Project Planning & Monitoring
Project Planning & Monitoring
Scope Management
Time Management
Resource Management
Cost Management
Work Breakdown Structure (WBS) of the project shall be basic tool for defining
the scope baseline
Prepared by Project Monitoring Cell - Kolkata Example – 1 (Scope) Ref. IS 15883 (Part 1) : 2013
Slide No. - 4
2) Activity duration estimating
Contingency planning for activity duration shall include modifying the above calculated
activity duration based on :
1. Activity constraints of time, location, etc.
2. Risks foreseen for the activities
3. Study of the project environment and other subjective issue
Finish to start (FS) : Successor activity to start after the predecessor activity finishes
Start to start (SS) : Successor activity to start after the predecessor activity has
started and is partly complete. So, for some duration both the activities shall take
place simultaneously
Finish to finish (FF) : Successor activity to finish only after the predecessor activity
has finished. In this situation also for some duration both the activities shall take place
simultaneously
Start to finish (SF) : There is a relationship between the start of the predecessor
activity and the finishing of successor activity
Example :
Consider a task involving 160 sqm of fixing timber formwork for the roof slab of a single- storey building. The time
earmarked for completion is four days, when working eight hours per day. If a worker’s team, consisting of one
skilled worker and two unskilled workers can install the formwork at the rate of 5 sqm/day, then :
Prepared by Project Monitoring Cell - Kolkata Example – 3 (Manpower schedule) Slide No. - 9
Planning of consumable material
Material required = (Work quantity required to be executed X Co-efficient of consumption) + Wastage
(Rolling Margin is to considered and added in reinforcement wherever applicable)
Monthly projection of Quantities
SN Activities Unit M1 M2 M3
1 Concrete (M25) Cum 1000 1200 1500
2 Reinforcement MT 100 120 150
Material requirement based on quantity plan
SN Materials Unit Co.eff Wastage M1 M2 M3
1 Concrete
0.4 1% 404 485 606
1.1 Cement MT
1000 x 0.4 x 101% 1200 x 0.4 x 101% 1500 x 0.4 x 101%
0.59 5% 620 743 929
1.2 Sand Cum 1000 x 0.59 x
1200 x 0.59 x 105% 1500 x 0.59 x 105%
105%
0.34 3% 350 420 525
1.3 Aggregate 10 mm Cum 1000 x 0.34 x
1200 x 0.34 x 103% 1500 x 0.34 x 103%
103%
0.37 3% 381 457 572
1.4 Aggregate 20 mm Cum 1000 x 0.37 x
1200 x 0.37 x 103% 1500 x 0.37 x 103%
103%
0.002 1% 2.02 2.42 3.03
1.5 Addmixture MT 1000 x .002 x
1200 x .002 x 101% 1200 x .002 x 101%
101%
1 2.5% 103 123 154
2 Reinforcement MT
1000 x 1 x 102.5% 1200 x 1 x 102.5% 1500 x 1 x 102.5%
Prepared by Project Monitoring Cell - Kolkata Example - 4 (Material Schedule) Slide No. - 10
Planning of Plant and Machineries
Efficiency of Equipment
Example : Calculate Batching Plant and Transit Mixer to be installed at site with following parameters
(Average concrete requirement / day, considering 26 working day = 5000 / 26 = 193 cum)
Batching Plant:
Assuming 10 working hrs per day for Batching Plant, required output = 300 / 10 = 30 cum / hour
Preferably, two no.s 30 cum Batching Plant should be installed at the project to avoid idling of resources during breakdown and to
pour higher volume of concrete if necessary.
Transit Mixer:
Considering distance between Batching Plant and most distant pour point, one cycle time (incl.loading, travelling and discharging) for
each transit mixer = 1 hr 30 mins
Considering 10 working hours / day, concrete carrying capacity of one TM / day = (10/1.5) X 5= 30 cum.
Hence, the requirement of TM for the project during peak = 300 / 30 = 9 no.s
However an additional TM may be required as a standby especially during breakdown / to pour of higher volume of concrete if
necessary.
Prepared by Project Monitoring Cell - Kolkata Slide No. - 12
Planning of Plant and Machineries
Example : Estimate Hourly Production of a backhoe with bucket capacity of 0.96 CuM, employed on excavation
of a foundation 4 meters deep in hard soil. The excavated earth is to be loaded in dump trucks, placed at a swing
angle of 75 degree. The expected performance efficiency is 80%
Ideal output of backhoe with bucket capacity of 0.96 CuM = 150 loose CuM (LCM) / hour
Backhoe output using equipment conversion factor of 0.8 operating at an optimum depth = 150 LCM X 80% =
120 LCM
Load factor for loading in dump trucks = 0.80 [Source : Basics of Construction Management]
Expected output / hr of backhoe = 120 X 0.67 X 0.80 X 1.05 X 80% = 54 LCM / hr.
Prepared by Project Monitoring Cell - Kolkata Example -5 (Plant & Machinery schedule) Slide No. - 13
Micro-level Planning and Reporting
Micro-level planning
Reporting
Worker’s Productivity
Example :
A task involving 160 SqM of fixing conventional formwork for the roof slab of a
single storey building completed in 4 days, by a workers’ team, consisting of 8
skilled and 16 unskilled workers, then calculate the workers’ productivity :
Equipment’s Productivity
Example :
If a front-end loader on a given job moves a load of 1.5 Cum of loose soil in one cycle,
consisting of loading – lifting – travelling – uploading – return trip – ready for loading,
and each cycle time is 1.2 minutes, then :
Actual output per working hour = Load per cycle X Cycles per hour
= 1.5 Cum X 60 minutes / 1.2 minutes
= 40 Sqm per day by 8 skilled labour + 16 unskilled labour
= 75 Cum per hour
[Source : Basics of Construction Management]
Slide No. - 19