Eaves Over Required Windows Not - Minimum Over From The Side & Rear Property Lines
Eaves Over Required Windows Not - Minimum Over From The Side & Rear Property Lines
A. Secure
B. Erection
C. Site work
47. canopy shall be removed ____days after protection no longer
required.
A. 30
B.15
C. 20
48. Located partly in one (1) fire zone and partly in another
A. 150-150mm
B. 200-300mm
C. 150-300mm
50. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
HAVE A DIVERSIFIED WORKING EXPERIENCE OF AN ARCHITECT OR
ENGINEER FOR HOW MANY YEARS?
A. 6
B. 4
C. 5
D. 7
51. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
BE A REGISTERED ?
A. Architect
B. Engineer
C. Urban Planner
D. Landscape Architect
E. A and B
52. IN QUALIFICATION FOR BEING AN BUILDING OFFICIAL, YOU MUST
BE A MEMBER OF A ACCREDITED ORGANIZATION OF NOT LESS THAN
HOW MANY YEARS
A. 2
B. 1.5
C. 3
D. 5
53. HOW MANY SETS OF PLANS AND SPECIFICATION ARE NEEDED FOR
THE REQUIREMENTS OF BUILDING PERMIT?
A. 5
B. 4
C. 6
D. 7
54. HOW MANY SETS OF PLANS AND SPECIFICATION ARE NEEDED FOR
THE REQUIREMENTS OF BUILDING PERMIT?
A. 800-900
B. 700-900
C. 900-1200
56. Groups H, I occupancies w/o seats, line of travel to exit door by an
aisle is not > ______ m
A. 45
B. 30
C. 60
57. For Protective Nets/Screen the G.I wire gauge must be
________mm mesh _____ net; canvas
A. 2.3
B. 2.2
C. 2.4
D. 2.5
59. For Protection of Pedestrians during Construction or
Demolition Canopies must _______m above the railway, live load 600
kg per sq.m.
A. 2.5
B. 2.6
C. 2.4
D. 2.3
60. for Protection of Pedestrians during Construction or Demolition
the Temporary walkway will be at least _____m wide (during
construction)
A. 1.2
B. 1.3
C. 1.4
D. 1.5