Progress Report
Progress Report
An
OVERVIEW
30.04.2019
BIHAR STATE HIGHWAYS PROJECT : PHASE-I
Status as on 31.03.2019
EA SH Name of the Length Name of Amount Original Revised Date of Original Extended Financial Physical Remarks
Pkg No. Road (Km) Contractor A/A Contract Contract Award Time of Time of achieve- achieve-
. (Rs. Cr.) Amount Amount Completion Completion ment ment (in
No. (Rs. Cr.) (Rs. Cr.) (In %) %)
1 68 Shivgunj- 83.051 MBL, 252.37 168.53 194.64 15.07. 09 16.04.12 31.03.19 78.05 99.94 Completed &
Baidrabad Kolkata inaugurated
on 27.03.16
2 69 Dumaria - 152.80 GIL, 442.27 313.50 318.75 30.12. 08 25.01.12 31.12. 15 89.29 99.58 Completed &
Rani Talab Mumbai inaugurated
on 27.03.16
3 70 Gaya – 58.23 GIL, 144.19 105.51 - 19.12. 08 - 10.12. 11 100 100 Completed
Rajauli Mumbai
4 71 Jehanabad - 85.20 C&C, 234.80 159.57 - 24.11. 08 - 24.06. 11 100 100 Completed
Shahpur Gurgaon
5 73 Siwan- 88.00 GR-JKM 290.33 229.41 - 03.07. 09 - 31.03. 12 100 100 Completed
Shitalpur (JV), New
Delhi
6 74 Hajipur - 87.06 C&C, 269.28 225.42 - 22.11. 08 - 19.06. 11 100 100 Completed
Areraj Gurgaon
7 75 Darbhanga– 46.75 IVRCL, 211.57 156.64 - 09.07. 09 - 18.06. 12 100 100 Completed
Madhwapur Hyderabad
8 76 Araria – 121.00 BSC - C&C 436.35 299.76 - 25.11. 08 - 18.12. 11 100 100 Completed
Bhaptiyahi (JV),
Gurgaon
9 77 Kursela - 102.93 BSC - C&C 348.67 277.93 - 25.11. 08 - 18.12. 11 100 100 Completed
Forbesganj (JV),
Gurgaon
TOTAL 824.22 2629.86 1936.26
C&G 79.70 79.70 79.70 100% Hume Pipe culvert 179 179/0 100 %
Achievement (in Cr.) 252.02 276.69 282.45 0.2 0.07 0.09 0.02 0.07 0.13 0.4 0.35 284.98 89.41
Gammon
Birpur-
5 91 100.84 592.27 India Ltd, 328.89 348.40 28.09.11 30.06.19 86.68 96.76 Ongoing
Udaikishangunj
Mumbai
TOTAL 374.255 2547.02/ 1823.61
3751.88