
Outputs, (Activities Resource
Estimating)
.1 Activity Resource Requirements
Identification and description of the types and quantities of
resources required for each scheduled activity in a work
package
.2 Activity attributes (updates)
.3 Resource Breakdown Structure (RBS)
A hierarchical structure of the identified resources by
resource category and type
.4 Resource Calendar (updates)
Working days and non-working days for each type of
resource and availability periods
.5 Requested changes
Activities Duration 6.4
Estimating
.1 Project Schedule
It contains project schedule network diagram, bar charts,
and milestone charts
.2 Schedule Model Data(updates)
Activity Activity Orig Rem % Early Early Late Total Resource Budgeted 1999 2000 2001
JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAYJUN
ID Description Dur Dur Start Finish Finish
Start
Float Cost
+ Procurement Phase
238 224 5 07SEP99A 15AUG00 35 244,427.60
+ Installation Phase
139 139 4 10AUG00 23FEB01 0 68,233.50
MGT Reserve
PM BASELINE
100
40
80
15
20
35
WBS ELEMENT
COST ACCOUNT
10 Work
Packages
20
Planning
WBS
ELEMENT
Organization
WORK
PACKAGES
WORK PACKAGE
WP No: ORG. No:
TASK DESCRIPTION:
Budget Amount:
Budget for 3 work packages scheduled to be accomplished - 28
Budget for 1 work package scheduled to be in-process - 6
BCWS - 34
8
14
12
12
BCWS : 34 10
Budget for 2 work packages scheduled completed - 14
Budget for 3 work packages scheduled in-process - 19
BCWP - 33
14
12
12
BCWS : 34 10
BCWP : 33
VARIANCE : -1
BUDGETED COST
FOR WORK 34
SCHEDULED
(BCWS) SCHEDULE
VARIANCE
BUDGETED COST
FOR WORK 33
PERFORMED
(BCWP) COST
VARIANCE
ACTUAL COST
FOR WORK 35
PERFORMED
(ACWP)
Material Costs
Material Order
Material Consumed
TIME
ANALYSIS
DEVELOP ESTIMATED COSTS AT COMPLETION
ESTIMATED COST AT COMPLETION
100 100
ACWP
50 50
BCWS
BASE LINE
BCWP
EARNED VALUE TIME OVERRUN
0 6 12
TIME
FUNCTIONAL RESPONSIBILITY
WORK PLANNING AND ASSIGNMENT
COST COLLECTION
BCWS-BCWP DETERMINATION
VARIANCE ANALYSIS
COST ELEMENT DELINEATION
CORRECTIVE ACTION
DATA SUMMARIZATION – WBS/FUNCTIONAL
CSCSC BENEFITS
1. CONFIDENCE IN CONTRACTOR’S INTERNAL
MANAGEMENT SYSTEM
A- Shorter
B- Longer
C- More responsive to needs
D- A & C
E- B & C
A: Longer
Question # 4
A plan has budgeted three weeks of
consultant effort, but the job was done in two
weeks, calculate the variance:
A- 1.5%
B- 33%
C- 75%
D- 67%
E- None of the above
A- -$100
B- $100
C- -$150
D- $150
E- 85%
C: -$150
Question # 6
Fast tracking means to:
E: 14 days
Question # 7
FORWARD PASS
Question # 7
BACKWARD PASS
Question # 8
Activity 3-6 reduced to 5 days; how long will the project takes
to complete, and name the critical path:
A- 10 days
B- 11 days
C- 12 days
D- 13 days
E- 14 days
3d
2 3 5d
3d
6
1
5 2d
8d 4
3d
Question # 8
FORWARD PASS
Question # 8
BACKWARD PASS
Question # 9
HOW MANY PATHS ARE THERE?
Question # 10
WHAT IS THE LENGTH OF THE CP?
FORWARD PASS….
Question #10
WHAT IS THE LENGTH OF THE CP?
BACKWARD PASS….
Question # 11
WHAT IS THE EXPECTED FINISH DATE?
Question # 12
WHAT IS THE FLOAT FOR ACTIVITY C?
Question # 13
WHAT IS THE LATE FINISH FOR
ACTIVITY E?
Question # 14
IF THERE IS AN IMPOSED DATE FOR
FINISHING THE PROJECT IN 25 DAYS,
WHAT IS THE TOTAL FLOAT OF THIS
PLAN?
Question # 15
WHEN WILL ACTIVITY ‘C’ FINISH?
A 5 B FS 2
B 7 C FS 4
C 6
A. END OF DAY 19
B. END OF DAY 20.
C. END OF DAY 16
D. END OF DAY 18
GRAPHICAL SOLUTION
ACTIVITY DURATION SUCCESSOR RELATIONSHIP LEAD LAG
A 5 B FS 2
B 7 C FS 4
C 6
A. END OF DAY 19
B. END OF DAY 20.
C. END OF DAY 16
D. END OF DAY 18
Q & A