Building Construction Methods-2
Building Construction Methods-2
PRE COMPLETION/
CONSTRUCTION POST
CONSTRUCTION COMPLETION
STAGE I
PRE CONSTRUCTION
NATIONAL BUILDING CODE
( P.D. 1096 )
5 MAJOR DIVISIONS IN BUILDING PLANS
ARCHITECTURAL PLAN
1 2 3 3 2 1 A B C
GA 26 CORR. G I. GA 26 CORR. G I.
ROOFING ROOFING
1 2 3 2 1 2 3
1 3
SCH. OF DOORS & WINDOWS
C C C
W-2 W-2
EXPOSED SLOPE
B STEEL ‘C’ B
CLASSROOM B PURLINS AND
SLOPE
RAFTERS D-1 W-1 & W-2
FLUSH TYPE GLASS JALOUSIE
D-1 W-1 W-1 D-1 HOLLOW CORE WINDOWS ON
A A A DOOR W MARINE ALUMINUM HOUSIG
CORRIDOR PLYWOOD FACING
ON WOOD FRAME
FLOOR PLAN REFLECTED CEILING ROOF PLAN
*PLANS BY BOD
STRUCTURAL PLAN
C-PURLINS
RAFTER C
A B
ANGULAR
BRACE
CORR. GI
SHEETS
WF-1 WF-1
WF-1
WF-1
LB LB
BASE PLATE W LONG
ANCHOR BOLTS
C1-F1
C1-F1
ROOF INSULATION CEILING
FIN. COMPRESSED BETWEEN SLAB ON FILL
PURLINS AND RAFTER
D-1 W-2
WF-1
WF-1
CORRIDOR
DOWEL
CLASSROOM FFL WF-1 WF-1
FGL
WELL COMPACTED NGL
COL. FTG. C1-F1 C1-F1 C1-F1
GRAVEL FILL
WALL FTG
DETAIL CROSS SECTION
FOUNDATION PLAN
*PLANS BY BOD
STRUCTURAL PLAN
A A1
L
4-12mmØ
9mmØ STIRRUPS
350mm THK. CONCRETE
FOOTING
N.G.L.
SECTION
WF (4" CHB) PLAN
PLUMBING SYSTEM
WATER LINE INCLUDING DRAINAGE, WASTE AND VENTILATION SYSTEM OF BUILDING
DRY VENT
WATER CLOSET
HOT WATER RETURN
FLOOR DRAIN
KITCHEN SINK
FIXTURES
SMALL DRILLING EQPT. DROP HAMMER DRIVING HEAVY BORING RIG W/ VIBRO HEAVY CABLE GRAB
USE FOR MICRO PILES RIG FOR PRE CAST PILES HAMMER FOR BORED PILES FOR BARRETTE PILES
PURPOSE
THIS DEPARTMENT ORDER SETS THE GUIDELINES, RULES AND PROCEDURES, TO BE FOLLOWED
BY ALL CONCERNED IN THE IMPLEMENTATION OF DEPARTMENT OF LABOR AND EMPLOYMENT D.O.
No. 13(DOLE D.O. No.13), SERIES OF 1998 OTHERWISE KNOWN AS THE “GUIDELINES GOVERNING
OCCUPATIONAL SAFETY AND HEALTH IN THE CONSTRUCTION INDUSTRY”, WITH EMPHASIS GIVEN
ON THE METHODOLOGY TO BE USED IN ESTIMATING THE COST OF CONSTRUCTION SAFETY AND
HEALTH PROGRAM AS REQUIRED IN SECTION 17.
GENERAL GUIDELINES
IN COMPLIANCE WITH SECTION 17 OF DOLE D.O. No. 13, THE IMPLENTATION OF CONSTRUCTION
SAFETY SHALL BE CONSIDERED IN ALL STAGES OF PROJECT PROCUREMENT ( DESIGN,
ESTIMATE, AND CONSTRUCTION ) AND ITS COST SHALL BE INTEGRATED TO THE OVERALL
PROJECT COST UNDER PAY ITEM “SPL- CONSTRUCTION SAFETY AND HEALTH” AS A LUMPSUM
AMOUNT, TO BE QUANTIFIED IN THE DETAILED ESTIMATE. LIKEWISE, ALL REQUIREMENTS,
PROVISIONS, AND INSTRUCTIONS PERTAINING TO THE IMPLEMENTATION OF CONSTRUCTION
SAFETY AND HEALTH IN EVERY PROJECT SHALL BE INCLUDED IN THE PROJECT BIDDING
DOCUMENTS SPECIFICALLY UNDER THE INSTRUCTION TO BIDDERS.
CONCTRUCTION PROJECT
(D.O. No. 56 S. 2005)
MANPOWER EQUIPMENT/FACILITIES
COSTING
PAY ITEM “SPL – CONSTRUCTION SAFETY AND HEALTH” AS
A LUMP SUM AMOUNT, TO BE QUANTIFIED IN THE DETAILED
ESTIMATE.
NOTE : DERIVED FROM CPES MANUAL
BUILDING CONSTRUCTION METHODOLOGY
( BY PERT/CPM DIAGRAM)
PROJECT: ONE(1) STOREY TWO(2) BEDROOM LOW COST HOUSING
ELECTRICAL/SANITARY ROUGH-IN
J
16
14 INST. ELECT/
12 MECH/SANITARY
CARPENTRY WORKS FIXTURES
P S
2 1
1 2 6
MOVE- 4 13 17
IN
EARTH CONCRETE MASONRY 8 1O 15 MOVE
WORKS WORKS WORKS ROOF FRAMING ROOFING FINISHES PAINTING OUT
A B C F H M N Q T V
2 2 5 3 5 4 4 3 2
WAIT WAIT
WAIT WAIT WAIT
2 4
E G K O R U
1 2 2
SOIL BACKFILL INST. OF PURLINS INST. GUTTER & INST. FAB. MATLS &
HARDWARE
POISONING 5 WAIT 9 FLUSHING
3 11 14
I W
3
DAMPROOFING/SLAB ON FILL
7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CALENDAR DAYS
LEGEND:
NETWORK - A B
ES LS EF LF
ACTIVITY -
EVENT - A
ES LS
DUMMY -
CRITICAL PATH -
STAGE II
CONSTRUCTION
NVPILAR 2008
NVPILAR 2008
CONSTRUCTION METHODOLOGY FOR BUILDINGS
STAGE I – WORK ACTIVITIES BELOW / ON GROUND
PART A – MOBILIZATION
-MOVING IN OF MANPOWER,
EQUIPMENT & MATERIALS AT
THE PROJECT SITE.
PART A-FACILITIES FOR THE ENGR
A.1.1- OFFICES & LABORATORIES
A.1.2- VEHICLES FOR THE ENGR
A.1.3- ASSISTANCE TO THE ENGR
A.1.4- PHOTOGRAPH
PART E – DAMPROOFING/
MOISTURE CONTROL
ABOVE/ON GROUND
PART C – TERMITE CONTROL -POLYETHELENE SHEETS
& WOOD PRESERVATION BELOW GROUND
DPWH SPECS VOL III- ITEM 1000 DPWH SPECS VOL III ’95 ED.
UPPER- WOOD PRESERVATION ITEM 1016-WATERPROOFING
LOWER- SOIL POISONING -HYDROLITHIC WATERPROOFNG
NVPILAR 2008
CONSTRUCTION METHODOLOGY FOR BUILDINGS
STAGE III – FINISHING WORKS / COMPLETION OF THE STRUCTURE
NVPILAR 2008
1. WORKMANSHIP
2. MATERIALS
3. TIME
4. FACILITIES
5. ENVIRONMENTAL, SAFETY & HEALTH
6. RESOURCE DEPLOYMENT
COMPLETION/POST COMPLETION
PREPARATION OF AS – BUILT PLANS & SPECS.
( RULE II OF THE I.R.R. OF PD. 1096 )
SECTION 62.2
For the procurement of infrastructure projects, the contractor shall assume full responsibility for
the contract work from the time project construction commenced up to final acceptance by the
government and shall be held responsible for any damage or destruction of the works except
those occasioned by force majeure. The contractor shall be fully responsible for the safety,
protection, security and convenience of his personnel, third parties, and the public at large, as
well as the works, equipment, installation and the like to be affected by his construction work
and shall be required to put up a warranty security in the form of cash, bank guarantee, letter of
credit, GSIS or surety bond callable on demand, in accordance with the following schedule:
The warranty security shall be stated in Philippine pesos, shall remain effective during the
applicable warranty period provided in section 62.2.2 hereof, and shall be returned only after the
lapse of the said warranty period.
WARRANTY
( R.A. 9184, RULE XIX, SECTION 62 )
62.2.2.
After final acceptance of the project by the Government, the contractor shall be held
responsible for structural defects and/or failure of the completed project within the
following warranty periods from final acceptance, except those occasioned by force
majeure and those cause by other parties:
A) Permanent Structures: Fifteen (15) years
Buildings of types 4 (steel, iron, concrete, or masonry construction with walls,
ceilings, and permanent partitions of incumbustible fire resistance) and 5 (steel,
iron, concrete, or masonry construction), steel and concrete bridges, flyovers,
concrete aircraft movement areas, ports, dams, diversion tunnels, causeways,
wharves, piers, dikes, filtration and treatment plants, sewerage systems, power
plants, transmission and communication towers, railway system, and other
similar structures;
• EDGARDO C. GARCES • DANIEL A. PABLICO • ROSELYN C. NIEBRES • LEONARDO E. JARAPLASAN DPWH | Bureau of Construction
Scope of Works in Building Construction
A – MOBILIZATION,
B – EARTHWORKS
D – FOUNDATION WORKS
F – CONCRETE WORKS
G – MASONRY WORKS
H – CARPENTRY WORKS
K – ROOFING WORKS
L – FINISHES
M – PAINTING / VARNISHING
N – WATER PROOFING
O – SANITARY WORKS
P – ELECTRICAL WORKS
Q – MECHANICAL WORKS
4. Inadequate/lack of testing equipment on the project - Require the contractor to strictly follow the requirement
site. of the contract.
5. Inadequate/lack of safety measures and signboards -Conduct briefing and trained contractors personnel on
including Personal Protective the necessity of these requirement as part of the
Equipment of workers on the project site. contract.
6. Improper disposal of waste materials and debris within -Provide/set-up guidelines and procedures for immediate
the project site. implementation of the contractor.
7. Lack of the necessary permit and clearances from -Imposed sanctions if necessary.
local officials.
2. No-graduation marks -Do not allow driving of piles unless otherwise graduation is clearly
marks on the piles for accuracy of pile driving records and data.
3. Non-conformance to -Call the attention of the Project Engineer, direct rigger to have the
specified splicing splicing on a staggered basis for cluster piles.
requirements.
4. Presence of cracks -Removed and replaced.
B. CAST-IN-PLACE BORED PILES
1. Non-conformance to the required level of excavation. -Monitor and check elevation through actual measurement.
2. Improper disposal of spoils and debris. -Require the Project Engineer to immediately disposed/spread spoils
before it becomes an obstructions and delay the project.
3. Non-conformance to the required spacing of tie, stiffener bar and -Call the attention of the Project Engineer and properly adjust spacing
spacer. to meet requirements.
4. Improper curing of concrete samples. -Require the Materials Engineer to thoroughly check and supervise
the curing and handling of samples as this was critical in the
determination of the actual strength of concrete.
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
C.CONCRETE
1. Concrete structure failed to meet the strength requirements as per - Conduct investigation and in-place testing to determine actual
concrete sample specimens. strength.
- If structure failed to meet strength requirement through in-place
testing, refer to Structural Engineer/ Designer to assess extent of
remedial and corrective works.
2. Appearance of hairline cracks - Chipped off concrete to determine extent of cracks.
- Apply concrete epoxy.
3. Appearance of honeycomb or spalling - Chipped off concrete to removed honeycomb portion.
- Apply concrete epoxy prior to re-concreting.
4. Sagging or bulging of concrete. - Provide additional shoring and bracing if concreting is still on
going.
- For minor sagging or bulging removed affected portion and plaster.
- For major bulging, removed and replaced if necessary.
5. Non-conformance to finishing/ plastering requirement. - Require the Project Engineer to make the necessary
adjustments.
- Removed and replaced plastering works if necessary.
6. Improper curing -Call the attention of the Materials Engineer to make the
necessary adjustment to conform to standard requirements.
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
VII. MASONRY WORKS
1. Non-conformance to the required strength for both non-load - Non-load bearing, 500 psi and load bearing at 800 psi.
bearing and load bearing CHB. - Removed and replaced all CHB that does not conform to the
strength requirements.
- Conduct visual inspection and field testing.
2. Non-provision of lintel beam and stiffener column. - Chipped off laid CHB and install stiffener columns.
- Require the Project Engineer to make the necessary
adjustment.
- Reject/removed and replaced if necessary.
3. Non-conformance to the vertical and horizontal dowel. - Require the Project Engineer to make the necessary
adjustments.
- Reject/removed and replaced if necessary.
VIII. CARPENTRY AND JOINERY WORKS
1. Undersize lumber and plywood. - Require the Project Engineer to removed and replaced all
undersize materials.
2. Non-conformance with the required spacing for ceiling joist, - Require the Project Engineer to make the necessary
nailers, vertical studs and horizontal studs. adjustments.
3. Non-conformance to the required species of lumber. - Require the Project Engineer to make the necessary
adjustments.
- Reject/removed and replaced if necessary.
IX. FABRICATED MATERIALS AND HARDWARE
A. DOORS
1. Doors are not well fitted to the door frames. - Require the Project Engineer to make the necessary
2. Door accessories and other hardwares items were installed adjustment.
not according to schedule. - Conduct frequent inspection and verification to monitor
B. WINDOWS fabrication prior to installation.
1. Windows are not well fitted to the window frames. - Reject/removed and replaced if necessary.
2. Window accessories and other hardwares item were
installed not according to schedule.
3. Installed doors and windows were not in accordance with
specifications. DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/REMEDIAL MEASURES
X. ROOF FRAMING WORKS
A. STEEL FRAMING
1. Use of corroded structural elements. - Conduct visual inspection, verification and monitoring of
2. Undersize structural steel elements. fabrication prior to installation and erection of steel
3. Non-conformance to the required spacing of purlins trusses to ensure compliance to materials and
and trusses. specifications.
4. Insufficient welding at critical joint. - Require the Project Engineer to make the necessary
adjustment on the materials and workmanship.
- Reject/removed and replaced if necessary.
B. TIMBER TRUSSES
1. Use of low quality, untreated timber materials. - Conduct visual inspection, verification and monitoring of
2. Undersize timber materials. fabrication prior to installation of wooden trusses
3. Non-conformance to the required spacing of purlins including bolts, nuts and nails to ensure compliance to
and trusses. materials and specifications.
- Require Project engineer to make the necessary
adjustment on the materials and workmanship of the
structure.
- Reject/removed and replaced if necessary.
XI. ROOFING WORKS
1. Non-conformance to the required gauge and length. - Removed and replaced.
2. Non-conformance to the specified overlapping( end - Conduct inspection and monitoring to ensure
lap, side lap ). compliance with the plans and specifications.
3. Non-conformance to the approved method of fastening - Require the Project Engineer to make the necessary
and joining. adjustment on the workmanship.
1. Occurrence of leaks. - Conduct further leak test, provide silicon sealant.
2. Non-conformance to the approved material - Reject/removed and replaced if necessary.
requirements such as downspouts, gutter, flashing and
ridge roll. DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
XII. FINISHES
ITEM 1018- CERAMIC TILES
1. Occurrence of cracks on the materials. - Conduct inspection, verification and monitoring of the
2. Uneven laying of tiles. materials and methods of installation to ensure compliance
ITEM 1019- WOOD TILES to specifications.
1. Non-conformance to the design lay-out. - Require/instruct the Project Engineer to make the necessary
2. Uneven laying of tiles. adjustment to the materials and workmanship.
ITEM 1021- CEMENT FLOOR FINISH - Reject/removed and replaced if necessary.
1. Uneven surface. - Defer payment of accomplishment until contractor complied
2. Presence of temperature cracks. with requirements.
3. Weak mixture of fine and course aggregate.
ITEM 1026- PEBBLE WASHOUT FINISH
1. Uneven surface
2. Pebbles are not uniformly distributed.
3. Presence of temperature cracks.
XIII. PAINTING/VARNISHING
ITEM 1032- PAINTING/VARNISHING
1. Non-application of surface neutralizer. - Conduct inspection, verification and monitoring of painting
2. Non-conformance to the number of coat/application of materials to ensure conformance to specifications.
paint. - Require/instruct the Project Engineer to make the necessary
3. Occurrence of feeling-off of paint. adjustment to conform with the specifications.
4. Non-conformance to the approved brand and - Reject/removed and replaced if necessary.
specifications of paint. - Defer payment of accomplishment until the contractor
complied with the requirements.
MANPOWER MATERIALS
EQUIPMENT
DPWH | Bureau of Construction
A MOBILIZATION
GRAVEL BEDDING
1 General Requirements
1.1 Earth- Moving Equipment
2 Methodology
2.1 Construction Survey
2.2 Finding Grade Level
2.3 Setting Batterboards
NYLON CHORD
BATTER BOARD
PLUMB BOB
STAKES
or corners at 90 1/2" x 4’ x 8’
PLYWOOD BOARD
degrees.
2” x 3”
BATTER BOARD
5. Verify the measure- 2” x 2”
STAKES
ment in the plan.
a) Center to Center,
b) Center to Outer Side a c
c) Outer to Outer side
d) Inside to inside. b d
Staking out is done before establishing the grade level. It begins with
locating the lot lines. Corners of the lot should normally be marked with
stakes. Then, proceed:
1. Center and level the instrument (builder’s level or transit) over the lot
corner stake. Measure the setback called for by local codes. Sight across to
the opposite corner stake.
2. Drive a 2 × 2 stake at the setback in line with the lot stakes. Use the
transit or builder’s level to check alignment. The vertical and horizontal
crosshairs should center on the top of the stake. Drive a nail on the top-
center of the stake.
3. Place another stake at the correct setback for one side of the property
line. You are now ready to stake out the building lines.
Staking Procedure
Staking out building lines requires two persons. When a builder’s level is
used, the second person will use a rod that must be plumbed along the line of sight.
Since a transit can pivot up and down, the second person uses a stake to locate
corners along the building line.
1. Attach a plumb bob to the center screw or hook on the underside of the
instrument. Some instruments have an optical plumb for zeroing in over a
point. Shift the tripod until the point of the plumb bob is directly over
the point marking the corner of the building lines. This is at point A on line
AB, as shown in the figure.
2. Level the instrument before proceeding further. Recheck for plumb.
3. From point A (or station A), turn the telescope so the vertical crosshair is
directly in line with the edge of a stake or rod held at point B. When using a
transit, sight the telescope on the stake.
4. Use a measuring tape along line AB to locate distance to the corner. Drive a
corner stake at this point.
3 Quality Control
*For Clearing and Grubbing, Removal of Structures, Structure
Excavation:
3 Quality Control
*For Embankment:
Wood preservation
a process wherein the wood is also
treated with chemical solution and
are applied directly either external
or internal on wood surfaces. LOWER LOCATION :
SOIL POISONING
1 General Requirements
1.1 All labor, materials and equipment to be used in
the completion of the job shall be furnished by the
pest control provider.
2 Treatment Procedures
2.1 Pre-Construction Treatment
2.1a Soil Treatment
2 Treatment Procedures
2 Treatment Procedures
2.2 Post- Construction Treatment
Cordoning Method
- When there is no visible evidence
of termite infestation
Drenching Method
- When the soil shows termite
infestation
2 Treatment Procedures
2.2 Post- Construction Treatment
3 Quality Control
Minimum Test Requirements:
1 General Requirements
Considerations:
1. Check the foundation base or soil condition if it
complies with the boring data.
2. Check the depth if it complies with plans.
3. Check alignment and distances.
4. No footing shall rest on fill.
5. All footings and tie beams shall rest on a well
compacted gravel bed
6. Back fill shall be place in layers at 200mm thk. and
shall be compacted to 95% Maximum Dry Density.
Strip foundation
3 Quality Control
3.1 Pile integrity test
1 General Requirements
1.1 Formworks and Scaffoldings
1.2 Steel Reinforcement
1.3 Cement
1.4 Aggregates
1.5 Water
1.6 Admixture
1.7 Storage of Materials
1 Methods
FORMWORKS AND SCAFFOLDINGS
1. Formworks Construction
B. STEEL REINFORCEMENTS
Steel is considered as an excellent partner of concrete in
resisting tension and compression. The design of reinforced
concrete assumes that concrete and steel acts together in
carrying load in the state of simultaneous deformation.
1. ) Bar splicing
a. Tension Bar
b. Compression Bar
2. ) Bar Spacing
- shall not be less than the normal diameter of the bars or
40 mm for column, or as specified in the structural design notes.
4. Details of Reinforcement
a. ) Standard Hooks
• 180 deg. Bend plus 4 bar diameter extension, but not less
than 65 mm at free end of bar.
• 90 deg. Bend plus 12 bar diameter extension at free end
of bar.
•For stirrup and tie hooks
A. 16mm bar and smaller, 90 deg. Bend plus 6 bar
diameter at free of bar or
B. 20mm and 25mm bar, 90 deg. Bend plus 12 bar
diameter extension at free end of bar or
C. 25mm bar and smaller, 135 deg. Bend plus 6 bar
diameter at free end of bar, or
D. As specified in the structural design notes
6. Bending
2. Storage of Materials
Aggregate Tests
Samples of the fine and coarse aggregates to be used shall be
selected by the engineer for test at least 30 days before the start of
the concreting operations.
No aggregates shall be used unless certified to have satisfactory
passed all tests, and a written authority has been served for their use.
Admixtures
Admixture Shall Conform to
Air-entraining admixtures ASTM C 260
Water-reducing admixture
Retarding
ASTM C 494.
Water-reducing/retarding
Water-reducing/accelerating
Buckets or Hoppers
Pipes
Conveyor Belt
Concrete Pump
Drop
Chute
Maximum
Drop
Height
1.50 meter or
less
PROPER IMPROPER
DPWH | Bureau of Construction
F CONCRETE WORKS
6. Construction Joints
Construction joints shall be made only as shown in the Plans or as
called for in the pouring schedule, unless otherwise approved by
the Engineer. It shall be thoroughly cleaned of foreign matter and
laitance.
4-12mmØ
9mmØ STIRRUPS
350mm THK. CONCRETE
FOOTING
N.G.L.
SECTION
WF (4" CHB) PLAN
F CONCRETE WORKS
7. Curing of Concrete
1. Water Method
2. Curing Compound
3. Waterproof Membrane Method
4. Forms-in-Place Method
3 Quality Control
Minimum Test Requirements:
a) CONCRETE:
1. Design Mix
1.a Batching Plant – to be prepared by the Supplier
1.b Jobsite – to be prepared by the contractor
2. Conduct Trial Mix (reference only)
3. Submit Samples for:
3.a Portland Cement
1- Q (Quality Test) for every 2,000 bags or fraction thereof
3.b Fine Aggregates:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.c Coarse Aggregate:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.d Water:
1- Certificate from Project Engineer
DPWH | Bureau of Construction
F CONCRETE WORKS
2 Methods
Block laying after the
concreting of tied
column
Concreting of column
after block laying of
walls
3 Quality Control
Minimum Test Requirements:
1 Requirements
Quality of Materials
All materials to be incorporated in the carpentry and joinery works
shall be of the quality specified in the approved plans and
specification. Before incorporation in the work, all materials shall
have been inspected / accepted by the Engineer or his authorized
representative.
Shop Drawings
Shop drawings complete with essential dimensions and details of
construction, as may be required by the Engineer in connection with
the carpentry and joinery work, shall be submitted for approval
before proceeding with the work.
a. Drywall Partition
1. Vertical and horizontal alignment
2. Material specification
3. Complete installation of Electro-mechanical rough-ins
4. Rigidly connected to the flooring, walls and at the bottom of the
ceiling frames.
5. Appropriateness of tools to be used.
Ceiling
1. Dimension and alignment of nailers/metal frames
2. Material specification
3. Complete installation of sanitary/plumbing and electro-
mechanical rough-ins
4. Properly anchored to the carrying metal channel/wood runner.
5. Complete installation of roof framing and roofing
6. Appropriateness of tools to be used.
Metal
Steel Stud Furring
Furring Channel
DPWH | Bureau of Construction
H CARPENTRY & JOINERY WORKS
1 Quality Control
TYPES OF WINDOWS
1. WINDOWS
A. Steel Casement Window
B. Awning Window
C. Jalousie Window
D. Sliding Aluminum Framed Window
E. Fixed Aluminum Framed Window
F. Wooden Windows
G. Others
Installation
a. Steel windows
- shall be plumb set and true in the openings. The joints
between the window frame and masonry shall be carefully
caulked. Windows shall be designed for glazing from the
outside with spring wire glazing clips and glazing putty.
2. Glass slats are lugged into the slat clips starting from
way down and up until the whole unit is entirely glazed.
2. DOORS
A. Hollow Core Flush Door
B. Panel Door
C. PVC Door
D. Glass Door
E. Steel Door
F. Others
WOODEN DOORS
Material Requirements
1. Lumber
Lumber doors, windows jambs, and panels when required, shall be
kiln-dried with moisture content of not less than 14% and shall be of
the specie indicated in the Plans and/or specifications.
2. Plywood
Plywood for hollow core flush doors shall be 3-ply, rotary cut, 6mm thick
ordinary plywood or as indicated in the plans.
3. Adhesive
Adhesives shall be water resistant resins and shall be non-staining.
DPWH | Bureau of Construction
I FABRICATED MATERIALS & HARDWARES
Construction Requirements
Fabrication
Wooden doors, including frames, shall be fabricated in accordance
with the designs and sizes shown in the Plans. The fabricated products
shall be finished square, smoothly sanded and free from damage.
Installation
1 Procedure
1. Steel frames are attached together by means of a rivet, a bolt or by
welding. Before assembly, a sample of all the steel members shall be
tested if they conform to the desired strength specified in the plans and
specifications.
3. When punching and drilling steel make sure that the hole drilled or
punched is 1.5 to 3 mm greater than the diameter of the bolt to make it
easy in inserting and bolts through it.
1 Procedure
5. When the work is completed, inspect if it is welded in accordance
with the penetration length and thickness needed in the
construction.
LENGTH OF WELD
1 Quality Control
Minimum Test Requirements:
1 Requirements
Material Requirements
Construction Requirements
A. Preparatory Works
Preparatory to the installation of the corrugated G.I. roofings,
purlins should have been placed and spaced properly to fit the
length of the roofing sheets. The top of the purlins should be
at the same plane.
b) Valleys
Valleys shall lap at least 450 mm each way under the roofing
sheets and shall be secured to the framework with
galvanized nails. The nails are placed below the roofing
sheets. Rivets along the side of the valley shall be fastened
at every second corrugation.
c) Flashing
Flashing, of gauge 26 plain G.I. sheets, unless otherwise specified,
shall be installed along intersections of roofs and concrete or
masonry walls. Flashing running parallel to sheet corrugations must
have its edge turned down. Flashing across sheet corrugations or at
an angle thereto, shall lap at least 250 mm and the edge of flashing
turned down at each corrugation.
d) Gutters
Gutters, of gauge 24 plain G.I. sheets, shall be fabricated to the
shape and dimensions indicated in the Plans. Gutter joints shall be
flat seam folded in the direction of flow and soldered evenly. Gutter
shall be attached to fascia board with appropriate nails or screws
spaced of not more than 900 mm on centers. As additional support,
gutters shall have plain G.I. strap hangers 25 mm wide fastened to the
roof nailers and shall be spaced at not more than 900 mm on centers.
The gutter shall be installed with a pitch of 1 in 100 sloped toward
the downspout.
2 Methods
a. Lay-outing
In laying out the placement for the J-
Bolts, make sure that it will be aligned
near enough to the lip of the purlin
avoiding it to be drilled when making
holes. A guide chord may be stretched
out from end to end of the purlin to
establish alignment.
b. Drilling
c. Installation
In the installation of J-Bolt, two (2)
manpower is required to work
concurrently. One will insert the bolt
through the hole from the indoor
and the other will fasten the nut out
door.
3 Quality Control
Minimum Test Requirements:
1 Requirements
CERAMIC TILES
Material Requirements
a. Glazed Tiles and Trims
b. Unglazed Tiles
c. Trims
d. Accessories
e. Cement
f. Sand
g. Lime
Construction Requirements
A. Surface Preparation
B. Installation Procedure
• Before the tile is applied the floor surface shall be tested for
levelness or uniformity of slope by flooding it with water.
• Ceramic tiles shall be soaked in clean water prior to
installation for a minimum duration of one hour.
• Determine and mark the layout of ceramic tiles, joint
location and position of trims and fixtures so as to minimize
the incidence of a tile being cut less than one half of its size.
• All lines shall be kept straight and true to profiles, plumbed
and internal corners rounded using the appropriate trims.
• Pitch the floor to drain as shown in the Plans or as directed
by the Engineer
C. Grouting and Pointing - Tiles shall have been laid in place for
at least 24 hours before grouting of the joints is started
D. Cleaning
E. Protection from Construction Dirt
DPWH | Bureau of Construction
L Ceramic Wall Tiles
D. Cleaning
1 2
3
DPWH | Bureau of Construction
L FINISHES
PEBBLE WASHOUT
This Item shall consist of furnishing all materials, labor,
tools and equipment required in undertaking the proper
application of pebble washout finish as shown in the
Plans and in accordance with Specifications.
1 2 3
4 5
DPWH | Bureau of Construction
L FINISHES
4. Trowel finish
3 Quality Control
Minimum Test Requirements:
1 Requirements
Material Requirements Construction Requirements
a. Paint Materials a. Surface Preparation
b. Tinting Colors b. Application
c. Concrete Neutralizer c. Mixing and Thinning
d. Silicon Water Repellant d. Storage
e. Patching Compound e. Cleaning
f. Varnish f. Workmanship
g. Lacquer g. Method of Measurement
h. Shellac h. Basis of Payment
i. Sanding Sealer
j. Glazing Putty
k. Natural Wood Paste Filler
Surface Preparation
Surface preparation
for Boards Surface preparation
for Concrete &
Masonry Surface
A. Types of Waterproofing
Cement-base Waterproofing
Membrane Waterproofing
Liquid Waterproofing
a. Installation of Pipes
b. Sewer Connections and Clean-outs
c. Inspection and Quality Control
d. As-built drawings
DPWH | Bureau of Construction
O SANITARY WORKS
Plumbing
This Item shall consist of furnishing all materials, tools,
equipment and fixtures required as shown in the Plans for
the satisfactory performance of the entire plumbing system
including installation in accordance with the latest edition
of the National Plumbing Code and Specifications.
Material Requirements
a. Water supply pipes and fittings
b. Approved alternate pipe and fittings
c. Septic Tank
d. Plumbing fixtures and fittings
e. Roof Drains, Downspout
Plumbing
Construction Requirements
Quality Control
Minimum Test Requirements:
COMMON PROBLEMS