Materials Quality Control in Concrete NEW
Materials Quality Control in Concrete NEW
1. Paste
2. Mineral aggregates
Paste:
is the mixture of water and cement
Mineral Aggregates:
compose of fine and coarse
Composition of Concrete:
In fresh concrete, the individual particles of
aggregates and cement are suspended and separated
by thin layers of water. This makes the mix plastic and
workable.
WIDTH = 6 INCHES
HEIGHT = 6 INCHES
Beam Specimens
Area = L x W
21” x 6”
Using the same rammer used in = 126 sq.m
concrete cylinder sample Note : 1 blow per 2 sq.inch
2,204.60 lbs 18
FS = 2.40 tons x x = 440.92 psi
ton (6x6x6)
MPa
FS = 440.92 psi x 0.006895 = 3.04 MPa
psi
Load applied at a
constant rate within
the range of 20 to
50 psi/sec.
For Cylinder
P where:
CS =
A P = Load
A = Area
π D2
Cross Sectional Area =
4
3.1416 (6)2
A=
4
A = 28.27 in2
EXAMPLE
note:
3,000 psi @ 28 days
3,500 psi @ 14 days
Drilled Cores
Significance and Use:
7 3
9
6 4
5
When the measurement of any core is less than the
specified thickness by more than 25 mm, additional
cores will be taken at no less than 5 m. intervals
parallel to the center line in each direction, from the
affected location. Obtaining of core samples will only
be stopped when core which is not deficient in
thickness by more than 25 mm. is found in each
direction.
Drilled Cores
Significance and Use:
E. Joint Filler
a. Poured Joint Filler
Tests: 1 – Q, Quality Test on each type of
ingredient for each shipment
Minimum testing requirements
Item 311 – Portland Cement Concrete Pavement
F. Special Curing Agents
Tests: 1 – Q, Quality Test for each shipment
G. Steel Bars
Tests: For every 10,000 kgs or fraction
thereof for each size
1 – Q, Quality Test (Bending, Tension
and Chemical Analysis
Minimum testing requirements
Item 311 – Portland Cement Concrete Pavement
H. Concrete
Tests: Flexural Strength Test on concrete
Beam Samples:
1-set consisting of 3 beam samples shall
represent a 330 sq.m. of pavement, 230mm depth, or
fraction thereof placed each day. Volume of
concrete not more than 75 cu.m.
I. Completed Pavement
Tests: Thickness determination by concrete core
drilling on a lot basis.
Five (5) holes per kilometer per lane or five (5) holes
per 500m when 2 lanes are poured concurrently
Minimum testing requirements
ITEM 405 – STRUCTURAL CONCRETE
F. Steel Reinforcement
Tests: 1-Q, Quality Test for every 10,000kg or fraction thereof for
each size
G. Concrete
Tests: Compressive strength on concrete cylinder samples, 1 set consisting of
three (3) concrete cylinder samples shall be taken each day’s pouring and to present
not more than 75 cu.m of concrete or fraction thereof.
Minimum testing requirements
Item 505 – Riprap and Grouted Riprap
A. Cement:
Tests: 1-Q, Quality Test for every 2000 bags or
fraction thereof
B. Fine Aggregate:
Tests: 1-Q, Quality Test for every 1500 cu.m of
fraction thereof
1-G, Grading for every 75 cu.m or fraction
thereof
C. Stone
Tests: 1 –Q, Quality Test /Inspection Report
E. Water
Tests: 1-Certificate from the Project Engineer of
1-Q, Quality test, if source is questionable
Test Results and Field Application
ITEM DESCRIPTION
1. Portland Cement
• Only Type I Portland Cement shall be used unless otherwise
provided for in the Special Provisions.
• The product of only one mill of any one brand and type of
Portland Cement shall be used on the project unless
otherwise permitted by the Engineer.
0.600 mm ( No. 30 ) -
0.300 mm ( No. 50 ) 5 - 30
0.150 mm ( No. 100 ) 0 - 10
3. Coarse Aggregate
• contain not more than one (1) mass percent of material passing the
0.074 mm ( No. 200 sieve ) by washing nor more than 0.25 mass
percent of clay lumps, nor more than 3.5 mass percent of soft
fragments.
• tie bars shall be deformed bars that are to bent and re-straightened
during construction and shall conform to the requirements of
AASTHO M 31 or M 42.
• dowel bars shall be plain round bars where one-half of the length
shall be painted with one coat of approved lead or tar paint and
shall conform to the requirements of AASTHO M 31 or M42.
• reinforcing steel shall be free from dirt, oil, paint, grease, mill
scale and loose or thick rust which could impair bond of the steel
with the concrete.
6. Joint Fillers
Cement
• cement shall be stored immediately upon delivery at the site
in a weatherproof building which will protect the cement
from dampness.The floor shall be raised from the ground.
• bulk cement, if used, shall be transferred to elevated air tight
weathered proof bins.
• cement bags shall be stacked closed together to reduce air
circulation but should never be stacked against outside walls.
• stack the cement bags so that the first in are the first out
• on small jobs where a shed is not available, bags should be
placed on raised wooden platforms at least 4 to 6 inches
above the ground and water coverings should fit over the pile
and extend over the cement and the platform.
Concrete Aggregates
Reinforcing Steel
• steel bars shall be stored immediately upon delivery at
the site in a weatherproof location which will protect the
steel bars from corrosion. The floor shall be raised from
the ground.
PROPORTIONING, CONSISTENCY AND
STRENGTH OF CONCRETE
Slump Requirements :
- if vibrated, a slump between 37.5 – 75 mm (1-1/2 – 3 inches)
- if not vibrated, a slump between 12.5 – 37.5 mm (½ - 3 inches)
PROPORTIONING, CONSISTENCY AND
STRENGTH OF CONCRETE
Strength Requirements :
• the time elapsed from the time the water is added to the
mix until the concrete is deposited in place at the site, shall
not exceed 45 minutes when concrete is hauled in non-
agitating trucks, nor 90 minutes when hauled in truck
mixers.
• when volumetric measurements are authorized for small
project requiring less than 75 cu.m. of concrete per day of
pouring, the weight proportions shall be converted to
equivalent volumetric proportions. Use of chute is allowed
provided that a weighing scales for determining the batch
weight will be used.
Mixing of Concrete
Longitudinal Joints
• deformed steel tie bars of specified length, size, spacing shall
be placed perpendicular to the longitudinal joints and may
be bent at right angles against the form of the first lane
constructed and straightened into final position before the
concrete of the adjacent lane is placed.
• tie bars shall not be painted or coated with asphalt or other
materials or enclosed in tubes or sleeves.
• when shown on the plans and when the adjacent lanes of
pavement are constructed separately, joint steel side forms
shall be used which will form a keyway along the construction.
Longitudinal Joints
• longitudinal formed joints shall consists of a groove or cleft,
extending downward from and normal to the surface of the
pavement and shall be continuous and be no gaps in either
transverse or longitudinal joints at the intersections of the
joints.
• longitudinal sawed joints shall be cut by means of approved
concrete saws to the depth, width and line shown on the plans
and shall be thoroughly cleaned and immediately filled with
sealer.
• the longitudinal joints shall be sawed before the end of the
curing period or shortly thereafter and before any equipment
or vehicles are allowed on the pavement.
Transverse Contraction Joint/ Weakened Joint
Longitudinal joints
Width = 6mm,
min.
• if the strength of control specimens does not meet the strength requirements and
it is not advisable to obtain cores from the structure due to structural considerations,
payment of the concrete will be made at an adjusted price due to strength deficiency of
concrete specimens as specified hereunder:
Deficiency in Strength of Concrete Specimens Percent (%) of Contract
Percent (%) Price Allowed
Portland Cement
Thank You
and
Good Luck