EIA Process
EIA Process
Presentation on
Current Requirements in Environment
Impact Assessment (EIA) – Process &
Procedures as Per MoEF & CC
Guidelines
0
Introduction
1
Evolution & History of EIA
EIA process took off after mid 1980’s, after World Bank adopted EIA for major
development projects, in which borrower country had to undertake the EIA
under the Bank’s supervision.
2
Core values of EIA
3
Objectives of EIA
Predict incremental levels of pollutants in the study area due to the proposed project;
Validate the predicted pollution load with respect to the present pollution load due to airport
operations;
Evaluate the predicted impacts on the various environmental attributes by using scientifically
developed and widely accepted Environmental Impact Assessment modelling methodologies;
Prepare an EIA report, complying to all the TOR conditions issued by MoEF& CC;
To identify critical environmental attributes required to be monitored and suggest post project
monitoring plan; and
To carry out risk assessment and prepare the disaster management plan.
4
Methodology of the EIA Study
Existing topography, location of surface water bodies like ponds, canals and rivers;
5
Environmental Impact Assessment – Cycle & Procedure
Screening
Public hearing
6
NOTIFICATION OF
ENVIRONMENTAL IMPACT
ASSESSMENT-2006
7
UNDERLYING BASIS, SPIRIT AND PREAMBLE
EIA 1994
Environment Protection Act 1986
8
Categorization of projects and activities
9
Requirements of prior Environmental Clearance (EC)
10
Requirements of prior Environmental Clearance (EC)
11
STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY (SEIAA)
12
Expert Committees for Screening, Scoping
and Appraisal (EAC and SEAC)
Expert Committees
13
Application for Prior Environmental Clearance
Submit pre-feasibility report for all and conceptual plan for construction
activities
14
STAGES IN EC PROCESS
Stage 2: Scoping
Stage 4: Appraisal
Sequential order
All of which may not apply to particular cases as set forth in this
notification
15
STAGE 1: SCREENING
Only for Category-B projects and activities to determine if they need EIA
16
STAGES IN EC PROCESS
Stage 2: Scoping
Stage 4: Appraisal
Sequential order
All of which may not apply to particular cases as set forth in this notification
17
Stage 2: SCOPING
Expert Appraisal Committee (EAC) in the case of Category ‘A’ projects or activities
State level Expert Appraisal Committee (SEAC) in the case of Category ‘B1’
projects
A site visit by a sub- group of EAC or SEAC will be conducted only if considered
necessary
18
STAGE 2: SCOPING
In the case of Category A Hydroelectric projects TOR shall be conveyed along with
the clearance for pre-construction activities
If TOR not finalized and conveyed to the applicant within sixty days of the receipt of
Form-1, TOR suggested by the applicant shall be deemed as the final TOR
approved for the EIA studies
Approved TOR shall be displayed on the website of the MoEF&CC or the concerned
SEIAA
The decision together with reasons for the same shall be communicated to
the applicant
Prepare EIA draft report as per the approved ToR and Guidelines of MoEF&CC.
19
Stages in EC process
Stage 2: Scoping
Stage 4: Appraisal
Sequential order
All of which may not apply to particular cases as set forth in this notification
20
Stage 3: Public consultation
All Category ‘A’ and Category B1 projects or activities shall undertake Public
Consultation
Public hearing at the site or in its close proximity- district wise, to be carried out
in the manner prescribed in Appendix IV, for ascertaining concerns of local
affected persons
21
Component 1: Public hearing
Public hearing shall be conducted by the State Pollution Control Board (SPCB)
If the public agency nominated reports that it is not possible to conduct the public
hearing in a manner which will enable the views of the concerned local persons to
be freely expressed
After due consideration of the report shall rule that the public consultation in
the case need not include the public hearing
22
Component 2: Responses from other concerned persons
Invite responses from such concerned persons by placing the Summary EIA
report.
Make available on written request from any concerned person the Draft EIA
report for reference at a notified place during normal office hours till the date of
the public hearing
All the responses received as part of this public consultation process shall be
forwarded to the applicant through the quickest available means
23
After public consultation…
24
2
5
Stages in EC process
Stage 2: Scoping
Stage 4: Appraisal
Sequential order
All of which may not apply to particular cases as set forth in this
notification
25
Stage 4: Appraisal
Appraisal of all projects or activities which are not required to undergo public consultation, or
submit an Environment Impact Assessment report (Category B2) shall be carried out on the
basis
Form -1A
26
2
7
Stage 4: Appraisal Contd…
27
Grant or Rejection of EC
28
Grant or Rejection of EC Contd…
If decision not granted within stipulated time, the applicant may proceed as
if the environment clearance sought for has been granted or denied by the
regulatory authority in terms of the final recommendations of the Expert
Committee concerned
Area Development projects and Townships, the validity period shall be limited
only to such activities as may be the responsibility of the applicant as a
developer
Seven years for all others projects (Airports) and can be extended to five
years.
30
Post Environmental Clearance Monitoring
31
Environmental Clearance Process
32
Summary of EIA process and Timelines
Who does it?
Submission of application (Form 1, prelim reports)
Investor
Investor
Prepare preliminary EIA report
State Pollution
45 days Stage 3: Public consultation (2 components) Control Board
Update EIA report (Investor)
Expert
60 days Stage 4: Appraisal
Committee
15 days
Regulatory
30 days Final Decision
Authority
33
Legal & Institutional Frame Work - Environment
34
Legal & Institutional Frame Work
Workmen's Compensation Act, 1923
The Trade Unions Act, 1926
The Petroleum Act, 1934 and the Petroleum Rules
The Industrial Disputes Act, 1947
Factories Act, 1948
Minimum Wages Act, 1948
Employees State Insurance Act, 1948
Employees Provident Fund and Miscellaneous Provisions Act, 1952
The Maternity Benefits Act, 1961
Personal Injuries (Emergency Provisions) Act, 1962
Contract Labour (Regulation and Abolition) Act, 1970
The Payment of Gratuity Act, 1972
The Child Labour (Prohibition and Regulation) Act, 1986
The Building & Other Construction Workers (Regulation of Employment and Conditions of Service)
Act,1996
Electricity Act, 2003
Right to Information Act, 2005
35
Thank you
List of Projects or Activities Requiring Prior Environmental Clearance
38
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
1 (d) Thermal Power Plants < 500 MW (coal / lignite / naptha & gas based); General Condition shall apply
< 50 MW
5MW (Pet coke ,diesel and all other fuels )
Including refinery residual oil waste except biomass
2 Primary Processing
2 (a) Coal Washeries 1 million ton/annum <1million ton / General Condition shall apply
throughput of coal annum (If located within mining area the proposal
throughput of shall be appraised together with the mining
coal proposal)
2 (b) Mineral beneficiation 0.1 million ton/annum < 0.1 million ton General Condition shall apply (Mining
mineral throughput / annum proposal with Mineral beneficiation shall be
mineral appraised together for grant of clearance)
throughput
39
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
40
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
41
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
42
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
5 (e) Petrochemical based Located out side Located in aSpecific Condition shall
processing (processes other the notifiednotified industrial apply
than cracking & reformation industrial area/area/ estate
and not covered under the estate
complexes) -
5 (f) Synthetic organic chemicals Located out side Located in a Specific Condition shall
industry (dyes & dye the notified notified industrial apply
intermediates; bulk drugs and industrial area/ area/ estate
intermediates excluding drug estate
formulations; synthetic rubbers;
basic organic chemicals, other
synthetic organic chemicals
and chemical intermediates)
43
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
45
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
7 (e) Ports, Harbours 5 million TPA of < 5 million TPA of General Condition shall
cargo handlingcargo handling apply
capacity (excluding capacity and/or
fishing harbours) ports/ harbours
10,000 TPA of
fish handling
46
capacity
List of Projects or Activities Requiring Prior Environmental Clearance Contd…
48