Assembly Line Balancing
Assembly Line Balancing
Undesirable waiting
Overproduction!
Generates waste
Balanced Line
20 sec
11 sec D 18 sec
B
12 sec H
13 sec
E 15 sec 9 sec
A 13 sec J K
15 sec 17 sec
F
C I
13 sec
G
Example (cont.)
• Step 2: Determine Takt time or Workstation Cycle Time
C=Production time per day / Customer demand (or output per day)
C= 28800 sec (8 hours) / 1000 units = 28.8
To form Workstation 1:
11 sec
A Lot: 15>11!
15 sec
C Following tasks: 5
WS1: A+C=28 sec
Cycle Time
met!
Example (cont.)
• Forming Workstation 2:
20 sec
B+D>Cycle time!
D
11 sec
13 sec B 12 sec
E LOT:_F&G>E
A
15 sec 13 sec
13 sec
G Arbitrarily choose F
Example (cont.)
• Following the same criteria we achieve our balancing with
7 workstations
Remaining Feasible Task with
Task with
Workstation Task Task Time Unassigned Remaining most
LOT
Time Tasks followers
A 13 15.8 B, C B, C C
1
C 15 0.8 -
B 11 17.8 E, F, G E, F, G F, G
2
F 13 4.8 -
3 D 20 8.8 -
G 13 15.8 E
4
E 12 3.8 -
5 H 18 10.8 -
6 I 17 11.8 -
J 15 13.8 K
7
K 9 4.8 -
Example (cont.)
• Step 6: Calculate Efficiency
11 sec D 18 sec
B 12 sec H
13 sec
E 15 sec 9 sec
A 5 sec I* J*
15 sec F
C
8 sec
*Previously J & K respectively
G
Let’s practice (solution)
• Takt time
C = 28,800 sec / 1000 units = 28.8
• Theoretical number of workstations
N = 126/28.8 = 4.38 (~5 workstations)
• Primary rule: number of following tasks
• Secondary rule: longest operation time
Let’s practice (solution)
• Following the rules and observing cycle time and precedence
we obtain:
Remaining Feasible Task with
Task with
Workstation Task Task Time Unassigned Remaining most
LOT
Time Tasks followers
A 13 15.8 B, C B
1
B 11 4.8 -
C 15 13.8 E, F, G E
2
E 12 1.8 -
3 D 20 8.8 -
4 H 18 10.8
G 8 20.8 F
5 F 5 15.8 I
I 15 0.8 -
6 J 9 19.8 -
Let’s practice (solution)
• Efficiency = 126/(6*28.8) = 73%