0% found this document useful (0 votes)
62 views

Implementation Schedule

implementation / actual schedule

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views

Implementation Schedule

implementation / actual schedule

Uploaded by

edla3710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 1

IMPLEMENTATION SCHEDULE

CONTRACT DURATION = 52 MONTHS

2016 2017- 2020

31 MAY JUN 25 NOV 14 DEC 11 JUL 19 JAN 30 MAR 07 SEP


2016 2016 2016 2017 2019 2020 2020 2020

01 JUL 13 DEC
NOTICE TO PROCEED 2016 2017
98.85% Physical Accomplishment
as of 19 January 2020
DESIGN WORKS 6 months

SITE ESTABLISHMENT 17½ months


3 yrs & 2 months
INLET CONSTRUCTION
3 yrs & 3 months
OUTLET CONSTRUCTION

TUNNEL BORING MACHINE (TBM)


(Ordering, Manufacture, Delivery to Philippines, 23½ months
and Assembly to site)

TUNNEL CONSTRUCTION 18 months


(TBM excavation, Tunnel lining construction,
and TBM disassembling)
4 months
OTHER WORKS, TESTING,
COMMISSIONING, AND ACCEPTANCE