Mock PMP Test
Mock PMP Test
1
2. In which document would you find the code of account identifier,
description of work, responsible organization:
A. Scope Statement
B. WBS Dictionary
C. PERT/Charts
D. Responsibility Assignment Matrix
2
3. All the following statements relating to Project Management Staff and the
project team are accurate EXCEPT:
A. Buy
B. Build
C. Neither build, nor buy
D. Need more information on suppliers to make a decision
Answer: A Explanation: If you buy, the cost is: $ 80,000 + $ 1,000 = $ 81,000,
If you build, the cost is: $ 4,000 x 7 x 3 + $ 2,000 = $ 86,000. So, in this
situation, it is preferable to buy.
4
5. Which of the following would not be helpful in performing the Develop
Schedule Process?
5
6. In the context of the communication model, all the following statements
are correct EXCEPT:
6
7. The government has mandated that you ensure the neighborhood is not
adversely impacted by your project. For your project, this directive is
regarded as a/an:
A. Assumption
B. Ethical practice
C. Constraint
D. LEAN
7
8. You are estimating schedule activity costs by determining the unit cost
rates, e.g., staff costs per hour. All the following could be used to determine
resource cost rates EXCEPT:
8
9. You are performing the Control Risks process, and are on the lookout for
indications that a risk has occurred or is about to occur. These indications
can also be referred to as:
A. Triggers
B. Workarounds
C. Risk averse
D. Triggers, early warning signs, and risk symptoms
9
10. Stakeholders, including consultants, customers, sponsors, and
professional and technical associations, that gather and analyze information
with people and/or computers, are some of the sources of:
10
11. You decide to use statistical sampling for your project, because
surveying the entire population involves all the following issues, except:
A. Inaccurate data
B. More money
C. More time
D. More resources
11
12. Your organization requires that all technical projects go through Initiate,
Analyze, Design, Implement, Test, and Closeout project life cycle which is:
13
14. You advocate active participation of your team members; this is
because you believe in:
14
15. Which of the following is the most widely used contract type?
15
16. Please refer to the diagram given
(all units are in days). What is the project
float if management wants to complete this project within 13 days?
A. 0 days
B. - 3 days
C. 2 days
D. Cannot be determined, because information given in the question is incomplete
17
18. Your project is almost complete, when the customer requests an additional
feature in the project`s final product. The BEST course of action is to:
18
19. You and the other Project Management Staff are using cost
aggregation, reserve analysis, expert judgment, and funding limit
reconciliation to establish a cost performance baseline. This is performed
during which process?
A. Control Costs
B. Determine Budget
C. Estimate Costs
D. Create WBS
Answer: B Explanation: Knowing your tools & techniques is how you get
this one right. Aggregate means “add” it all up. Determine Budget is the
process of aggregating the estimated costs of individual activities or work
packages to establish an authorized cost baseline. Cost aggregation,
reserve analysis, expert judgment, historical relationships, and funding limit
reconciliation are all the tools/techniques used in this process.
19
20. Graphical representations of situations showing cause-and-effect, time
ordering of events, and other relationships among variables and outcomes
are also referred to as:
A. S-curve charts
B. Graphical evaluation and review technique (GERT)
C. Causal influence diagrams
D. Run charts or scatter diagrams
20
21. During executing, all the following statements are apply, except:
21
22. Determining the required levels of quality for the project is the
responsibility of:
A. Project Sponsor
B. Project Manager/Project Management Staff
C. Project Team
D. All stakeholders in the project
22
23. You understand that managing stakeholder engagement is an important
priority. Which statement on project stakeholders is NOT correct?
A. Inspection
B. Expert judgment
C. Observations
D. Focus groups
A. Smoothing
B. Compromising
C. Confrontation
D. Withdrawal
25
26. You had conducted an independent estimate to find out the cost of sub-
contracting the manufacturing of 1,000,000 ball-bearings for your automobile
company. You estimated the cost to be $500 per bearing. However, when
you asked for bids and proposals from prospective sellers, the minimum
price quoted was $750 per bearing. The reasons for the variance in the
estimate could be all the following, EXCEPT:
27
28. You are performing the Manage Communications Process. Which of
the following is NOT an Tool/Technique:
28
29. One of your team members filed a critical report ten minutes before a
bidder conference. You notice some serious errors have crept into the
report. You should:
30
31. You are the project manager in an automobile manufacturing company.
Machine parts required in your manufacturing process supplied by a vendor
did not reach in time because of heavy rains. You had anticipated this risk
and planned for it in your risk register. You started using unutilized machine
parts supplied one year ago. However, this has subjected your project to a
new risk - the machine parts which were not used for one year suffer from
higher level of defects. This new risk can also be called:
A. Contingency risk
B. Pure risk
C. Secondary risk
D. Residual risk
31
32. You are in the process of performing the work as defined in the project
management plan to achieve the project`s objectives. This is done during:
32
33. You are managing the tools/spare parts section for an aircraft
manufacturing company. Your team members have discovered some
defective tools/spare parts. The probable cause for these could be materials
used, defective measurement systems, inaccurate tolerances in the
machines, or other factors. To determine what caused the defect, you use:
33
34. You have been managing a project to construct a bridge on an
Interstate highway. You have divided the project into phases to provide
better management control. Which of the following is a characteristic of a
project phase?
A. Value engineering
B. Unanimity
C. Voice of customer
D. Kanban
A. Recognition
B. Increased responsibility
C. Career advancement possibilities
D. Salary
36
37. You have to provide a critical deliverable within five months and do not
have time to go through the Conduct Procurements process. You decide to
sign a contract with a supplier with whom your company has done some
work in the past. The risk you are accepting in this situation is:
Answer: A Explanation: The risk here is that even though the supplier has
worked with the company in the past, they may not have the required skills
for the current project.
37
38. You are in the process of performing the Develop Schedule process to
determine planned start and finish dates for project activities. Which of the
following inputs will be helpful for beginning this process?
38
39. You are performing the Control Communications Process to organize
and summarize the information gathered. Later, you present the results of
the analysis as a comparison to the performance measurement baseline.
Some common formats for performance reports that you could use are:
39
40. You are managing a project in a foreign country, and now you realize
you will have to pay a fee to some government agencies to get your work
done. You should:
BAC = $ 300,000
AC = $ 100,000
EV = $ 150,000
CPI = 1.2
ETC = $ 120,000
A. $ 250,000
B. $ 220,000
C. $ 280,000
D. $ 300,000
42
43. Project integration management includes the processes and activities
needed to identify, define, combine, unify, and coordinate the various
processes and project management activities. For successful project
integration management, it would likely be best to have:
A. Cost of conformance
B. Failure costs
C. Sunk costs
D. Opportunity costs
44
45. As a portfolio manager, you would be responsible for managing which
of the following?
A. Project interdependencies
B. Projects and programs
C. Programs and operations
D. Functional work and operations
45
46. The sponsor wants to make a change to the project. You should:
48
49. The process of identifying the specific actions to be performed to
produce project deliverables refers to:
A. Define Activities
B. Collect Requirements
C. Create WBS
D. Create Stakeholder Management Plan
49
50. All of the following are inputs to the Define Scope Process, except:
A. Requirements documentation
B. Project Charter
C. Project Scope Statement
D. Organizational Process Assets
50
51. You have conducted a communication requirements analysis to
determine the total number of possible communication channels in the
project. While conducting the analysis, you learn that the number of
communication channels:
51
52. You have been asked to help management select two of three
potential projects. Which of the following would not apply?
A. Configuration management
B. Constrained optimization method
C. Benefit measurement methods
D. Analogous estimating
52
53. You are in the Identify Risks Process and are determining which risks
may affect the project and document their characteristics. Whom would you
want to be a part of the Identify Risks process?
A. The project manager, project team members, subject matter experts, and
customers.
B. The risk management team, end users, and risk management experts.
C. All relevant stakeholders.
D. Positively impacted stakeholders.
54
55. In a normal distribution, standard deviation refers to:
A. Distance of measurement from the mean (i.e. how far from the mean)
B. Distance of measurement from the most likely value
C. Distance of measurement from the middle most value
D. A tool that is used in qualitative risk analysis
56
57. You are the project manager at a software development company, and
need ideas for project and product requirements. Which of the following
techniques would you most likely use to gather creative ideas at your
meeting?
A. Focus groups
B. Idea/mind mapping
C. Nominal group technique
D. Brainstorming
57
58. You invest a lot of time in team development to increase the team`s
performance, which in turn increases the likelihood of meeting project
objectives. Which of the following indicators would you most likely NOT use
to evaluate your team`s effectiveness?
A. Zero
B. Duration equal to the phase duration
C. Duration estimates plus cost of conformance and contingency reserves
D. Early start plus duration
60
61. You would like to conduct a lessons learned session to identify project
successes and failures, as well as make recommendations to improve
future project performance. This is usually done:
Answer: C Explanation: During the project life cycle, the project team and key
stakeholders identify lessons learned concerning all aspects of the project. The
lessons learned are compiled, documented, and distributed so that they
become part of the historical database. However, most of the organizations
prefer post-implementation meetings and case studies to document lessons
learned.
61
62. You recently went on an official trip to another country to discuss a
business proposition with a potential vendor. The vendor took you out for
lunch and offered you gifts, as it is customary in that country. You must:
A. Tell the vendor that you cannot accept the gifts as per company policy
B. Accept the gifts as it is a local custom, but promptly inform your
manager
C. Return the gifts, because accepting them could be interpreted as a
personal gain
D. Accept the gifts, as they are not very expensive
63
64. You have identified important risks and planned the appropriate
responses. Some risks (e.g. possibility of natural disasters impacting the
project) have been documented and accepted in your risk management
plan. What are the remaining risks called?
A. Unidentifiable Risks
B. Residual Risks
C. Secondary Risks
D. Inherent Risks
64
65. In a recent job interview, you are asked to define the most important
characteristic of a project manager. Which of the following will be the best
answer?
65
66. You have been asked to prepare a process improvement plan.
You should consider all the following, except:
66
67. You are responsible for managing a project in your company but
you have little authority and have to constantly report to a functional
manager. To which organizational structure does your company best
relate to?
A. Matrix
B. Functional
C. Projectized
D. Balanced
67
68. You are a project manager in a manufacturing company, and are
developing a new product. In this context, you are conducting
requirements workshop for the stakeholders to determine the product`s
critical characteristics. Which technique would best be used for this
purpose?
A. Team-building activities
B. Ground rules
C. Interpersonal skills
D. Core team rules of conduct
71
72. You are the project manager with seven team members. One more
member will be joining the team after a week. What will be the number of
communication channels once the new member joins your team?
A. 28
B. 21
C. 18
D. 36
72
73. All of the following are inputs for the Monitor and Control Project Work
Process, except:
73
74. Half way through your construction project, the CPI is 0.85 and SPI is
1.25. What could be the possible reason?
A. A critical resource went on sick leave for a long period of time, which
had not been anticipated earlier.
B. The cost of raw materials required for construction increased by 10%.
(You had anticipated a cost increase of 12% in your project plans.)
C. In anticipation of delays, the project was crashed to decrease the
duration.
D. There was four days waiting time in the curing of concrete, and work
could not be done during that time.
75
76. Which of the following are not inputs to the Direct and Manage
Project Work Process:
76
77. You have completed a NASA project for the launch of a weather
forecasting satellite. The satellite is being tested for a specific quality
metric. For which processes are quality metrics used?
77
78. You are a project manager in XYZ Company, which has a projectized
organizational structure. In this environment, all of the following are true,
except:
Answer: A
80
81. Which of the following would not be used during the Control
Procurements Process?
81
82. All the following statements regarding the creation of duration estimates
are correct, EXCEPT:
A. Mathematical analyses like CPM, GERT, and PERT indicate the dates
on which the activity can be scheduled, given resource limits and other
constraints.
B. Duration compression techniques, including fast tracking and crashing,
can help in decreasing the project schedule.
C. WBS classification allows for useful activity ordering and sorting.
D. The duration of the project is the sum of the duration of all the activities
in the project.
83
84. The seller`s project is undertaken on contract and you are an employee
of the seller. Since you earlier worked with ABC Bank, the buyer, you are
aware of the evaluation criteria used in ABC Bank to select sellers. You
understand this could be a potential conflict of interest situation. How do
you propose to act?
A. .9
B. 0.48
C. 1.7
D. .3
Answer: B Explanation: CV = EV - AC
So, EV = CV + AC = 65,000 + 125,000 = 190,000.
TCPI = (BAC-EV) / (BAC-AC)
= (250000-190000) / (250000-125000)
= 60000/125000
= 0.48
85
86. In your project, you have just conducted a risk data quality assessment to
evaluate the degree to which the data about risks is useful for risk management.
What is your next step?
A. Perform a structured review of project plans and assumptions, both at the total
project and detailed scope levels.
B. Develop checklists to identify risks based on historical information and
knowledge that has been accumulated from previous similar projects.
C. Conduct planning meetings to develop the risk management plan.
D. Conduct interviews to quantify the probability and impact of risks on project
activities.
Answer: D Explanation: Justification: Risk data quality assessment is a tool for Perform
Qualitative Risk Analysis process. It refers to "Interviewing" which is a tool and technique for
Perform Quantitative Risk Analysis. Perform Quantitative Risk Analysis is conducted after
Perform Qualitative Risk Analysis. Option A: This refers to "Documentation Reviews" which is
a tool and technique for Identify Risks process. Identify Risks process is conducted before
Perform Qualitative Risk Analysis process. Option B: This refers to "Checklist Analysis" which
is a tool and technique for Identify Risks process. Identify Risks process is conducted before
Perform Qualitative Risk Analysis process. Option C: This refers to "Planning Meetings and
Analysis" which is a tool and technique for Plan Risk Management process. Plan Risk
Management process is conducted before Perform Qualitative Risk Analysis process. 86
87. You are the project manager for a project managed under contract. You
receive a change request from the buyer involving a new government
regulation. What should you do FIRST?
88
89. Your project sponsor has specified that you have to complete your
project within 3 months with a funding limit of $ 250,000. This is an
example of:
A. Authoritative management
B. A constraint
C. An assumption
D. High-level risk
A. Observation technique
B. Prototype
C. Requirements analysis
D. Quality sample
91
92. The subcontracting requirements for machining high-value equipment are
very demanding. Hence, you have determined the technical criteria to
evaluate the sellers. This is an example of:
92
What is the float of activity 5?
A. 0
B. 1
C. 2
D. -1
Answer: A Explanation:
A. 0
B. 8
C. 12
D. 20
94
95. Your company has recently been awarded a contract by the government
to reconstruct houses devastated by an earthquake. In this context, the
government’s role will most likely provide the:
97
98. You are managing a small project with five team members working part-
time. At the beginning of every week, you allocate work to all the team
members. This is an example of:
98
99. After joining as a stand-in project manager for an ongoing project, you
are informed by the team that certain features are added to the deliverable
that were not requested by the customer, to earn the customer’s
appreciation. In this situation:
A. Validate Scope
B. Control Risks
C. Control Stakeholder Management
D. Perform Quality Assurance
100
101. Some of the benefits of a well-constructed project scope statement
include all, except:
101
102. You are managing a high priority project, requiring more than 1,000
team members. During human resource planning, you would like to apply
proven principles to shorten the time needed to create a human resource
plan to ensure you are when and how human resource requirements will
be met. Which of the following “subsidiary plan” does this describe?
A. Stakeholder register
B. Linear Resource Chart
C. Staffing management plan
D. Stakeholder allocation plan
102
103. The following is the data for a CPIF project you are managing:
Target cost is $ 100,000; Actual cost is $ 80,000;
Target fee is $ 20,000; Maximum fee is $ 25,000;
Sharing ratio is 60:40.
Answer: C Explanation:
Target cost (TC) = $ 100,000
Target fee (TF) = $ 20,000
Maximum fee = $ 25,000
Sharing ratio=60:40
Actual fee (AF) = {(TC - AC) * SSR} + TF = {($ 100,000 - $ 80,000) * 40%} + $
20,000 = $ 20,000 * 40% + $ 20,000 = $ 28,000,
Although the actual fee is more than the maximum fee, the maximum fee ($ 25,000)
only is payable. So, final price = AC + AF = $ 80,000 + $ 25,000 = $ 105,000 103
104. Of the following documents, all of which are updated during the Control
Schedule process, which is NOT a part of the project management plan?
A. Schedule baseline
B. Cost baseline
C. Schedule management plan
D. Schedule data
104
105. What are the outputs for the Plan Scope Management Plan?
105
106. As part of your duties as a project manager, you provide confidential
company data to a vendor. In this context, which of the following precautions
should you take?
A. Insist that the vendor signs a non-disclosure agreement after you release
the sensitive information.
B. Make sure that the vendor receives all the sensitive information in time.
C. Ensure that the vendor signs non-disclosure agreement before you
release the sensitive information.
D. Monitor the vendor in order to prevent her from sharing the information
with her competitors
A. Variance Analysis
B. Estimate Costs
C. Determine Budget
D. Estimate Procurement Costs
A. S-curve
B. Histogram
C. Just in Time, LEAN, Kanban Charts
D. Pareto diagram
108
109. Ideally, when should a project manager begin working on a project?
A. As soon as a possible
B. After the Project Charter has been approved
C. When the WBS is completed
D. At any time during the project life cycle, depending on requirements
109
110. All the following statements about "Quality" and "Grade" are true,
except:
A. Grade is a rank given to entities having the same functional use but
different technical characteristics.
B. Low quality product may be of high grade.
C. Low grade products may have high quality levels.
D. It is a problem if the product is of high quality and low grade.
113
114. A contract which includes features of cost reimbursable and fixed price
types of contract is a:
A. Sequence Activities
B. Define Activities
C. Estimate Activity Resources
D. Estimate Activity Durations
A. Your friend bids for the contract and you inform the committee and the
project sponsor about it.
B. Your relative bids for the contract and you do not inform the project
sponsor about it.
C. Your close friend bids for the contract and you refrain from participating
in the contract awarding decision process without informing your
sponsor.
D. Your friend bids for the contract and you make sure the contract is
awarded to him.
A. Collect Requirements
B. Plan Stakeholder Management
C. Create WBS
D. Define Scope
118
119. Your company is a pioneer in the construction industry. The
government recently floated a tender for setting up a new airport. Since
you do not have all the requisite skills within the company, you enter into
a joint venture with a leading airport construction company to bid jointly
for the government contract. This is an example of:
A. Risk exploitation
B. Risk sharing
C. Risk enhancing
D. Risk mitigating
120
121. Your company has implemented ISO standards for quality. In this
context, which of the following statements regarding quality is NOT
accurate?
A. Disagree with your manager because you know that phase end reviews
should be used at the end of each phase of the project
B. Agree with your manager
C. Escalate this issue to the project sponsor
D. Take advice from a senior project manager about what should actually be
done at the end of each phase of the project
A. Define Activities
B. Estimate Activity Durations
C. Sequence Activities
D. Develop Schedule
126
127. While identifying stakeholders, you plan to group the stakeholders
based on their level of authority and their active involvement in the project.
You can do this by using a:
A. Power/interest grid
B. Power/influence grid
C. Influence/impact grid
D. Salience model
Answer: B Explanation: There are multiple classification models (for
stakeholders) available including, but not limited to: Power/interest grid, grouping
the stakeholders based on their level of authority (power) and their level or concern
(interest) regarding the project outcomes; Power/influence grid, grouping the
stakeholders based on their level of authority (power) and their active involvement
(influence) in the project; Influence/impact grid, grouping the stakeholders based
on their active involvement (influence) in the project and their ability to effect
changes to the project`s planning or execution (impact); and Salience model,
describing classes of stakeholders based on their power (ability to impose their
will), urgency (need for immediate attention), and legitimacy (their involvement is
127
appropriate).
128. Your company asks you to manage a project of its subsidiary unit in
another country. You quickly realize that workers in the subsidiary unit have
poor work ethics as compared with that of your parent company. In this
context, which of the following will be the most appropriate course of action?
A. Ask your new team to emulate the work ethics of the teams of your
parent concern.
B. Take steps to change the work culture of your new team.
C. Regard your new team as lazy and impose sanctions.
D. Treat it as cultural differences, and try to determine ways to improve
productivity.
Answer: C Explanation: Earned value (EV) = The sum of the approved cost estimates for activities
completed during a given period = Estimated cost of work that is completed after day 11
= $ 5,000 + $ 5,000 + $5,000*.50 = $ 12,500 (because Activity A, Activity B are complete, Activity
C is 50% complete)
Present value (PV) = Present work to be completed after day 11 = $ 5,000 + $ 5,000 + $ 5,000 *
(1/5) (because at end of day 11, according to our plan, Activity A, Activity B should be complete;
Activity C only one day out of 5 days should be complete, i.e. 20% complete ($ 1,000 of work
should be done) = $ 11,000.
Actual cost (AC) = Actual Cost of work completed = $ 13,000.
Schedule variance (SV) = EV - PV = $ 12,500 - $ 11,000 = $ 1,500
Since SV is positive, we are ahead of schedule.
Cost variance (CV) = EV - AC = $ 12,500 - $ 13,000 = - $ 500
Since CV is negative, we are over budget.
129
130. You have identified disaster situations (e.g. floods, earthquakes, etc.)
as potential risks. The project sponsor suggested that, at the project level,
no steps could be taken to deal with such risks and recommended creation
of a contingency reserve (with 5% of the project budget) which could be used
in case of disaster situations. This is an example of:
A. Risk mitigation
B. Risk acceptance
C. Risk avoidance
D. Risk transfer
A. Training
B. Rework
C. Loss of reputation
D. Warranty
133
134. The process of monitoring the status of the project and product scope
and managing changes to the scope baseline is referred to as:
A. Validate Scope
B. Control Scope
C. Monitoring and Controlling Project Work
D. Scope Verifications
134
135. Motivating your team members is important for the success of the
project. You understand from the HR manager that employees are
motivated by self-esteem, recognition, and self-actualization. To which
theory is the HR manager referring?
A. Theory Y
B. Learning curve theory
C. Herzberg`s theory
D. Maslow`s Hierarchy
of Needs
136
137. During the Control Schedule Process, changes to project schedule
can result in change requests to:
A. Schedule baseline
B. Components of project plan
C. Activity attributes
D. Schedule baseline and/or components of Project Management Plan
137
138. You are the project manager of a $ 20 million project, and you are
struggling to manage the needs of all the stakeholders. So, you decide to
classify the stakeholders, which will enable you to focus on the relationships
necessary to ensure the success of the project. All the following are valid
ways to classify stakeholders EXCEPT:
A. According to Interest
B. According to Organization hierarchy
C. According to Involvement
D. According to Influence
141
142. The Project Management Staff are unable to determine the monetary
value for risk impacts on your construction project. One of the team
members suggests that you just develop a list of risks to watch out for.
However, you tell that you still can prioritize the risks by:
142
143. To resolve conflicts in your project, you can use all the following
conflict resolution methods, except:
A. Collaborating
B. Smoothing
C. Avoiding
D. Directing
143
144. You have recently taken over a project from another project manager,
who left the company. The project has a CPI of .9 and an SPI of .6, but
senior management was not informed. What should you do FIRST?
145
146. A project team member informs you that a particular task is taking
much more time than estimated. You are surprised because you, had not
anticipated this delay, and you ask for status reports and forecasts from all
project team members. Which Process Group are you in?
A. Initiating
B. Executing
C. Monitoring and Controlling
D. Planning
A. Problem solving
B. Avoiding (Withdrawing)
C. Forcing
D. Confronting
148
149. Six months into your project, your management lets you know you will
receive an incentive of $ 5,000, if you complete the project one month
ahead of schedule. When closing the project ahead of schedule, your team
informs you the product contains a minor flaw and may not fully satisfy the
customer`s needs. However, rectification of the minor flaw will require lot of
changes and take 2 more months. In this context, you will:
150
151. You are working in the Project Management Office (PMO) of your
organization. Your job responsibility is to:
A. Uncontrolled changes
B. Controlled changes
C. Manageable changes
D. Unmanageable changes
152
153. All of the following relate to negotiating skills you should have,
except:
153
154. You are documenting project purchasing decisions, specifying the
approach and identifying potential sellers. Some tools you can use include
all the following, except:
Answer: D Explanation: Option D: This is the correct option, as the task is not on
the critical path. Option A: Since LS - ES = LF - EF = 5 days, the task has a slack
of 5 days; hence this task cannot be on the critical path. Option B: There is no
information in the question that suggests that the project may get delayed.
Option C: The project float is the amount of time a project can be delayed
without delaying the externally imposed date. Since the externally imposed date
is not mentioned, we cannot determine the project float. 155
156. You have just discovered a risk during your project that requires an
immediate corrective action. During which Project Risk Management
Process is this action performed?
A. Prevent team members from starting the work without your permission.
B. Prevent scope creep.
C. Prevent unnecessary changes to project scope.
D. Clarify and initiate the work for each work package.
A. Costs of nonconformance
B. Emotional Intelligence-related costs
C. Failure costs
D. Prevention costs
158
159. You are in the process of obtaining seller responses to select a seller.
You conduct a bidder conference, where your primary objective is to:
159
160. You would like to use project management best practices to
sequence the activities for your road construction project. Which of the
following are based on preferred dependencies and/or best practices?
A. Mandatory dependencies
B. Discretionary dependencies
C. Industry norms
D. Best Practice standards for ISO 9001 certification
A. Identify Risks
B. Establish an agreed-upon basis for evaluating risk
C. Ensure that the degree, type, and visibility of risk management are
commensurate with both the risks and the importance of the project
D. Provide sufficient resources and time for risk management activities
163
164. When you (the buyer) control a contract, you should pay attention to
all the following, except:
164
165. You are working on a 12 month assignment to build a website with
4000 pages for $ 1,000,000. You are supposed to spend $ 250,000 every 3
months. After 6 months, you determine that only $ 400,000 of work is
completed and cost incurred is $ 800,000. What is the ETC?
A. $ 2,000,000
B. $ 1,500,000
C. $ 1,000,000
D. $ 1,200,000
166
167. While preparing the schedule for the project activities, you find there
is very limited information on activity durations, but you may be able to
obtain some information from others within you company. Which estimating
tool do you use?
A. Three-point estimates
B. Parametric estimating
C. Quantitative estimating
D. Analogous estimating
A. Identify Stakeholders
B. Collect Requirements
C. Create Project Charter
D. Create Project Management Plan
170
171. A documented direction to perform an activity that can reduce the
probability of negative consequences associated with project risks is
called:
A. Corrective action
B. Preventive action
C. Defect repair
D. Risk transference
A. Design of experiments
B. Control chart
C. Organizational process assets
D. Trend analysis
A. 18%, $ 500,000
Answer: B Explanation:
B. 17.33%, $ 461,538 SV = EV – PV EV = SV + PV
C. 17.8%, $ 437,500 = 30,000 + 100,000 = 130,000
D. 18%, $ 437,500 CV= EV – AC AC = EV- CV
=130,000 – 50,000 = 80,000
Percentage Complete = EV/BAC x 100
= 130,000/750,000x100 = 17.33%
CPI=EV/AC
= 130,000 / 80,000 =1.625
EAC = AC + (BAC-EV) / CPI
= 80,000 + (750,000 – 130,000) / 1.625
= 80,000 + (620,000) / 1.625
= 461,538
174
175. Which of the following processes occur in the Planning Process
Group?
A. Identify Risks
B. Manage Stakeholders Engagement
C. Acquire Project Team
D. Identify Stakeholders
175
176. You have discovered that a deviation from the schedule baseline has
occurred. You want to determine the reason and level of variance relative to
the schedule baseline so that corrective action can be taken. Which of the
following tools would you use for this purpose?
A. Scheduling tool
B. Performance reviews
C. What-If Scenario analysis
D. Variance analysis
Answer: D Explanation:
Variance analysis is used to determine the cause and degree of variance
relative to the schedule baseline and decide whether corrective or preventive
action is required.
176
177. When your company buys computers from Dell, you also pay extra for
a three-year warranty which ensures that any manufacturing defects will be
covered. The risk response strategy used is:
A. Exploit
B. Avoid
C. Mitigate
D. Transfer
A. Cost of conformance
B. Customer retention costs
C. Failure costs
D. Performance costs
179
180. In which Process Group will approved changes be implemented?
A. 0.9
B. 1.176 Answer: B Explanation: CV = EV - AC, AC = EV - CV
C. 1.5 200,000 - 25,000 =175,000
D. -1.5 EAC = AC + ETC
EAC = 175000 + 425000
EAC = 600,000
182
183. The concepts of "Zero Defects" and "Do It Right First Time" were
formulated by:
A. Ouichi
B. Deming
C. Crosby
D. Juran
183
184. A new project manager in your organization, is ready to enter into a
contract, but is unsure of the type of contract she should select. Which type
of contract represents the highest risk to the seller?
184
185. A red, yellow, green graph, that can be used to graphically
illustrate the risks 9threats and opportunities) on the project,
qualitatively is called the:
185
186. You are involved in manufacturing ball bearings using lathe machines.
The ball bearings should have a diameter of 5.0 cms - allowable control
limits are 4.95 cms to 5.05 cms. Measurements made after the end of the
process for the bearings produced are: 4.96, 4.98, 5.01, 5.03, 5.02, 5.01,
5.03, 5.04, 5.02, 4.96, 4.98, and 5.00. What is your conclusion about the
process?
186
187. Your customer has decided to terminate your software project as the
need for the product does not exist anymore. As a project manager, what
step would you take first?
189
190. Which of the following will you undertake in the Monitoring and
Controlling process of your project?
A. FS (Finish to Start)
B. FF (Finish to Finish)
C. SS (Start to Start)
D. SF (Start to Finish)
191
192. If there is a fire, the risk response plan developed is to use a fire
extinguisher. If the fire extinguisher cannot take care of the fire, you call the
fire department. Calling the fire department is an example of:
A. Secondary risk
B. Residual risk
C. Fallback Plan
D. Work around
A. Statistical sampling
B. Control chart
C. Pareto diagrams
D. Inspection
194
195. You create several project documents which will help your team
manage the project. Which of the following is NOT an example of a project
document?
A. Schedule baseline
B. Assumption log
C. Roles and responsibilities matrix (RACI RAM)
D. Risk register
195
196. You have asked your programmer to give you an estimate of how long
she will take to complete a software program. She mentions that she would
most probably get the job finished in 2 hours. But if she runs into some
issues doing unit-testing for the program, it could take her as long as 7
hours. On the other hand, she may be able use with to pick up a similar
program from the organization process assets, in which case it will take her
only 1 hour. What is the standard deviation?
A. 2 hours
B. 1 hour
C. 3 hours
D. Cannot be determined from the provided information
Answer: B Explanation:
Standard Deviation = (Pessimistic – Optimistic )/ 6 = (7 - A) / 6 = 1
196
Activity Xy (7 days)y Activity Z
197. Refer to the diagram above. Which of the following situations could this
diagram most likely represent?
A. Project coordinator
B. Manager with considerable authority
C. Support person
D. Functional manager
198
199. A team member suggested the addition of a functionality, which he
thinks, will improve customer satisfaction. This feature was listed as out of
scope in the Project Charter. Your approach should be to:
A. Theory Y (McGregor)
B. Theory X (McGregor)
C. Maslow`s hierarchy of needs
D. Theory Y (Ouichi)
200
201. Your Project Sponsor wants to know what measures you have taken to
ensure quality on your project. You tell her you will use most of the
“Seven Basic Quality Tools,” which include all of the following, except:
Answer: B. Although helpful for tracking requirements over the course of the
project, RTM is not one of the 7 basic quality tools. Likewise, project
management software is helpful mostly for scope, schedule, and budget—not
quality.
201
202. A Business Analyst is assisting you in developing a business case with
senior management. This relates best to:
A. Product requirements
B. Product specifications
C. Business requirements
D. Collaboration with the customer
202
203. Your company is constantly looking for ways to reduce/eliminate waste
on all projects. This relates best to:
A. 80/20 rule
B. Halo effect
C. Parkinson’s law
D. LEAN
Answer: D. LEAN relates to best to Just in Time (JIT) and possibly Kanban
visual charts. 80/20 often relates to Pareto charts. Halo effect relates to
assuming people will be good at another assignment, simply because they are
good at another job. Work expands so as to fill the time/money available
relates to Parkinson’s law.
203
204. A Business Analyst will assist you on the project you have just been
assigned to. She tells you she will use the following project document to
track requirements:
204
205. You are observing that people on your team believe that stakeholders
should behave as “robots,’ to decrease the “drama” during the project
lifecycle. But you understand the people should recognize their own and
other stakeholder’s emotions, and to use this information to guide
thinking and behavior. This relates best to which of the following.
205
206. You’re being assigned to an important software development project
that must be completed within three weeks. Most of your past experience
has been with predictive lifecycles, but this project will require you to be
more adaptive to frequent modifications. You will need to work closely
with stakeholders over five, main, iteration, milestone events. This
relates best to:
A. Just-in-time (JIT)
B. Kanban
C. LEAN
D. Agile
206
207. Formalized acceptance relates best to which processes?
207
208. You are developing a RACI-RAM. What does RACI stand for?
208
209. Which of the following would be best for ensuring the project aligns with
business requirements?
A. Quality Control
B. Contracts
C. Key Performance Indicators (KPIs)
D. Stakeholder Engagement
209
210. Which of the following would best relate to Tuckman’s team phases
(sequentially) teams often go through:
Answer: C. The rest are made up, or not in the correct sequence.
210
211. A quality management and control tool, also useful for risk contingency
planning is:
A. Histograms
B. Pareto Charts
C. Benchmarking
D. Process Decision Program Charts (PDPC)
Answer: D. Process Decision Program Charts (PDPC) may be used for this
purpose. NOTE: PDPC is NOT one of the seven basic quality tools are as
the others here are. For the exam, link Pareto charts to the “vital few,” and the
80/20 rule.
211
212. Which of the following relates best to to Total Quality Management
(TQM), Edwards Deming, iterative/incremental/adaptive lifecycles, Agile,
and possibly rolling wave/progressive elaboration?
212
213. Your project has an SPI of .9, and a CPI of 1.2. Which of the following
could be the reason for this?
Answer: B. You are only progressing at 90% of the rate originally planned,
but are 20% under budget. Eventually, you will have to pay the vendors, and
at that time, you may find that you are also over budget. Often, when you are
behind schedule, it’s just a matter of time before you go over budget as well.
213
214. Your company has been working with a particular contractor for many
years, and has been happy with their performance. You have just been
assigned to take over a very large project, that will require the services of
a competent contractor. A program manager advises you to just use the
“standard” generic company contract. Which of the following would be
the best course of action for you to take before hiring the seller?
Answer: B. Note how it’s best to seek “expert” advice. In the case of
contracts, the legal and/or the procurement departments are better than the
other stakeholders mentioned in the other answers. The other answers still do
not address the fact the contract needs to reflect the work, schedule, cost, etc
are appropriate. For the exam, get everything in writing. 214
215. You are performing the Develop Project Team Process. Which of the
following tools/techniques would you most likely be performing?
A. Compromising
B. Pre-assignment
C. Training/mentoring
D. Maslow’s Hierarchy of Needs
Answer: A. Note how this relates best to project financial, budget, & cost
procedures. ($) B is more for schedule, not cost-related. C is too general. D
is quality, not cost-related.
216
217. A Senior Project Manager that does not believe in PMI best practices,
and never took the PMP exam, has recently retired. You have been
assigned his project which is now only 50% done. After assessing the
project with the Project Sponsor, you realize the project is significantly
behind schedule, and significantly over budget. During your discussion,
the Project Sponsor realizes the project has now become a “huge money
pit,” because the project/product scope was poorly defined. The most
likely reason this has occurred relates to all of the following, except:
Answer: C. Note how this does not relate to what’s most vital during the early
phases of the project. While helpful, this tool will not help if a good foundation
is not first determined.) All the rest, relate to solid PMI best practices.
217
218. You are making up a hammock portion of the project schedule network
diagram. Activity A can start immediately, and takes 10 days. Activity B
can start immediately, and takes 11 days. Activity C can start after
Activity A and B are complete and takes 20 days. Activity D can start
after activity B is complete, and takes 30 days. Activity E can start after
Activity D is complete, and takes 5 days. Activity F is the last Activity in
the diagram, can start after Activity D and E are complete, and takes 10
days. Which is true?
219
220. The late finish for Activity D was 20 days, and the early finish is 21 days.
Based on this information you know:
Answer: D. Activity D is not only on the critical path, it is one day late. Late
Finish – Early Finish = Float. 20 – 21 = -1 (NOTE: Just because one activity
is late, does not necessarily mean the project will be late.)
220
221. You and key stakeholders are determining the scope for the project.
It’s important to have an accurate scope baseline. Which of the following
processes produces the scope baseline?
A. Create WBS
B. Plan Requirements Management
C. Define Scope
D. Collect Requirements
221
222. You and your project management staff are performing product
analysis. What process are you performing?
A. Define Scope
B. Collect Requirements
C. Create WBS
D. Develop Project Charter
222
223. You and your project management staff are determining calendar dates
for your project’s schedule. You are performing which of the following
processes?
A. Start-to-finish
B. Start-to-start
C. Finish-to-finish
D. Finish-to-start
224
225. You and your project management staff are determining the budget
required to complete the project. You have estimated the costs and
aggregated the costs to perform the project activities. When you examine
the Project Charter, you note the control account is less than what will be
needed to complete the project. This relates to:
A. Procurement estimating
B. Cost Control
C. Delphi technique
D. Funding limit reconciliation
225
226. You are in the middle of a biomedical device project in Canada. A team
member informs you the project currently has a CPI of 1.3. Which of the
following should you do first?
A. Ask the team if they can work overtime for the foreseeable future.
B. Tell the Project Sponsor you will need to crash the project as soon as
possible.
C. Verify that the EV and PV that were used to calculate are correct.
D. Verify that the EV and AC that were used to calculate are correct.
Answer: D (EV/AC = CPI) If these numbers are correct (verify first), the
project is under budget. A Since you are likely under budget, this will
probably not be necessary. B is not needed—see A. C PV is not used to
calculate CPI.
226
227. You are in the middle of a large building project in Brazil. A team
member informs you that changes will need to be made soon. Which of
the following should you do first?
Answer: C Follow your change control process, is typically always the best
course of action. The other options may all be part of this process.
227
228. You have been assigned to set up a call center in Panama, that will
service most of Central and South America. You and a Business Analyst
are assisting with developing a business case as an input to the Project
Charter. Which of the following does not relate to developing a Project
Charter?
228
229. EV = 100, AC = 110, PV = 90. Based on this data, which of the
following is true?
Answer: A (EV / AC = CPI) .90 means you are only getting .90 cents for
every dollar invests (over budget). EV / PV = SPI 1.11 means you are 11%
ahead of schedule. So, you are over budget, and ahead of schedule right
now. Crashing the project would likely put it even more over budget.
229
230. You have been asked by your Project Sponsor where you have
documented the steps that will be taken during the course of the project
to make continuous improvements. Where is this information
documented?
Answer: B. Along with quality metrics and quality checklists. A & C are
made up terms. Benchmarking is a tool/technique for analysis of scope and
quality.
230
231. You have been asked by your Project Sponsor to develop an adaptive
lifecycle for your project, that will only take about 2 weeks to complete.
Which of the following does not relate to an adaptive lifecycle?
A. Loss of business
B. Legal liabilities
C. Rework
D. Training
Answer: D. Upfront, preventative costs. A, B, & C all relate the cost of NON-
conformance (failure costs).
232
233. Which of the following relates to linking performance to rewards, that
may change over time?
A. Situational Theory
B. Expectancy Theory
C. Hygiene Theory
D. Theory Z
233
234. Which of the following relates to “motivating agents”:
234
235. All of the following tools can be used to brainstorm the source of
defects, except:
A. Ishikawa diagrams
B. Causal influence diagrams
C. Quality metrics
D. Nominal group technique
236
237. Which of the following best relates to observing/analyzing “feelings”?
A. Stakeholder engagement
B. Conflict resolution
C. Emotional intelligence (EI)
D. Communication model
A. Compromising
B. Smoothing
C. Avoiding
D. Storming
Answer: A It’s the best answer, because joint problem solving is not listed. B
& C do not address the problem. D may be the team development stage that
includes conflict, but is not a technique for managing it.
.
238
239. You have just been assigned to build a large state-of-the-art cleanroom
for a large computer chip manufacturer. You need to ensure risk is
carefully managed over this two-year project. Which of the following
lifecycles would be most appropriate?
A. Agile
B. Predictive
C. Iterative
D. Rolling wave
A. Formalized acceptance
B. Quality Assurance is performed
C. Changes are recommended to the Change Control Board
D. Risk audits/reassessment is performed
240
241. You will require two, key contractors (SMEs) to execute your
landscaping project, and are negotiating now to determine their
availability. This is an example of:
A. Fait accompli
B. External stakeholders
C. Pre-assignment
D. Virtual team members
242
243. You will need to spend a significant amount of time estimating
resources, duration, and cost on your project. Which of the following
estimates is most likely the least accurate:
A. Parametric estimating
B. Three-point estimating
C. Bottom-up estimating
D. Analogous
243
244. You will need to spend some time estimating resources, duration, and
cost on your project. Which of the following estimates may encourage
participation and reduce bias:
A. Parametric estimating
B. Three-point estimating
C. Bottom-up estimating
D. Delphi technique
244
245. You and your project management staff are developing the Human
Resource Management Plan. You are currently discussing how to
recognize and reward the project team. Which of the following is typically
the best approach:
245
246. Which of the following does not relate to Communications Management:
246
247. You are developing a predictive lifecycle on your construction project in
Mexico to better manage risk. Process sequence is paramount. Which
processes are not listed in the proper sequence?
Answer: A Estimating comes after sequencing activities. All the rest are in
the proper sequence.
247
248. You are currently helping senior management determine which project
to select. All of the following relate to project selection methods, except:
A. Affinity diagrams
B. Constrained optimization method
C. Benefit cost ratio
D. Monte Carlo Simulation/Modeling
248
249. You are currently closing down your project. Which is a helpful input for
closing down the project, and closing procurements.
249
250. You are performing quantitative risk analysis during Planning. Expected
monetary value analysis (EMV) (e.g. decision tree) provides the following
information; Project A has an EMV of $100,000, Project B has an EMV of
$75,000, Project C has an EMV of $100,500, and Project D has an EMV
of $90,000. You would most likely choose which project based on this
information.
A. Project B
B. Project A
C. Project D
D. Project C
Answer: D. With no other information available, just choose the highest EMV.
Note that answer “D” is Project “C.” Be careful!
250
251. You have to resolve a conflict that is beginning to plague you and one of
the members on your project team. The person you need to resolve the
conflict with is in the same city, but not in your building. The best way to
resolve the conflict is:
A. Notify the person’s boss via email, to see if all three of you can come to a
compromise.
B. Set up a phone conference with the person before the next meeting, to let
them know why you are concerned.
C. Bring up the issue at the next project status meeting, and allow the team
to help resolve the issue.
D. Set up a time to meet the person, and meet them in the cafeteria or break
room to chat about the issue(s).
251
252. You are working with your project management staff on your risk
register. All of the following could relate to this process except:
Answer: A. This information would not likely appear in the risk register, but
the other choices would.
252
253. Which of the following processes has “change requests” as an input:
Answer: B. This is the only process that has “change request” has an input.
It would be an output for all the other choices. The change control board
(CCB) would review the recommendation during this process and
approve/reject/defer the recommendation.
253
254. You are determining how to address threats on your project. Which of
the following would be least applicable as a risk response strategy for
threats on your project?
A. Mitigate
B. Avoid
C. Transfer
D. Reveal
254
255. All of the following relate to risk opportunities, except:
A. Share
B. Accept
C. Enhance
D. Secondary risk
Answer: D. These are risks that may need to be addressed after contingency
strategies have been taken. All the rest are opportunity response strategies.
(For opportunities, ESEA. Exploit, Share, Enhance, Accept.)
255
256. You are in the process of selecting a contractor for your building project.
Which of the following is most important:
Answer: B. Capability for the work, fairness and objectivity are paramount
when selecting a seller. All the others choices are important too, but B is the
best answer. Capability is more important than availability.
256
257. You are asking your contract administrator to archive procurement
related information in the records management system. You are most
likely performing:
257
258. You are working with your seller and your contract administrator to
ensure both parties are meeting contractual obligations. You are most
likely performing which process:
A. Conduct Procurements
B. Change Control
C. Close Procurements
D. Control Procurements
258
259. During Planning, you decided to hire 10 contractors. Now, you are
having regular unresolved issues with one of them. What is the best
thing to do first?
Answer: A. “Look before you leap.” Hopefully, you have a termination clause.
The other options do not provide the information you will need to make an
informed decision.
259
260. You have been asked to calculate the “To Complete Performance Index”
(TCPI) based on the EAC. The BAC is 100,000, the EV is $120,00, the
EAC is 110,000, and the AC is $105,000. What is the TCPI?
A. -4
B. 4
C. .83
D. 5,000
Answer: A. The formula, when based on EAC, is (BAC – EV) / (EAC – AC)
-$20,000 / $5,000 = -4, which is good.
260
261. You have been asked to use weighted average estimates. Optimistic
estimate is 100, most likely estimate is 125, and pessimistic is 200.
Based on this information, which of the following is true for this situation?
A. You should use the triangular formula, 100 + 125 + 200 / 3 = 141.66 days
B. You should use Program Evaluation and Review Technique, by weighting
the most likely by a factor of 4. The formula is O + 4M + P / 3. This
means the calculation is 100 + 500 + 200 / 3 = 266.66 days.
C. You should use Program Evaluation and Review Technique, by weighting
the most likely by a factor of 4. The formula is O + 4M + P / 6. This
means the calculation is 100 + 500 + 200 / 6 = 133.33 days.
D. Pessimistic - Optimistic = 100 days.
261
262. Your Project Sponsor has asked you to overlook some quality issues on
your “Bridge to Somewhere” project, and just move on to close out the
project. You should tell them which of the following, first?
Answer: D. You will have to see how the Project Sponsor responds to this,
and then take the proper actions. A may be a little too spontaneous. B is not
advised, and could make a lot of things much worse for you. C is not adhering
to the PMI code of ethics. This question relates to professional responsibility.
262
263. Which of the following is the most sought-after characteristics of a
leader to have?
Answer: B. Best answer. Trust and integrity are considered more important
than the other choices. This relates to professional responsibility.
263
264. You are reviewing some bids from sellers, when you notice that a close
family member wants to be considered for work on your project. You
should:
264
265. Which of the following best relates to a portfolio:
265
266. Your WBS has just been drafted for your 6 month, $200,000 commercial
construction project. Some quality issues and weather-related risks will need
further research, but your sponsor has asked for a responsibility assignment
matrix. Which of the following processes should be performed next.
A. Gather Requirements
B. Estimate Activity Resources
C. Sequence Activities
D. Define Activities
266
267. You are called into your sponsor’s office to explain your evaluation
regarding a variance you documented in your weekly status report. Which
process group does this reflect.
267
268. Your boss has asked you to help them decide which project would most
likely benefit the company, but all your projects must comply with six sigma
quality requirements. This activity might encompass all of the following,
except:
Answer: A. The rule of seven relates to a quality control chart. All the rest
relate to “project selection methods,” which is what you are actually doing, as
you are in the Initiating Process Group.
268
269. After two months of research, your business case is nearly complete.
Which of the following process are you most likely ready to perform.
A. Initiating
B. Develop Project Management Plan
C. Develop Project Charter
D. Identify Stakeholders
269
270. In the middle of your project, you determine several changes have been
made by a several stakeholders. You have asked each of these stakeholders
for a detailed description of the changes they have implemented. This most
likely relates to:
270
271. Everything has been going very well on your project, when suddenly the
customer requests a major change. What should you do first?
Answer: A. Creating a formal change request, should be the first step in the
change control process. Until you have the change request, performing the
others would be premature.
271
272. Although your customer can be “high-maintenance” at times, they have
asked for very few changes over the past 8 months. You’ve been able to
remain ahead of schedule and under budget to this point in the project. Since
you have some extra time and money, the customer asks for one last “small
change.” What should you do?
A. Get permission from the Sponsor and/or the Change Control Board
B. Perform assumptions analysis to determine the overall risk
C. Analyze the impact of the change on other project constraints
D. Since the change does not impact the budget and you have extra time,
implement the change
272
273. You will be using multi-level programming to select your next project.
Which of the following does this relate to?
Answer: D. Any project selection technique with the word “programming” (or
simulation/modeling) in it, relates to the Constrained Optimization Method. A
Earned Value Analysis is a technique for performance measurement, and is
performed during Monitoring and Controlling.
273
274. You will using the benefit measurement method to select your next
project. This relates to all of the following, except:
A. Present Value (PV), Net Present Value (NPV), Internal Rate of Return
(IRR)
B. Payback period, opportunity cost, sunk cost
C. Law of diminishing returns, depreciation, Expected Monetary Value (EMV)
D. Monte Carlo Simulation (S-curve report)
Answer: D. Any project selection technique with the word “simulation” in it,
relates to Constrained Optimization Method, and requires a computer. All
other choices relate to Benefit Measurement Methods.
274
275. Things have gone well on your first software development project, and
you think you are ready to begin closeout. What should be done before
moving to the “Close Project or Phase” Process Group?
275
276. You are in the midst of collecting requirements. You might use all of the
following, except:
Answer: B. Decompose the work occurs later during the Create WBS
process. A, C, and D relate to tools and techniques for the Collect
Requirements process, but note how just knowing the sequence helps here.
276
277. Which of the following would best benefit from the “Create WBS
process”?
A. Stakeholders
B. Project Team
C. Customer
D. Project Manager
Answer: A. Note how this is one of the those, “all of the above” type
answers. It includes the others.
277
278. Your Sponsor wants you to “cut the red tape,” and get on with project
execution. You are explaining the benefits of creating a WBS. A WBS would
best relate to which of the following benefits?
278
279. When is the best time to Validate Scope?
279
280. You have just accepted all the deliverables and addressed all items in
the issue log. But now, the customer is asking for one more change. Which
of the following is most appropriate to do first at this late stage in the project
life cycle?
Answer: B. Ask the customer for a description of the change is the best
answer… Always “look before you leap.” Follow your change control
process, even during Closing.
280
281. You are having difficulty decomposing the work. What is the most likely
reason?
281
282. You have asked your business analyst to do the product analysis. You
recommend getting this information prior to creating a WBS. Which of the
following relates best to this?
Answer: A. This would be done to better draft the project scope statement ,
prior to the other options. Again, sequence matters!
282
283. You are using project management software to monitor your software
development project. There is no lag time on the critical path. However, you
have just realized that a key activity had a late finish day of 12, and an early
finish day of 14. Based on this information, which of the following can be
currently said of the activity.
284
285. You are determining the scope of your software project with the
applicable stakeholders, who are more familiar with Scrum. They refer to the
customer as the “Product Owner.” You are fine with this rename, as long as
you get the correct requirements. In this context, documenting features and
functions best relates to:
285
286. You’ve been hired as a PMO consultant to audit some projects. You
have thought favorably of one of their Project Managers in particular, but they
often struggle with bringing their projects in on budget. When you begin the
audit, you notice that she has hired a relative as a sub-contractor. Some
expenses appear abnormally high. You should:
Answer: A. This is the best answer AFTER you have done the proper
investigation to report. Let the PMO take the appropriate action after you
present your findings… And as always, DO THE RIGHT THING!
286
287. You have been assigned to manage a project for a “difficult customer”
that you have worked with in the past. You thought their decisions were
rash, and you didn't feel respected professionally. Your manager still thinks
you're the best choice for this contract, even though there are other
opportunities in the portfolio. What should you do?
Answer: B. Projects may have “difficult” stakeholders that can cause conflict.
You have to deal with conflicts—it goes with the job. If your manager wants
you to do your job…DO YOUR JOB!
287
288. Your brother is preparing for the PMP exam, which you have just
passed. He asks you to share some of the questions from the exam with
him. What should you do?
A. Coach and mentor him with whatever questions you can remember form
your exam.
B. Explain you cannot cooperate with unethical behavior.
C. Direct him to online resources (e.g. pmi.org) with sample questions and
explain that exam questions vary per exam applicant, and are
confidential.
D. Document and report him to PMI.
Answer: B. In many parts of the world, this is just how things work. (Even in
the U.S. sometimes .) It’s kind of like a “When in Rome” situation. Note that
it says they are a “government official,” not some private, covert, “coyote-type”
person. But, it’s also good to keep things visible, whenever possible. Note
that having a meeting (and documenting), accomplishes almost nothing.
289
290. One of your team members has recently been coming late to project
meetings. He's an important contributor, and you consider him a friend. Last
week, you smelled alcohol on his breath. He showed up late again today.
After the meeting, you ask him to stay behind to discuss the situation. When
it's just the two of you in the room, you clearly can smell alcohol again. What
should you do?
A. Terminate him.
B. Report him to HR.
C. Ask him why his behavior has changed.
D. Tell him to get into a recovery program or else.
Answer: D. Note this is a “legal issue.” In this case, PMI would investigate,
and if true, revoke their PMP status. The PMI headquarters in Pennsylvania,
not the PMI local chapter, would handle this situation
291
292. You are performing a project audit, when you notice there is an
additional $3,500 charge. You were told it was essentially, a “finder’s fee,”
that will go back to the sales department. Your organization’s VP has already
signed off on the charge. You should:
Answer: B. This is something that may be serious, and you don’t want to
cover up, deceive, or take anything into your own hands. In this case, it’s best
to let someone in the legal department know ASAP, and let them advise you
as to the appropriate action.
293
294. A former boss you liked working for, is looking for new opportunities for
the new consulting agency he has just started. His skills are a great match
for the project you have started to manage for the county. However, county
guidelines dictate that all contracts must be awarded through a vetting
process. This process is based on price, experience, and performance.
However, since his consulting firm is new, it doesn't meet the county's
preferred number of years of experience. What should you do?
Answer: D. This takes you off the hook, by merely stating that you all “have
to follow the rules.” Who knows, if there are no other qualified applicants,
management may have to make an exception—but that’s not your call.
294
295. You have miscalculated a final cost change amount for your project,
undercharging the customer nearly $8,000. The project was worth more than
$900,000, so this shortage could be easily absorbed by your company. The
project was slightly late, but the customer (not happy) had signed a change
order for the late delivery. Now, you believe this customer will no longer do
business with your company in the future. You should:
Answer: A. Honesty (even if it could hurt) is the best policy. Keep things
“above the table,” as much as possible. Note that by sending it registered
mail, they have to sign for it. Remember that analysis and communication are
very important during times of change control. 295
296. Which of the following is not a formula for Estimate At Completion
(EAC)?
296
297. Which of the following is not a formula for Earned Value Management?
A. N = n (n-1) / 2
B. CV = EV - AC
C. SV = EV - PV
D. SPI = EV / PV and CPI = EV / AC
298
299. Which of the following relate to being ahead of schedule, but over
budget?
Answer: D. SPI must be greater than 1, and the CPI must be less than
one to be correct. Note A, means on schedule, but not ahead of schedule.
B is a bogus answer. Variances that are negative are behind, so C is
incorrect.
299
300. Which of the following is incorrect?
Answer: C. A TCPI that is less than 1 is good. All the rest are true
statements regarding the results of the formulas.
300