Module 3 Project Initiation
Module 3 Project Initiation
Module 3
Project Initiation
During project initiation, the Agency plans how the authorized project
is to be implemented. Planning begins by fleshing out what the project is
to deliver and documenting the result in the PRD. The Agency then
considers what approach to take to manage and carry out the work to
implement the project , selects the project delivery method, assesses the
type and size of resources needed for the project , and documents these
in the PMP. Planning concludes with establishing the selected project
management organization through the assignment of Agency staff to the
project and retaining of a Program Management Consultant (PMC) for the
project management work where the Agency does not have staff
resources with the necessary skill and experience.
Role of the Agency in Project Initiation
Topic Description
Authorization Reference to project authorization that selected and authorized the project
Stakeholders Corporate sponsors, customers, third parties impacted, project team
Deliverables Products/services the project will deliver
Scope of Work Work to be done to deliver the products/services (high-level summary)
Cost Estimate Initial order of magnitude estimate of the project budget
Schedule Milestone Initial project schedule in terms of key project milestones
Finance Project financial requirements and sources of funding
Risks Threats to the project (e.g., adverse environmental factors)
Resources Resources needed to accomplish the project
Constraints Constraints such as limited resources/funding, sites available, etc.
Acceptance Criteria What determines acceptable products/services and their approval
Table 3.2 The project manager for our example bus maintenance facility project scenario approached the PRD as
follows:
Authorization Incorporated references to the project authorizations: Capital Improvement Program recommending example project,
Agency Board action approving the project, and Department agreement for funding a share of the project.
Stakeholders Identified parties with an interest in or impacted by the project, including: Agency Board, Department, Agency operations, elected
officials in whose area the project is located, and the community and businesses adjacent to project.
Deliverables Prepared a high-level description of the example project: facilities, equipment , and systems.
Scope of Work Developed a high-level work breakdown structure (WBS) of the project work phases: acquire land for garage facility, obtain
environmental clearance, design facility and equipment , construct facility and supply/ install equipment, test and start-up, and
accept completed facility.
Cost Estimate Allocated the P1.5B budget across the high-level WBS.
Schedule Milestone Estimated the initial project schedule milestones for accomplishing the high-level WBS phases.
Finance Costed out project requirements for funds from Agency, state and Department grant sources, and debt financing.
Risks Identified potential threats to project success, such as unknown ground conditions at the proposed facility site.
Resources Listed the types of staff and other resources needed for the project, e.g., environmental specialists, architects and engineers,
construction contractors, and equipment suppliers.
Constraints Identified project constraints: limited cash flow from debt financing, shortage of experienced contractors.
Acceptance Criteria Specified requirements to take occupancy of the building and approve the performance of the equipment .
PLANNING THE PROJECT
Management Project Management Manage the overall project and its phases – Planning, Engineering, and Technical
and Control initiation, planning, design, construction, and closeout
Project Management Oversight Oversee project performance by a party independent of the project team and report to project sponsor(s)
• Work done by the Agency and the work that is contracted out to
consultant and/or construction contractors.
• Degree of control the Agency maintains over how the work is done
and the control transferred to contractors through contracting out.
• Assignment of risks associated with the project work undertaken
by the Agency and contractors.
For the example bus maintenance facility project , the project manager
plans a design/bid/build (D/B/B) delivery strategy where: the project
manager and other Agency staff will manage the project; design and
design management will be contracted out to a General Engineering
Consultant (GEC); and a Construction Manager (CM) will be retained to
manage construction carried out by various construction contractors and
suppliers.
What alternative delivery strategies are available to a project manager? A
project manager may contract out any one or all of the project management,
design, and construction functions to acquire the capability and capacity
needed for the project. Contracting out a function also results in transferring,
from the Agency to the contractor, responsibility for and control of the means
and methods of how the work is executed, as well as the risks associated with
the performance of the work. Table 3.4 describes alternative project delivery
strategies along with the corresponding transfers of control and risk from the
owner organization to the contractor. Figure 1 illustrates the sharing of control
and risk between the Agency and the contractor for different delivery strategies.
For smaller Agencies it is of ten expedient for the project manager to
choose delivery strategies similar to the example above, that contract out
the project work rather than hire an entire project staff. It is difficult to
recruit qualified project staff for a single project. Using contracted services
allows the project manager to better match resources to project needs. A
contractor can be retained when the need arises and the project manager
can immediately terminate their involvement and expense when the project
need is over. Whatever delivery strategy the project manager selects, it is
important that the Agency, through the project manager, retains the
ultimate authority and accountability for the effective management of the
project. This is the case even where the Agency’s project manager
chooses to retain a Program Management Consultant (PMC) to manage
the project on behalf of the Agency.
Table 3.4 Project Delivery System
Strategy Sub-strategy Description Owner Control/Risk
Own Forces Total Project Owner manages, designs, Owner has total control
and constructs project with and accepts all risks
own forces
Construction Owner manages and
constructs project with own
forces, and retains
construction
Design/Bid/Build Owner Managed D/B/B Owner manages project, Maintains overall project
contracts out design to control and transfers
engineering consultants detailed engineering
and construction to design/construction tasks
contractors and risks to contractors
Strategy Sub-strategy Description Owner Control/Risk
GEC Owner retains a GEC to manage the Owner transfers control of design
design and design consultants and design management tasks
and risks to GEC
CM Owner retains CM to manage Owner transfers control of
construction contractors Construction and construction
management tasks and risks to
CM
PMC Owner retains a PMC to manage the Owner maintains control of
project including consultants and project scope and transfers
contractors project management tasks and
risks to PMC
CMAR
Construction Owner may also retain a Owner retains a CMAR contractor in Owner transfers a share of
Manager at Risk GEC and PMC final design, who participates in control of scope through design to
design review, estimating, and value the CMAR contractor and all of
engineering and at some agreed the control and risk of the
point guarantees a fee to manage management and execution of
and carry out construction construction
Strategy Sub-strategy Description Owner Control/Risk
D/B
Design/Build Owner may also GEC completes design through Owner maintains control of scope through
retain a GEC and preliminary concept design (30 percent) after which
PMC engineering(approximately 30 control and risk of design and construction
percent). Owner retains a D/B is transferred to D/B contractor
contractor to complete design
and construct the project
D/B/O/M
Design/Build/ Design/Build/Operat As for D/B plus contractor is Owner transfers control and risk of
Operate/ e responsible for the operations operations and maintenance to the
Maintain or Design/Build/ and maintenance of the facility contractor
Operate & Maintain for a specified period
Tu r n k e y Could be used for Could be used for D/B or Owner controls scope of performance
D/B or D/B/O/M D/B/O/M specification after which control and risk
of conceptual/detail design and
construction transfers to turnkey contractor,
including operations and maintenance if
D/B/O/M
PROJECT ORGANIZATION AND MANAGEMENT STRUCTURE
The project manager has to provide the project team with a road map
on how to get the project done. The PMP sets out how the project is to
be managed, executed, monitored, controlled, and closed through the
phases of its life cycle. Table 3.5 sets out a typical PMP outline that would
apply to a construction project such as the example bus maintenance
facility project.
In the PMP, the project manager sets out the management approach
for the project based on the decisions made with respect to the project
delivery strategy, organization and management structure, assignment of
responsibilities between the Agency and contractors, and delegation of
management and financial authority through the project team.
The project’s scope, budget , and schedule are refined to establish
baselines for the project’s scope of work, costs, and schedule that are
documented in the PMP (Module 9 is about about project control
techniques used for establishing baselines). Scope, budget , and
schedule baselines are yardsticks against which future project
performance can be measured and assessed, and changes
controlled. Depending on the project phase baselines are established
for a project phase or the entire project baseline is established after
completion of preliminary engineering. A baseline remains unchanged
through the project or project phase unless a revision to the project’s
goals and objectives is authorized by the Agency’s executive
management responsible for the project authorization.
The PMP is a “living” document and is updated as the
project progresses, usually as the project enters a new phase,
such as moving from design into construction. Updating and
revising the PMP requires the project manager to: add
management detail on how a new phase is to be managed,
note any changes to the project scope, and forecast project
costs and schedule against the baselines.
Traditionally the project is managed by personnel in the planning
organization through completion of the environmental phase. As
the project moves into the design and construction phase where
engineering and construction management skills are required, it is
critical that the top management recognize and plan for the
changes in project management leadership necessary to
successfully make the transition from the planning/environmental
phase to the design and construction phase. In Section 9 we
explain some useful tools and techniques that support the project
manager in the control of scope, cost , and schedule.
Table 3.5 Project Management Plan Outline
A project’s authorization may be limited to proceeding up to a
certain milestone at which certain criteria must be met for the project
to receive further authorization to continue. This staged authorization
is known as staged-gate decision-making. In our example project
scenario the agreement with the FTA authorized funding up to the
conclusion of preliminary engineering. At this point, continued FTA
funding was conditional on the Agency preparing an acceptable PMP,
demonstrating the capability and capacity to put in place the
resources to manage and undertake design and construction, and
securing financing for the Agency’s share of the project costs.
Supporting Management Plans