The document describes a deep braced excavation method for a box culvert underpass project in Serang, Banten, Indonesia. It includes plan and section views of the excavation stages, showing the use of steel sheet piles and H-beams for temporary shoring. The shoring is removed and backfill added in stages as the excavation depth increases until the final excavation depth is reached, then construction of the box culvert structure can begin. Diagrams show the process of building foundation, walls and floors slab by slab while dismantling bracing levels.

Uploaded by

SWL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
514 views

Underpass Box Culvert 1

The document describes a deep braced excavation method for a box culvert underpass project in Serang, Banten, Indonesia. It includes plan and section views of the excavation stages, showing the use of steel sheet piles and H-beams for temporary shoring. The shoring is removed and backfill added in stages as the excavation depth increases until the final excavation depth is reached, then construction of the box culvert structure can begin. Diagrams show the process of building foundation, walls and floors slab by slab while dismantling bracing levels.

Uploaded by

SWL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 40

UNDERPASS BOX CULVERT PROJECT SERANG - BANTEN

BOX CULVERT
DEEP BRACED EXCAVATION METHOD STATEMENT
UNDERPASS BOX CULVERT PROJECT - SERANG BANTEN

+ 0.000 (Ground Level Existing)

A
A

B King Post-H-Beam…300*300*10*15 (Typ)

Steel Sheet pile - 400.170.15,5mm (Typ)

PLAN VIEW OF STEEL SHEET PILE TEMPORARY SHORING SHEET No: 1 0F 12


Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)

King Post-H-Beam…300*300*10*15 (Typ) SKETCH DRAWING :


ELLUSTRATION OF DEEP EXCAVATION METHOD.
SECTION: A - A (Excavation Stage: 1) SHEET No: 2 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)

King Post-H-Beam…300*300*10*15 (Typ) SKETCH DRAWING :


ELLUSTRATION OF DEEP EXCAVATION METHOD.
SECTION: A - A (Excavation Stage : 2) SHEET No: 3 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)

King Post-H-Beam…300*300*10*15 (Typ) SKETCH DRAWING :


ELLUSTRATION OF DEEP EXCAVATION METHOD.
SECTION: A - A (Excavation Stage : 3) SHEET No: 4 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)

King Post-H-Beam…300*300*10*15 (Typ) SKETCH DRAWING :


SECTION: A - A (Excavation Stage : 4) ELLUSTRATION OF DEEP EXCAVATION METHOD.
SHEET No: 5 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)

-8,600

SOIL NATURAL
-11.900

King Post-H-Beam…300*300*10*15 (Typ) SKETCH DRAWING :


ELLUSTRATION OF DEEP EXCAVATION METHOD.
SECTION: A - A (Excavation Stage : 5)
SHEET No: 6 0F 12
B

H-Beam.300*300*10*15 (Typ)

-11.900

- 8,600
A
A

King Post-H-Beam…300*300*10*15 (Typ) B King Post-H-Beam…300*300*10*15 (Typ)

Steel Sheet pile - 400.170.15,5mm (Typ)

PLAN VIEW OF COMPLETED EXCAVATION, STRUT & BRACING OF TEMPORARY SHORING

SKETCH DRAWING :
ELLUSTRATION OF DEEP EXCAVATION METHOD.
SHEET No: 7 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)
+ 0.000 (GL. Exis't)

H-Beam.300*300*10*15 (Typ)

Selected # Selected
Selected Selected -8,600
Bakfill Bakfill CONCRETE SLAB Bakfill Bakfill

-11.900
King Post-H-Beam…300*300*10*15 (Typ) SHEET No: 8 0F 12
SECTION: B - B, (Stage 1 Begin to Construction)
Warking Flow chart :
1. Begin to build the Foundation of the building
2. Selected backfill both side of foundation
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)
+ 0.000 (GL. Exis't)

H-Beam.300*300*10*15 (Typ)

Selected wall wall wall wall wall Selected


Bakfill Bakfill

# Selected
Selected Selected Bakfill Selected -8,600
Bakfill CONCRETE SLAB Bakfill Bakfill

-11.900

King Post-H-Beam…300*300*10*15 (Typ)


SECTION: B - B, (Stage 2 Begin to build of Wall)

Warking Flow chart :


1. To build the Walls of the building
2. Dismantle the struts and braced level by level and build floor slab accordingly
3. Selected backfill both side the building continued.
4. Repeat procedures 2 and 3 till completed of the building.

SKETCH DRAWING :
ELLUSTRATION OF DEEP EXCAVATION METHOD.
SHEET No: 9 0F 12
Steel Sheet pile - 400.170.15,5mm (Typ) H-Beam…300*300*10*15 (Typ)
+ 0.000 (GL. Exis't)

H-Beam.300*300*10*15 (Typ)

wall wall wall wall wall

wall wall wall wall wall


Selected Selected
Bakfill Bakfill

Selected #
Selected Selected Selected - 8,600
Bakfill Bakfill CONCRETE SLAB Bakfill Bakfill

-11.900

King Post-H-Beam…300*300*10*15 (Typ)


SECTION: B - B, (Stage 3 Continued to build of second stage
Wall) SHEET No: 10 0F 12

Warking Flow chart :


1. To build the Walls of the building
2. Dismantle the struts and braced level by level and build floor slab accordingly
3. Selected backfill both side the building continued.
4. Repeat procedures 2 and 3 till completed of the building.
5. Continued repeat procedures 2 and 3 till completed of the building
Steel Sheet pile - 400.170.15,5m m (Typ) H-Beam …300*300*10*15 (Typ)
+ 0.000 (GL. Exis't)

H-Beam.300*300*10*15 (Typ)

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall


Selected Selected
Bakfill Bakfill

Selected # Selected
Selected Selected - 8,600
Bakfill Bakfill CONCRETE SLAB Bakfill Bakfill

-11.900
King Pos t-H-Beam …300*300*10*15 (Typ)

SECTION: B - B, (Stage 4 Continued to build stage of Wall)

Warking Flow chart :


1. To build the Walls of the building SHEET No: 110F 12
2. Dismantle the struts and braced level by level and build floor slab accordingly
3. Selected backfill both side the building continued.
4. Repeat procedures 2 and 3 till completed of the building.
5. Continued repeat procedures 2 and 3 till completed of the building
Steel Sheet pile - 400.170.15,5m m (Typ) H-Beam …300*300*10*15 (Typ)
+ 0.000 (GL. Exis't)

H-Beam.300*300*10*15 (Typ)

wall wall wall wall wall


Selected Selected
Bakfill Bakfill

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall

Selected Selected
Bakfill Bakfill

wall wall wall wall wall


Selected Selected
Bakfill Bakfill

Selected # Selected
Selected Selected - 8,600
Bakfill Bakfill CONCRETE SLAB Bakfill Bakfill

-11.900
King Pos t H-Beam ….*... (Typ)
SECTION: B - B, (Stage 5 Continued to build stage of Wall) SHEET No: 12 0F 12

Warking Flow chart :


1. To build the Walls of the building
2. Dismantle the struts and braced level by level and build floor slab accordingly
3. Selected backfill both side the building continued.
4. Repeat procedures 2 and 3 till completed of the building.
5. Continued repeat procedures 2 and 3 till completed of the building
PT. MULTIKREASI DEVELINDO
GENERAL CONT RACT OR
Jl. Arjuna Selatan No 37 - Kemanggisan - Jakarta - Indonesia

PROPOSAL PENAWARAN HARGA


UNT UK PROYEK
UNDERPASS DOUBLE CELL BOX CULVERT
SERANG – BANT EN.

Prepared By :
PT. MULTI KREASI DEVELINDO
PT. MULTIKREASI DEVELINDO

T ABEL OF CONT ENT

1. SUMMARY

2. PRELIMINARY

3. TEMPORARY WORK

4. BORE PILE FOUNDATION

5. UNDERPASS BOX CULVERT

6. PEMINDAHAN JALAN SEMENTARA

7. VARIATION ORDER (VO)


SUMMARY
Proyek : Underpass Box Culvert
Pemilik :
Biaya : Main Summary

Item Pekerjaan Amount


No DESCRIPTION ( Rp )

MAIN SUMMARY

BILL 1.0 Preliminaries -

BILL 1.1 Temporary Work


- Shoring H Beam dan steel sheet pile (Turap penahan tanah) -
- Jembatan darurat dan perkuatan Rel Kereta Api (By Other)

BILL 1.2 Bore Pile Foundation -

BILL 1.3 Underpass Box Culvert -

BILL 1.4 Pemindahan Jalan Semenatara (By Other) -

BILL 1.5 Variation Order (VO) -

Total (1) -
Profit : ...% -
Total (2) -
PPH :..% -
Total (3) -
PPN :10% -
Grand Total -
BILL 1.0 PRELIMINARIES
BILL NO. 1.0. CONSTRUCTION PRELIMINARIES W ORK.

Project : Underpass Box Culvert


Owner : PT. .....
Budget : PreliminarY

No DESCRIPTION Unit Qua ntity Unit Price Amount


( Rp ) (Rp)

CONSTRUCTION PRELIMINARIES.

Allow for preliminaries for the necessary execution of the


works in accordance with the conditions of contract,
A LS 1 -
specifications and drawings including, but not limited to
the followings :

- Employer's facilities (Site Office)


- Contractor facilities
- Temporary works
- Insurance
- Contractor’s Storage Sheds
- Site clearing
- Removal of rubbish
- Testing of materials
- Protection of the works
- Control of noise and polution
- Cleaning the works upon completion
- Complying with statutory requirement
- Local Transportation
- Man Power
- Temporary Access
- Temporary Buildings
- Siting of Temporary Structures
- Contractor’s Site Office and other Site Accommodation
- Temporary Site Accommodation and other facilities for the Employer and the Project Manager
- Site Hoarding
- Telephones
- W ater
- Lighting and Power
- General Scaffolding and Staging
- Shoring, Propping and Strutting
- Removal of W ater
- Temporary Drainage
- Fire Protection
- Lightning Protection
- Signboard

- Havy Equipment as follow :


1. Excavator
2. Bolduzer
3. Compactor machine
4. Mobile Crane 25 Ton capacity
6. Dump truct
7. Air Compressor
8. Genset
9. Jack Hamer
10. Truck engkel
11. Vibrator
12.Bar bending machine
13. W elding machine
14. Light track
15. Stamper
16. Compactor mesin kecil
17. Avansa
18. Sepeda motor
19. Theodolit
20. W aterpass

TOTAL -
CARRIED TO SUMMARY
BILL. 1.1 TEMPORARY WORK
BILL NO. 1.1 TEMPORARY W ORK
Proyek : Underpass Box Culvert
Pemilik
Biaya Temporary W ork
No DESCRIPTION Unit Qua ntity Unit Price Amount
( Rp ) (Rp)
ALL QUANTITIES ARE PROVISONAL SUM.

PRELIMINARIES
Allow for preliminaries for the necessary execution of the
works in accordance with the conditions of contract,
Ls 1,00 -
specifications and drawings including, but not limited to the
followings :
- Employer's facilities (Site Office)
- Contractor facilities
- Temporary works
- Insurance
- Storage
- Site clearing
- Removal of rubbish
- Testing of materials
- Protection of the works
- Control of noise and polution
- Cleaning the works upon completion
- Complying with statutory requirement
- Man Power
- Havy Equipment
- Transportation
- Equipment mobilization and demobilization of boring with
rig boring
- Safety dan HSE

Total -
Previous sheet -
TEMPORARY SHORING WORKS (Turap penahan
tanah)
A Temporary support as Schaffolding and acessories item 1,00 -

H-Beam Pile
Driving & Extracting For H-Pile (as King Post Pile)
B m 960,00 -
H.300.300.10.15 L =12000mm
Temporary Supply of H-Pile (as King Post Pile)
C ton 90,00 -
H.300.300.10.15 L =12000mm

Wale & Strut Installation & demolised H-beam


D m 1.770,00 -
300.300.10.15

E Wale & Strut Temporary Supply of H-beam 300.300.10.15 ton 165,94 -

Strut/ Steel support


Wale & Strut Installation & demolised H-beam
F m 876,00 -
300.300.10.15

G Wale & Strut Temporary Supply of H-beam 300.300.10.15 ton 82,13 -

Wale & Strut Installation & demolised H-beam


H m 416,00 -
300.300.10.15

I Wale & Strut Temporary Supply of H-beam 300.300.10.15 ton 39,00 -

Wale & Strut Installation & demolised H-beam


J m 1.770,00 -
300.300.10.15

K Wale & Strut Temporary Supply of H-beam 300.300.10.15 ton 165,94 -

Wale & Strut Installation & demolised H-beam


L m 160,00 -
300.300.10.15

M Wale & Strut Temporary Supply of H-beam 300.300.10.15 ton 15,00 -

Temporary Ground Anchor termasuk kelengkapannya (jika


N Nos -
diperlukan)

O Miscellaneous Metal Work ton 5,58 -

Steel Sheet Pile -


Sheet Pile Driving & Extration
P m2 1.536,00 -
(400*170*15.5t, Penetration Depth = 12000mm)
Temporary Supply of Sheet Piles
Q ton 1.167,36 -
(400*170*15.5t, Penetration Depth = 12000m)

Sheet Pile Driving & Extration


R m2 1.000,00 -
(400*170*15.5t, Penetration Depth = 10000mm)
Temporary Supply of Sheet Piles
S ton 760,00 -
(400*170*15.5t, Penetration Depth = 10000mm)

Sheet Pile Driving & Extration


T m2 800,00 -
(400*170*15.5t, Penetration Depth = 8000mm)
Temporary Supply of Sheet Piles
U ton 608,00 -
(400*170*15.5t, Penetration Depth = 8000mm)

Sheet Pile Driving & Extration


V m2 480,00 -
(400*170*15.5t, Penetration Depth = 6000mm)
Temporary Supply of Sheet Piles
W ton 364,80 -
(400*170*15.5t, Penetration Depth = 6000mm)

TOTAL -
CARRIED TO SUMMARY
BILL.1.1 BORE PILE FOUNDATION
BILL NO. 1.2 PEKERJAAN PONDASI BORE PILE
Proyek : Underpass Box Culvert
Pemilik 0
Biaya : Bore Pile

No DESCRIPTION Unit Qua ntity Ha rga Sa tua n Jumla h


( Rp ) (Rp)

ALL QUANTITIES ARE PROVISONAL SUM

BORED PILE
PRELIMINARIES

Allow for preliminaries including materials, labour


and equipment, site mobilisation and demobilisation,
A accomondation. Acces etc. for the necessary Item 1,00 -
execution of the works in accordance with the
conditions of contract, specifications and drawings,

- Construction plant
- Employer's facilities
- Contractor facilities
- Temporary works
- Insurance
- Storage
- Removal of robbish
- Testing of materials
- Protection of the works
- Control of noise and polution
- Cleaning the works upon completion
- Complying with statutory requirement
- Man Power
- Havy Equipment
- Transportation

PENGUKURAN
Biaya untuk observasi dan pengukuran kembali letak
atau posisi titik-titik :
B Bor Pile Dia 800 mm kedalaman 20,90 meter ttk 24,00 -

PENGEBORAN
Biaya untuk pengeboran pada :
C Bor Pile Dia 800 mm kedalaman 20,90 meter m 501,60 -

DISPOSAL
Disposal/pembuaangan tanah bekas bor pile D 800
D m3 315,00 -
mm kedalaman 20.90 meter

PEKERJAAN PENGECORAN BETON.


Re a dy Mix . Concre te . K-300
Biaya untuk cor beton berikut casing pada :
E Conrete Pile Dia 800 mm kedalaman 20,90 meter m3 194,43 -

REINFORCEMENT.
Harga sudah termasuk pemotongan ujung kait,
penekukan dan transportasi besi diarea proyek
dan pembersihan.
F D. 16 mm kg 6.746,03 -
G D. 13 mm kg 6.471,26 -

TOTAL -
CARRIED TO SUMMARY
BILL 1.3 UNDERPASS BOX CULVERT
BILL NO. 1.2 PEKERJAAN PONDASI BORE PILE
Proyek : Underpass Box Culvert
Pemilik 0
Biaya : Bore Pile

No DESCRIPTION Unit Qua ntity Ha rga Sa tua n Jumla h


( Rp ) (Rp)

ALL QUANTITIES ARE PROVISONAL SUM

BORED PILE
PRELIMINARIES

Allow for preliminaries including materials, labour


and equipment, site mobilisation and demobilisation,
A accomondation. Acces etc. for the necessary Item 1,00 -
execution of the works in accordance with the
conditions of contract, specifications and drawings,

- Construction plant
- Employer's facilities
- Contractor facilities
- Temporary works
- Insurance
- Storage
- Removal of robbish
- Testing of materials
- Protection of the works
- Control of noise and polution
- Cleaning the works upon completion
- Complying with statutory requirement
- Man Power
- Havy Equipment
- Transportation

PENGUKURAN
Biaya untuk observasi dan pengukuran kembali letak
atau posisi titik-titik :
B Bor Pile Dia 800 mm kedalaman 20,90 meter ttk 24,00 -

PENGEBORAN
Biaya untuk pengeboran pada :
C Bor Pile Dia 800 mm kedalaman 20,90 meter m 501,60 -

DISPOSAL
Disposal/pembuaangan tanah bekas bor pile D 800
D m3 315,00 -
mm kedalaman 20.90 meter

PEKERJAAN PENGECORAN BETON.


Re a dy Mix . Concre te . K-300
Biaya untuk cor beton berikut casing pada :
E Conrete Pile Dia 800 mm kedalaman 20,90 meter m3 194,43 -

REINFORCEMENT.
Harga sudah termasuk pemotongan ujung kait,
penekukan dan transportasi besi diarea proyek
dan pembersihan.
F D. 16 mm kg 6.746,03 -
G D. 13 mm kg 6.471,26 -

TOTAL -
CARRIED TO SUMMARY
BILL 1.3 UNDERPASS BOX CULVERT
BILL NO. 1.3 BOX CULVERT & ROAD RAMP

Proyek : Uderpass Box Culvert


Pemilik
Biaya : Road Ramp & Box Culvert

No DESCRIPTION Unit Quantity Harga Satuan Jumlah


( Rp ) (Rp)
ALL QUANTITIES ARE ROVISIONAL SUM

BILL NO. 1.3 - PEKERJAAN TANAH

Pembersihan Lapangan
A Pembersihan lapangan sesuai dengan luasan yang diberikan
ls 1,00 -
pada gambar dengan luas area = 5,550 m2

Pekerjaan Bongkaran
B Bongkar/galian jalan Existing termasuk trotoar median dan
m2 5.211,68 -
road Kerb
C Pemadatan tanah m2 5.211,68 -

Pekerjaan Galian
Volume galian dihitung net, sehingga, volume satu meter
kubik galian sama dengan
satu meter kubik timbunan.Kontraktor harus sudah
memasukkan dalam harga satuan
pada pekerjaan tanah ini faktor bulking / shrinkage yang
diperkirakannya cukup dan
pengambilan besaran faktor-faktor tersebut sepenuhnya
menjadi tanggung jawab
Kontraktor.

Galian Tanah biasa dengan tanah galian ditimbun pada


timbunan
sementara untuk selanjutnya akan digunakan pada
pekerjaan timbunan.

D Galian tanah Box Culvert kedalaman 8.60 meter m3 2.322,00 -


E Galian Underpass Road Ramp (8,60 - 0,55 deep) m3 22.950,25 -
F Sumur tampung (3000 x 3000 x 3000mm) m3 200,00 -
G Box pompa (1500 x 1500 x 1500mm) m3 36,75 -

Pekerjaan Timbunan Tanah Bekas Galian


H Box Culvert kedalaman 8.60 meter m3 619,20 -
I Underpass Road Ramp (8,60 - 0,55 deep) m3 7.190,29 -
J Sumur tampung (3000 x 3000 x 3000mm) m3 121,00 -
K Box pompa (1500 x 1500 x 1500mm) m3 30,00 -
-
Disposal
Pembuangan tanah ke luar lokasi proyek pada tempat yang
diperbolehkan sesuai keinginan kontraktor termasuk
pengurukan dan pemadatan pada tempat pembuangan jika
diperlukan.

L Pembuangan tanah bekas galian m3 17.548,51 -


Bongkar/galian jalan Existing termasuk trotoar median dan
M m3 2.084,67 -
road Kerb

Total -
No DESCRIPTION Unit Qua ntity Ha rga Sa tua n Jumla h
( Rp ) (Rp)

Previous sheet -
BILL NO. 2 - PEKERJAAN KONSTRUKSI BETON.

Bobokan Kepala Tiang Pancang


Pembobokan kepala tiang pancang termasuk pembuangan
beton sisa bobokan, pembekokan serta pemotongan besi
tulangan tiang untuk dimasukan ke pile cap.
A Soldier Pile D 800 mm ( h= 12.90 m ) no 24,00 0,00

Compacted sand layer


B 100mm thick compacted sand layer m2 3.983,51 0,00

PEKERJAAN BETON BERTULANG


Harga untuk pekerjaan beton termasuk perapiahan,
pembuatan sparing pembersihan, penutupan kembali
lobang bekas baut juga perawatan (Curing), pemadatan
memakai Vibrator mesin, dan pembongkaran cetakan.

Ready Mix. Concrete. K-175


Lean concret tebal 50mm
Box culve rt
C Base Slab tebal 800mm m2 151,25 0,00
D Dinding tebal 500mm m2 12,10 0,00
E Pedestrian tebal 150mm m2 48,00 0,00

Unde rpa ss Roa d Ra mp


F Base Slab tebal 450mm m2 2.549,33 0,00
G Dinding tebal 500mm m2 263,72 0,00
H Gutter/saluran air (500mm x 350mm) m2 38,40 0,00
I Pedestrian tebal 150mm m2 879,08 0,00
J Sumur tampung (3000 x 3000 x 3000mm) m2 33,62 0,00
K Box pompa (1500 x 1500 x 1500mm) m2 8,00 0,00

Re a dy Mix . Concre te . K-300


Box Culve rt 0,00
L Base Slab tebal 800mm m3 110,40 0,00
M Dinding tebal 500mm m3 217,92 0,00
N Suspended slab 500mm m3 99,00 0,00
O Pedestrian tebal 150mm m3 7,20 0,00
P Dinding Cable duct tebal 150mm m3 7,43 0,00
Precast concrete cover cable duct tabal 100mm (Jalan
Q m3 3,30 0,00
setapak)

Unde rpa ss Roa d Ra mp


R Base Slab tebal 450mm m3 1.179,56 0,00
S Dinding tebal 500mm m3 1.197,36 0,00
T Gutter/saluran air (500mm x 350mm) m3 125,88 0,00
U Pedestrian tebal 150mm m3 131,86 0,00
V Sumur tampung (3000 x 3000 x 3000mm) m3 74,00 0,00
W Box pompa (1500 x 1500 x 1500mm) m3 9,25 0,00

Total 0,00
No DESCRIPTION Unit Quantity Harga Satuan Jumlah
( Rp ) (Rp)

Previous sheet 0,00


REINFORCEMENT.
Harga sudah termasuk pemotongan ujung kait, penekukan,
termasuk untuk transportasi besi beton diarea proyek.
Berat besi beton telah ditetapkan dengan menggunakan
berat nominal berikut ini dan untuk semua berat nominal.

6 mm - 0.222 kg / meter
8 mm - 0.395 kg / meter
10 mm - 0.617 kg / meter
12 mm - 0.887 kg / meter
13 mm - 1.042 kg / meter
16 mm - 1.578 kg / meter
19 mm - 2.250 kg / meter
22 mm - 2.983 kg / meter
25 mm - 3.853 kg / meter

Reinforcing steel bar, BJTD 40 in :


Box Culvert 0,00
A Base Slab tebal 800mm kg 32.347,10 0,00
B Dinding tebal 500mm kg 58.741,92 0,00
C Suspended slab 500mm kg 30.350,32 0,00
D Pedestrian tebal 150mm kg 1.658,68 0,00
E Dinding Cable duct tebal 150mm kg 1.171,86 0,00
Precast concrete cover cable duct tabal 100mm (Jalan
F kg 854,35 0,00
setapak)

Underpass Road Ramp


G Base Slab tebal 450mm kg 212.965,00 0,00
H Dinding tebal 500mm kg 302.706,88 0,00
I Gutter/saluran air (500mm x 350mm) kg 13.785,49 0,00
J Pedestrian tebal 150mm kg 15.558,18 0,00
K Sumur tampung (3000 x 3000 x 3000mm) kg 20.570,53 0,00
L Box pompa (1500 x 1500 x 1500mm) kg 3.038,38 0,00

Total 0,00
No DESCRIPTION Unit Qua ntity Ha rga Sa tua n Jumla h
( Rp ) (Rp)

Previous sheet 0,00


FORM WORK
Harga untuk pekerjaan cetakan / acuan (bekisting )
termasuk sudut-sudut sisi-sisi miring , pembuatan
penopang, pembuatan,pemindahan, pemotongan besi dan
pembersihan dipasang pada :

Box Culve rt
A Base Slab tebal 800mm m2 37,60 0,00
B Dinding tebal 500mm m2 883,20 0,00
C Soffit Support Suspe nde d sla b 500mm m2 198,00 0,00
D Pedestrian tebal 150mm m2 4,20 0,00
E Dinding Cable duct tebal 150mm m2 99,00 0,00
Precast concrete cover cable duct tabal 100mm (Jalan
F m2 10,56 0,00
setapak)

Unde rpa ss Roa d Ra mp


G Base Slab tebal 450mm m2 560,56 0,00
H Dinding tebal 500mm m2 4.833,04 0,00
I Gutter/saluran air (500mm x 350mm) m2 486,72 0,00
J Pedestrian tebal 150mm m2 68,33 0,00
K Sumur tampung (3000 x 3000 x 3000mm) m2 218,00 0,00
L Box pompa (1500 x 1500 x 1500mm) m2 27,00 0,00

Pe rke ra sa n ba da n ja la n
M Finishing Asphalt tebal 50mm m2 2.318,30 0,00

Pe ke rja a n la in-la in.


Pengaman Underpass (Gawang portal) H beam 300 x
N 300mm (T= 6,2 x L = 11,1 meter) termasuk pondasi gawang Nos 2,00 0,00
, accesories dan finishing.
O Saluran pembuang air termasuk Pipa PVC, accesories m' 66,00 0,00
Plat grill 500 x 50mm termasuk steel frame dan anchor
P m' 623,31 0,00
(Gutter)
Plat grill 800 x 800mm termasuk steel frame (Sumur
Q Nos 2,00 0,00
Tampung)
R Railing besi tinggi 800mm (Carbon steel dia 50mm) m' 439,66 0,00
S Dinding parapet 1/2 bata termasuk finishing pada cable duct m2 18,15 0,00

Pagar pengaman sementara Corrogated Zink + Frame Kayu


T m 583,66 0,00
kaso 5/7 termasuk pondasi.

De w a te ring
U - Dewatering (lots) ls 1,00 0,00
V - Deep Well ls 1,00 0,00

TOTAL 0,00
CARRIED TO SUMMARY
BILL 1.4 PEMINDAHAN JALAN SEMENTARA
BILL NO. 1.4 PEMINDAHAN JALAN SEMENTARA

Proyek : Ude rpa ss Box Culve rt


Pemilik
Biaya : Pemindahan Jalan Sementara

NO. DESCRIPTION Unit Qua ntity Unit Price Amount


( Rp ) (Rp)
ALL QUANTITIES ARE [ROVISIONAL SUM

Pe ke rja a n Pe rkua ta n Pe rlinta sa n Se me nta ra .

Pe k. Pe rsia pa n
Pembersihan lapangan sesuai dengan luasan yang diberikan
A pada gambar dengan luas area (104 meter x 5 meter = 520 m2 ls 0,00

Pe rkua ta n pe rlinta sa n
B Pemadatan m2 0,00
Perapihan jalan existing ( 50 meter kekiri dan 50meter kekanan
C dari Rel KA Existing) m2 0,00

D Sirtu 2/3 m2 0,00


E Plat beton K.300 ( 2440 x 660mm ) termasuk plate besi dll. Nos 0,00
F Post Jaga 2000 x 2000 x 2560mm Nos 0,00
G Portal besi pipa dia 150mm termasuk accesories, pondasi dan Nos 0,00
H finishing
Rambu rambu lalulintas sesuai dengan spec. Nos 0,00
0,00

TOTAL 0,00
CARRIED TO SUMMARY
BILL. 1.5 VARIATION ORDER (VO)
BILL NO. 1.5 VARIATION ORDER (VO)

Project : Underpass Box Culvert


Owner : PT. .....
Budget : VO

No DESCRIPTION Unit Qua ntity Unit Price Amount


( Rp ) (Rp)

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

TOTAL -
CARRIED TO SUMMARY
KUALIFIKASI DAN KLARIFIKASI

1. Proposal kami adalah Indikasi Bill of Quantity secara Provional Sum berdasarkan
gambar yang diberikan dari pemilik proyek Underpass Box Culvert di Serang
kepada PT. MKD, dan semua kuantitas pekerjaan akan dihitung kembali sesuai
dengan Gambar Konstruksi yang dilaksanakan (For Construction darawing) .

2. Proposal kami untuk Bangunan Underpass Box Culvert adalah Indika si Bil of
Quantity berdasarkan hasil perhitungan kami dan tata letak umum serta kriteria
desain yang diberikan oleh Pemberi Tugas kepada PT. MKD dan Setiap
penyimpangan karena perubahan dari Pemberi Tugas, Bill of Quantity harus
dihitung kembali.

3. Bill of Quantity yang kami hasilkan adalah berdasarkan asumsi dari gambar desain
yang kami terima seperti sebagai berikut :
- Bor pile kami asumsikan diameter 800mm.
- Pembesian/Reinforcement dia. 13mm, dia 16mm dan dia 22mm
- Dimensi atau ukuran2 dalam gambar disain tidak jelas.
- Ketebalan perkerasan jalan digambar 500mm diasumsikan menjadi tebal
50mm.
- Penguatan turap pengaman galian tanah kedalaman 8.50 meter menggunakan
Steel Sheet pile 400.170.15.5 dengan Strut bracing H Beam 300.300.10.15 dan
King post pile H beam 300.300.10.15

4. Semua desain sepenuhnya disediakan oleh Pemberi Tugas. Desain semua struktur
permanen dan sementara tidak termasuk dalam penawaran kami atau kami tidak
bertanggung jawab atas Desain dan tata letak bangunan tersebut.

5. Harga kami :
* Tidak termasuk PPH 3%
* Tidak Termasuk PPN 10%
* Berlaku ... (...) bulan
* Berdasarkan nilai tukar Dolar saat ini
* CAR, TPL dan Asuransi lain yang deperlukan akan desediakan oleh Pemberi
tugas
* PT. MKD menyediakan asuransi pekerja dan peralatan yang dimiliki oleh PT.
MKD

6. Kondisi komersial untuk ditinjau ulang dan disepakati bersama setelahnya.

7. Kontraktor berhak atas biaya tambahan dari biaya pendahuluan yang diperpanjang
karena perpanjangan waktu yang disebabkan oleh sesuatu di luar kendali PT.
MKD. Dan Kontraktor berhak atas kompensasi biaya awal karena dampak kuantitas
pekerjaan berkurang secara signifikan dibandingkan dengan BoQ.

8. Area proyek akan diserahkan, berserta akses untuk pekerjaan Operasional


konstruksi alat berat:
a. Pemeliharaan jalan akses utama External akan dilakukan oleh kontraktor lain.
b. Jalan akses internal akan disediakan dan dikelola oleh PT. MKD.

Keamanan External / titik akses dikelola oleh Pemberi Tugas, PT. MKD hanya
menyediakan keamanan internal untuk lingkup pekerjaan kami sendiri.
7. PT MKD menyediakan Power supply sementara untuk kegiatan konstruksi hanya untuk
lingkup pekerjaan kami sendiri.

8. Sumber air untuk pekerjaan akan disediakan oleh Pemberi Tugas

9. Persyaratan Keselamatan PT. MKD sesuai dengan Standar Indonesia (SNI).

13. Asumsi Teknis:


a. Lokasi Pembuangan tanah dan pembuangan tanah sementara akan ditunj uk dan .
menjadi tanggung jawab pemberi tugas.
b. Besi ulir U-39
c. Beton Readymix K. 300 akan disuplay sesuai standar batching plant yang disetuju
oleh pemberi tugas..
d. Area fasilitas sementara yang dibutuhkan oleh PT. MKD akan diberikan oleh
Pemberi Tugas tanpa biaya.
e. Kuantitas rebar remeasure didasarkan pada Bar Bending Schedule yang disetujui,
termasuk laps, kursi, dan lainnya berdasarkan metode kerja.
f. Kapasitas Mobil Crane minimum yang diizinkan yang digunakan adalah 25 T.

14. Item berikut di bawah ini tidak termasuk proposal kami:


a. Lapisan/campuran Integral water proofing.
b. Ruber Water Stop
c. Construction joint, Joint sealent, Dowel dan Expansion Joint
d. Finishing dinding beton
e. Ground Anchor (Temporary dan Permanen)
f. Penerangan selama proses konstruksi
g. Marka jalan
h. Pembongkaran Portal dan system lampu signal perlintasan dan aksesori
i. Perkuatan di perlintasan sementara
j. System penanggulangan banjir
k. Pekerjaan perkuatan Rel Kereta Api
l. Timbunan dan pemadatan Balas
m. Jembatan darurat
n. Pengamanan lintas sementara
o. Sewa lahan untuk pembuangan tanah bekas galian
p. Galian tanah keras/Rock soil dan tanah lumpur
q. Area pembuangan tanah bekas galian, akan disediakan/ditunjuk pemberi tugas.
r. Desain, Gambar, dan Perhitungan untuk semua Pekerjaan.
s. Kenaikan harga
t. Masalah Lingkungan, Risiko Tanah dan Masalah Geoteknis lainnya.
u. Pagar batas sementara.
v. Proteksi petir dan proteksi yang terkait termasuk grounding system.
w. Semua lisensi dan izin untuk IMB, AMDAL, IPB, third party sertifikasi.
x. Pekerjaan Koordinasi dan Pembangunan dalam Koneksi dengan pihak lain
y. Pekerjaan Mekanical, Electrical dan Plumbing.

Jakarta, .. Agustus 2019


PT. MULTI KREASI DEVELINDO
PT. MULTIKREASI DEVELINDO
GENERAL CONTRACTOR
Jl. Arjuna Selatan No 37 - Kemanggisan - Jakarta - Indonesia

THANK YOU