Project Management Cpm/Pert
Project Management Cpm/Pert
CPM/PERT
Professor Ahmadi
Slide
1
Learning Objectives
Understand how to plan, monitor, and control
projects using PERT/CPM.
Determine earliest start, earliest finish, latest
start, latest finish, and slack times for each
activity.
Understand the impact of variability in activity
times.
Understand important role of software such as
Microsoft Project in project management.
Slide
2
Project Planning
Specific questions that are considered:
What is goal or objective of project?
What are various activities (or tasks) that constitute
project?
How are these activities linked?
What are precedence relationships between activities?
What is time required for each activity?
What other resources (such as labor, raw materials, and
machinery) are required for each activity?
Slide
3
Project Scheduling
Questions to be answered:
When will project be completed?
What is schedule for each activity?
What are critical activities in project?
What are non-critical activities in project?
By how much can a non-critical activity be delayed
without affecting completion time of entire project?
If variability in activity times is considered, what is
probability project will be completed by a specific
deadline?
Slide
4
Project Controlling
Control of large projects involves close monitoring of
schedules, resources, and budgets.
Questions to be answered:
At any particular date or time, is project on schedule,
behind schedule, or ahead of schedule?
At any particular date or time, is money spent on
project equal to, less than, or greater than budgeted
amount?
Are there enough resources available to finish project
on time?
If project is to be finished in shorter amount of time,
what is best way to accomplish this at least cost?
Slide
5
Gantt Chart for a New
Voice Recognition System
a. Design System
b. Build Prototype
c. Test Prototype
d. Estimate Material Costs
e. Estimate Labor Costs
f. Refine Design
g. Build the final Product
h. Demonstrate the product
i. Market the Product
Slide
6
Drawing Project Network
Slide
7
CPM and PERT
Network techniques
Developed in 1950’s
CPM by DuPont for chemical plants (1957)
PERT by Booz, Allen & Hamilton with the U.S. Navy,
for Polaris missile (1958)
Consider precedence relationships and
interdependencies
Each uses a different estimate of activity times
Slide
8
CPM/PERT
CPM stands for Critical Path Method. It is Project
Scheduling with Known Activity Times (CPM)
Slide
9
Project Network
A project network can be constructed to model
the precedence of the activities.
The nodes of the network represent the
activities.
The arcs of the network reflect the precedence
relationships of the activities.
A critical path for the network is a path
consisting of activities with zero slack.
Slide
10
Determining the Critical Path
Slide
11
Determining the Critical Path
Slide
12
Determining the Critical Path
Slide
13
Uncertain Activity Times
Slide
14
Uncertain Activity Times
Slide
15
Network for construction of a new building
Example 1
A project comprises of the following activities and their predecessors.
Slide
16
Critical Path Method (CPM) Example 2
A project comprises of the following activities and their predecessors.
Immediate Expected
Activity Predecessor time (days)
A - 2
B - 6
C A 4
D B 3
E C, D 1
a. Draw a network and determine the critical path. How long will it
take to complete the project?
Slide
17
Program Evaluation and Review Technique
(PERT) Example 3
For the following activities and their predecessors and the three time
estimates (days):
Activity Predecessor Optimistic (a) Most Probable (m) Pessimistic (b)
A - 4 7.5 8
B - 1 2 3
C A 4 5 6
D B 7 8 9
E C, D 6 7 14
Slide
18
Network for construction of a new building
Refer to Example 1-Your turn
A project comprises of the following activities and their predecessors.
Draw a network for this project and determine the critical path. How
long would it take to finish this project?
Slide
19