Lecture 3& 4
Lecture 3& 4
Chapter: Two
Formation of Construction Contract
– Basics of Contract
– construction contract within the Ethiopian context
1
Introduction
The law is conventionally divided in to topics
according to their legal provenance.
The law of contract, the law of tort, the law of
property…
The law related to building and civil engineering
Sometimes called, “construction law” or “building law”
Under the Civil Code of Ethiopia construction
contracts are governed by
the law of contracts.
The Ethiopian law does not treat construction
contracts as a special case.
2
cont…
3
Major categories of construction law
Construction laws fall in to four major categories
Contract law:
those laws and regulation that affect the making
of contracts, both public and private
Laws governing the execution of work being performed
under the contract:
including the issuance and conformance to the
conditions of the various permits, regulations,
and other requirements
Laws that relate to settling of differences and disputes
Licensing laws
4
Basics of contract
• Contract law in construction works define the relationship of the parties involved
with regard to their obligations, responsibilities and privileges in the work and are
part of the existing law.
• The law is conventionally divided into topics according to their legal provenance,
the law of contract, the law of property and so forth.
• The Civil Code: Has five books
Book I : deals with “persons”
Book II: deals with “family succession” (replaced by a new version)
Book III: Deals with “goods”
Book IV: Deals with “obligations”
Book V: deals with “special contracts”
5
Cont…..
Generally, a contract is an agreement or willful promise enforceable
at law.
However, not all agreements or promises are contracts. Some may
lack enforceability at law.
A construction contract is a product of an agreement between the
employer & the contractor & it is enforceable at law.
Enforceable at law. means that if the agreement reached between the
employer & the contractor breached( deviations occur from the
promises) by one of the parties, the aggrieved party, either the
employer or the contractor, may bring a legal action against the other
to demand the enforcement of its rights with the support of law. 6
Cont…..
The general Law of Contract is governed under the Civil Code from
Article 1675-Article 2026.
Definition of Contract
According to Article 1675 of the Civil Code: A contract is an
agreement whereby two or more persons as between themselves
create, vary or extinguish obligations of a proprietary nature.
The construction contract clearly fulfils all the elements given to the
definition of contract.
The Form of Agreement, in the construction contract, clearly
presents the Agreement reached between the employer & the
contractor. 7
Cont…..
In principle, contracting with oneself is impossible
The construction contract, in principle, is only binding between the
employer & the contractor.This concept is related to the doctrine of
the privity of contract.
Privity of contract means that the contract is binding only the parties
who have made it.
8
The purposes of a contract
are to:
enforce law or bind conditions between or among the parties agree
to procure services or works or goods.
10
Formation of a contract
What should a contract satisfy to be enforceable in front of law?
According to Article 1678 ( Elements of Contract) of the Civil Code:
No valid contract shall exist unless
A. The parties are capable of contracting and give their consent
sustainable at law.
B. The object of the contract is sufficiently defined and is possible
and lawful.
C. The contract is made in the form prescribed by law.
The following are the fundamental elements of contract.
Capacity of the contracting parties;
Consent of the contracting parties;
Object of the contract; and
Form of contract, if any;
11
Capacity
Please, see Article 1678(a) of the Civil Code.
Capacity means competence to enter in to a legally binding
agreement.
Parties entering in to an agreement or contract shall,
therefore, be capable of contracting.
Legal capacity is of two types: Personal (Own)capacity;and
Representative(Agent) capacity;
Capacity of persons is legally presumed unless the contrary
is proved.
Persons could be:- natural (physical) persons; or legal
or juridical persons;
12
Cont…..
Natural Persons
Natural or physical persons are human beings.
Their legal capacity is determined by law.
The scope of capacity of physical persons is relatively unlimited
unless the contrary is proved.
Physical persons are the subject of rights & duties from birth
to death. See Article 1 of the Civil Code.
Legal Persons
Legal persons are of two types in terms of determining their
coming in to being & their legal capacity.These are:-
By legislation; (in case of public bodies/institutions); and
By registration; (in case of non-public bodies/corporate and/or
non-corporate private entities);
13
Cont…..
The following may not have (legal) capacity to enter in to contract &
bind themselves. These are:-
Minors (under the age of 18);
Companies adjudged or declared bankrupt;
Judicially interdicted persons;
Legally interdicted persons;
Persons, whose civil rights are suspended by the judgment of the
court;
Non-nationals, unless permitted by law or special prerogative;
Non-authorized Agents;
Agents, whose Power of Attorney has been revoked;
Agents , the Scope of their Power of Attorney does not cover the
intended transaction(ex. Tendering or Negotiation or Contract
14
Signing, .); and Others;
Cont…..
Natural persons or legal persons may enter in to contract:
Directly by themselves (in their own capacity): or
Through other persons called agents;
The power of agents (i.e. their representative capacity) should
always be checked, with respect to construction project, at:
The tendering stage;
The negotiation stage;
The contract signing stage; and
The Contract performance stage;
Sometimes also during dispute resolution process/phase;
15
Cont…..
The Power of Attorney creates a derivative legal capacity for
agents.
Agents, thus, acquire legal power, though not original, to
participate in construction tender, to negotiate, and/or to sign a
construction contract, in the name & on behalf of the named
principal and to bind the principal thereby.
A contract concluded by the person not capable under the law
may be invalidated at the request of such incapable person, who is
party to the contract. See Art. 1808(1).
16
Consent
Please, see Article 1678 (a) and Article 1679- Article 1710 of the Civil
Code)
Consent is a declared will of the individual to enter in to contract.
It is the willingness of the parties to enter in to a legally binding relation.
Declare that you have read all the incorporated documents and are willingly
bound by the terms!
Consent of the intended contracting parties decomposes in to :-
Offer; and Acceptance
17
Offer and Acceptance
Offer is defined as a proposal expressing the declared willingness
of the offeror to enter in to an agreement, if the offer is accepted.
Offer is a legal process which is a declaration of willingness or
intent to be bound by specific terms set out.
Offer may be made:- Orally; In writing; By sign; By conduct; By
specially stipulated manner for acceptance;
In case of (public) construction contract, offer shall be made in
writing.
A contract is complete when an offer by one party is accepted
without condition by the other party .
18
Cont…..
• Termination of offer:
• The following could be the way by which the offer could be
terminated. These are:-
By Death; -of either party before acceptance of the offer;
By Counter offer; -of the offeree;
Revocation; -by the offeror, within the time limit;
Withdrawal; -by the offeror; within the time limit;
By lapse of Time; -on part of the offeree, i.e. accepting the offer after the
prescribed time has elapsed;
20
Cont…..
Forms of Acceptance
The following could be forms of acceptance.
These are:- Orally; In writing; By sign; By conduct; As specially stipulated by
the offeror;
In the construction contract, especially for public works, acceptance in
writing is the most common & legally imperative practice.
The Letter of Acceptance is a clear example to this.
Offer and acceptance in construction:
Offer by contractor to do a job;
acceptance by client to the terms of the offer.
The issues in negotiation should be included as offer by contractor!
21
Consideration
• Consideration involves a benefit moving from the offeree/client to
the offeror /contractor in exchange for the promise .
• Consideration should be:
Of some value, but not necessarily adequate
Additional to the duty in the law
Additional to previous contract agreements ,For a future act
If one party makes a promise and the other party offers nothing in
return for that promise, the promise is unenforceable due to lack of
consideration.
22
Objects of the contract
Please, see Article 1678 (b) cum Article 1711 . Article 1718 of the
Civil Code);
The object of contract is the very obligations of the contracting
parties ex, in the construction contract, the obligations of the
employer and of the contractor to perform something.
The possible objects, i.e. the obligations of the contracting parties,
of contract are:- obligation to do (perform);obligation not to do; or
obligation to deliver;
The obligations of the contracting parties could be divided in to two
broad terms: Promises; and Considerations;
23
Cont…..
The object of a construction contract shall be sufficiently defined.
In the construction contract the whole purpose of all parts of the
contract documents (the BOQ, the Drawing, the Technical
Specification, notably, & including the Conditions of Contract (both
General and Special Conditions of Contract), and other documents like
filled forms) is to sufficiently define the object of the construction
contract, i.e. the very respective obligations of the contractor & the
employer.
The contractual obligation of the contractor (i.e. Promises) shall be
determined from the contract documents in terms of:
What to do: i.e. to construct:- water supply dam & systems; or
irrigation dam; or Hydropower dam; or other hydraulic
structures; or road; or building; or other type of structures;
In terms of its:- scope; quality; cost; time; safety; and other
aspects of its promises.
24
Cont…..
The Payment, obligation to do, or (Considerations) and other
contractual rewarding obligations of the employer shall also be
sufficiently defined in terms of:
Payment obligation: extent of contract price; types of payment;
timing for payment; conditions of payment; other related issues;
and other obligations in terms of other benefits, exchanges, &rewards;
These obligations are the very promises & considerations of the
contractor & the employer in the construction contract, respectively.
Unless the principle of implied terms or the rule of interpretation of
contract supports to resolve the issue of the object of contract, it is
difficult to define the object of contract by any body else except by the
contracting parties themselves.
The object of contract, even though sufficiently defined, it has to be
possible or capable of being performed.
25
Cont…..
The object of contract shall be lawful. Contract agreements can not
serve to achieve illegal objectives.
There shall not be any contract agreement on legally prohibited
matters.
Contracts shall not also go contrary to accepted moral values (as to
the principle of right or wrong) of the society.
If the contract found to be unlawful or immoral, the legal remedy
available is invalidation of the contract at the request of any
contracting party or interested third party. See Art. 1808(2) of the
Civil Code.
26
Form of contract:
Please, see Article 1678 (c) cum Article 1719 . Article 1730 of the
Civil Code.
Form may mean types of contract.
If no form is provided by law, contracts can be in any form the
parties agreed Otherwise, the contract agreement should be presented
in the form provided by law
For example,
A contract involving an immovable object should be in a written
form and needs to be registered by the authorities
Long term contracts, such as guarantees insurance etc, and
those entered with public organization should be in writing
In the absence of the law requiring the contract to be in writing, (see
Art.1719(1), the parties are free to make their contract as they wish.
They can make it orally or in writing. See Art. 1719(2).
27
Cont……
• Written contract:
According to the Civil Code of Ethiopia 1960, Art.1727
Any Contract required in writing shall be supported by a special
document signed by all the parties bound by the contract
It shall be of no effect unless it is attested by two witnesses
28
II. Terms of Contract
• The terms of contract are provisions or stipulations in a
valid contract describing some aspects of the
agreements between the parties to contract. The terms
define the rights and obligations of the parties in
accordance with their agreement. The terms can either
be express, implied or statutory
– Expressed terms are terms clearly stated in the
contract.
– Implied terms: are contract terms which are not
written down in a contract or openly expressed at
the time the contract is made, but which the law
implies
29
– Example Implied terms
– The materials and work will reasonably fit for the purpose.
31
III. Privitiy of Contract
Only parties who enter into a contractual agreement will
have the right to sue or a liability to be sued due to a
contract.
Assignment (Transfer from one person to another)
A debtor may with the consent of the creditor or
without such consent in cases provided by law or usage,
delegate to another the performance of his
obligation.(CC Ethiopia, Art 1976)
– Subcontracting(PPA Clause 7)
– The Contractor may subcontract with the approval of the
Engineer, but may not assign the Contract without the approval
of the Employer in writing. Subcontracting shall not alter the
Contractor’s obligations.
32
Discharge/set free of Contracts
• by Performance
– A construction contract will be discharged by
performance on the part of the contractor when
all the works has been completed including
maintenance during defects liability period,
the Engineer has issued all the required
certificates and
on the part of the employer when he has paid
all the payments due.
33
Discharge of Contracts
• By Agreement
• Mutual agreement (agree to cancel the
contract)
• By novation : According to Art. 1826, an
obligation may be extinguished by the principle
of novation when the parties agree to
substitute therefore a new obligation which
differs from the original one on account of its
subject or matter.
• Byaccord/agreementand
satisfaction/pleasure: The parties may accept
performance that is different from what was
agreed on in the original contract.
34
Discharge of Contracts
• By Frustration :
• Occurs when the contract was executable at
time of agreement but subsequent events, over
which the contracting parties have no control,
make it impossible to fulfill the contract
obligations. The Ethiopian civil code deals with
frustration under force majeure.[Art.1792]
–Force majeure (war, earth quake, natural
hazard)
35
Discharge of Contracts
• Breach
• failure to carry fundamental obligations under the
contract
• Leads to compensation and/or termination
• Famous in construction as liquidated damage
36
Invalidation of contracts
• Invalidated contract is a contract which is not
binding. The two main factors that can
invalidate a contract are mistake and
misrepresentation.
– Mistake: the term ‘mistake’ is used to
describe the situation in which an ‘offer’
made by one party and its ‘acceptance’ by
the other do not actually corresponds.
37
Invalidation of contracts
– the mistake must be fundamental to void the
contract ( it is usually be a mistake of fact which
will voids a contract);
• Identity of the subject matter
• Existence of the subject matter e.g. a contract
will be void where the subject matter of
contract has ceased, unknown to the parties
before the time of a contract.
• Mistake by one party to the promise of the
other party (the other party being aware of the
others mistake)
38
Invalidation of contracts
Misrepresentation (False statement):
Misrepresentation may be described as the
making of an untrue statement relating to fact
which includes another party to enter into
contract.
– When misrepresentation occurs, the injured party can
either state or reject the contract. He or she can also
bring as action for either recession/declie and
restitution or damages.
40
GCC
• General Condition of Contract is a document that states the
obligations and rights of the parties and details the
conditions under which the contract is to be carried out.
• These documents are published by different professional
associations, government bodies and also by financers.
• As the construction industry is dynamic those documents
shall be amended / improved through times, FIDIC could be
mentioned as an example it has published different
conditions of contract over the years (1957-1999).
41
• As the history of our national conditions of
contract indicates the first was published in 1959
by the Ministry of Housing, the second in 1987
by Building Transport Construction and Design
Authority, the third in 1994 by Ministry of Works
and Urban Development and the fourth and the
recent one in 2006 by the Public Procurement
Agency (amended in 2011) of the Ministry of
Finance and Development.
therefore, our discussion focus on the
provisions of the recent one!
42
• PPA conditions of contract divided the clauses
in five categories with 62 clauses,
– General
– Time control clauses
– Quality control clauses.
– Cost control clauses.
– Finishing of the contract,
43
General
45
Interpretation(Clause 2.3)
27. Program
28. Extension of the Intended Completion Date
29. Acceleration
30. Delays Ordered by the Engineer
31. Management Meetings
32. Early Warning
49
Time control clauses(PPA)
27.Program
27.1 Within the time stated in the Special Conditions of
Contract, the Contractor shall submit to the Engineer for
approval a Program showing the general methods,
arrangements, order, and timing for all the activities in
the Works.
27.3… If the Contractor does not submit an updated
Program within this period, the Engineer may withhold
the amount stated in the Special Conditions of Contract
from the next payment certificate and continue to
withhold this amount until the next payment after the
date on which the overdue Program has been submitted.50
Time control clauses(PPA)
27.Program
27.4. The Engineer’s approval of the Program shall not alter the
Contractor’s obligations. The Contractor may revise the
Program and submit it to the Engineer again at any time. A
revised Program shall show the effect of Variations and
Compensation Events.
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if
a Compensation Event occurs or a Variation is issued which
makes it impossible for Completion to be achieved by the
Intended Completion Date without the Contractor taking steps
to accelerate the remaining work, which would cause the
Contractor to incur additional cost. 51
Time control clauses(PPA)
29. Acceleration
29.1. When the Employer wants the Contractor to finish
before the Intended Completion Date, the Engineer will
obtain priced proposals for achieving the necessary
acceleration from the Contractor. If the Employer
accepts these proposals, the Intended Completion Date
will be adjusted accordingly and confirmed by both the
Employer and the Contractor.
29.2 If the Contractor’s priced proposals for an
acceleration are accepted by the Employer, they are
incorporated in the Contract Price and treated as a
Variation. 53
Time control clauses(PPA)
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to
delay the start or progress of any activity within the
Works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the
other to attend a management meeting. The business of a
management meeting shall be to review the plans for
remaining work and to deal with matters raised in
accordance with the early warning procedure.
.
54
31. Management Meetings
• 31.2 The Engineer shall record the business of
management meetings and provide copies of the
record to those attending the meeting and to the
Employer. The responsibility of the parties for actions
to be taken shall be decided by the Engineer either at
the management meeting or after the management
meeting and stated in writing to all who attended the
meeting.
55
Time control clauses(PPA)
32. Early Warning
32.1 The Contractor shall warn the Engineer at the earliest
opportunity of specific likely future events or circumstances that
may adversely affect the quality of the work increase the Contract
Price or delay the execution of the Works. The Engineer may
require the Contractor to provide an estimate of the expected effect
of the future event or circumstance on the Contract Price and
Completion Date. The estimate shall be provided by the Contractor
as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and
considering proposals for how the effect of such an event or
circumstance can be avoided or reduced by anyone involved in the
work and in carrying out any resulting instruction of the Engineer.
56
Quality Control (PPA)
33.1 The Engineer shall check the Contractor’s work and notify
the Contractor of any Defects that are found. Such checking
shall not affect the Contractor’s responsibilities. The Engineer
may instruct the Contractor to search for a Defect and to
uncover and test any work that the Engineer considers may
have a Defect.
34. Tests
34.1 If the Engineer instructs the Contractor to carry out a test
not specified in the Specification to check whether any work
has a Defect and the test shows that it does, the Contractor
shall pay for the test and any samples. If there is no Defect, the
test shall be a Compensation Event. 57
Quality Control (PPA)
If the final quantity of the work done: Differs from the quantity in
the BoQ,
The Engineer shall adjust the rate to allow for the change.
The Engineer shall not adjust rates if:
Advance Payments
&
Retention
The Employer does not give access to the Site by the Site Possession
Date stated in the Contractor’s approved work program.
The Engineer will assume that the Contractor will react competently &
promptly to the event.
Clause 44.4
or
Not having cooperated with the Engineer.
Clause 45 Taxes
Indices shall be appropriate for their purpose & shall relate to the
Contractor’s proposed source of supply of inputs.
The index value shall be deemed to take account of all changes in cost
due to fluctuations in costs.
48. Retention
All Defects notified by the Engineer to the Contractor before the end
of this period have been corrected.
The total amount of liquidated damages shall not exceed the amount
defined in the SCC
If applicable:
56 Taking over
The Employer shall take over the Site
&
The Works within 7 days of
The Engineer’s issuing a Certificate of Completion.
57. Final Account
The Contractor shall supply the Engineer with:
The Contractor shall supply them by the dates stated in the SCC.
The Engineer shall withhold the amount stated in the SCC from
payments due to the Contractor.
59.Termination
Offering,
Giving,
Receiving or
Soliciting,
The Engineer shall certify that: The Contract has been frustrated.
The Contractor shall:
Make the Site safe
&
Stop work as quickly as possible
After receiving this certificate
&
The following documents also form part of the Contract: [list any
other documents e.g. schedule of information provided by the
Contractor].
GCC 3.1
The language of the Contract is English and the law governing the
Contract is that of the Federal Democratic Republic of Ethiopia.
[Amend if an alternative language or law is to be used].
GCC 11.1
The Employer’s risks are as specified in the GCC. [Amend if the risks
in the GCC are to be modified].
GCC 25.3
Arbitration shall take place at: [state place e.g. Addis Ababa or any
other convenient location or delete if arbitration is not applicable]