Network Diagram: Sample Problems

This document provides a sample network diagram problem and its solution. It contains: 1) An activity-on-arrow network diagram with 6 activities and their early start (ES), early finish (EF), late start (LS), and late finish (LF) times calculated. 2) Identification of the critical path consisting of activities 1-2, 2-5, and 5-6, which have zero float/slack time. 3) Calculation of the float/slack time for each non-critical path.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views

Network Diagram: Sample Problems

This document provides a sample network diagram problem and its solution. It contains: 1) An activity-on-arrow network diagram with 6 activities and their early start (ES), early finish (EF), late start (LS), and late finish (LF) times calculated. 2) Identification of the critical path consisting of activities 1-2, 2-5, and 5-6, which have zero float/slack time. 3) Calculation of the float/slack time for each non-critical path.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 6

NET WORK

DIAGRAM
SAMPLE PROBLEMS
Solving for ES and EF Activity ES EF
1-2 0 5
Early Finish = Early Start + Duration 1-3 0 2
3-4 2 6
2-4 5 8
ES EF 4-5 6 11
0+5=5 2-5 5 9
2
ES 5 ES EF
0 5+4=9
1 5
ES EF

2 3 8+3=11

3
3 4
ES EF
4 ES EF
0+2=2
2+4=6
Solving for LS and LF Activity LF LS
4-5 11 8
Late Start = Late Finish - Duration 5-2 11 5
LF LS 4-2 8 5
9-4=5 4-3 8 4
1-2 5 0
2
1-3 4 2
LF LS 5
5-5=0 LF
1 5 11
LF LS 3
4-2=2 2

3
3 4
LF LS
8-4=4 4 LF LS
11-3=8
ACTIVITY LS ES SLACK or LF EF SLACK

1-2 0 0 0 5 5 0
1-3 2 0 2 4 2 2
2-4 5 5 0 8 8 0
2-5 5 5 0 9 9 0
3-4 4 2 2 8 6 2
4-5 8 8 0 11 11 0
a.) The length of each path
b.) The critical path
c.) The amount of float time for each path

10+10=10 10+8=18
0 10-10=0
START 23-4=19
10 8
1 2 4
19-8=11
11-6=5

4
6 13

25-2=23 24
6+12=18
3 5 6
0+6=6 12 2 END
23-12=11 23+2=25

PATH LENGTH IN WEEKS FLOAT/SLACK

1-2-4-5-6 10+8+4+2 = 24 25-24=1


1-2-5-6 10+13+2=25 25-25=0
1-3-5-6 6+12+2=20 25-20=5
Solve for value of Float or Slack
0 10 10+8=18
START 10 8
1 2 4 23-4=19
10-10=0 19-8=11
11-6=5 23-13=10

4
6 13

22 24
3 5 6
12 2 END
23-12=11 25-2=23 25

ACTIVITY LS ES FLOAT (LS-ES) Critical Path – activities with ZERO


1-2 10-10 = 0 At (1) = 0 0 FLOAT TIME
1-3 11-16 = 5 6-6 = 0 5 1-2; 2-5; 5-6
2-4 19-8 =11 0+10 =10 1
2-5 23-13 =10 0+10=10 0 Shared Slack or Shared Float
3-5 23-12 = 11 0+6=6 5 1-3; 3-5 5
4-5 23-4 = 19 10+8=18 1
5-6 25-2 =23 10+13=23 0 2-4; 4-5 1