100% found this document useful (1 vote)
390 views172 pages

Building Construction Methods-2

The document contains architectural, structural, and plumbing plans for a proposed one-story, one-classroom school building project with a duration of 30 calendar days. The plans include floor plans, elevations, sections, and details of the building layout, structural elements like beams and footings, and the plumbing system with water, drainage, and ventilation. The plans were prepared according to the National Building Code and aim to provide specifications for the pre-construction, construction, and post-completion stages of the project.

Uploaded by

Ag Missing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
390 views172 pages

Building Construction Methods-2

The document contains architectural, structural, and plumbing plans for a proposed one-story, one-classroom school building project with a duration of 30 calendar days. The plans include floor plans, elevations, sections, and details of the building layout, structural elements like beams and footings, and the plumbing system with water, drainage, and ventilation. The plans were prepared according to the National Building Code and aim to provide specifications for the pre-construction, construction, and post-completion stages of the project.

Uploaded by

Ag Missing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 172

+

PLANS SPECIFICATIONS PHYSICAL STRUCTURE

STAGE 1 STAGE 2 STAGE 3

PRE COMPLETION/
CONSTRUCTION POST
CONSTRUCTION COMPLETION
STAGE I

PRE CONSTRUCTION
NATIONAL BUILDING CODE
( P.D. 1096 )
5 MAJOR DIVISIONS IN BUILDING PLANS

ARCHITECTURAL AESTHETIC ARCHITECT

STRUCTURAL STRENGTH CIVIL ENGR

ELECTRICAL/ POWER, LIGHTING ELECTL ENGR/


ELECTRONIC & COMMUNICATION ELECTRONIC ENGR

SANITARY/ HEALTH AND SANITARY ENGR/


PLUMBING SANITATION MASTER PLUMBER

MECHANICAL NECESSITIES MECHANICAL ENGR


PROJECT: ONE(1) STOREY ONE (1) CLASSROOM SCHOOL BUILDING
DURATION: 30 CALENDAR DAYS

ARCHITECTURAL PLAN

1 2 3 3 2 1 A B C

GA 26 CORR. G I. GA 26 CORR. G I.
ROOFING ROOFING

D-1 D-1 D-1 W-2


W-1 W-1 W-2 W-2 CLASSROOM

FRONT ELEVATION REAR ELEVATION CROSS SECTION

1 2 3 2 1 2 3
1 3
SCH. OF DOORS & WINDOWS

C C C
W-2 W-2

EXPOSED SLOPE
B STEEL ‘C’ B
CLASSROOM B PURLINS AND
SLOPE
RAFTERS D-1 W-1 & W-2
FLUSH TYPE GLASS JALOUSIE
D-1 W-1 W-1 D-1 HOLLOW CORE WINDOWS ON
A A A DOOR W MARINE ALUMINUM HOUSIG
CORRIDOR PLYWOOD FACING
ON WOOD FRAME
FLOOR PLAN REFLECTED CEILING ROOF PLAN

*PLANS BY BOD
STRUCTURAL PLAN
C-PURLINS
RAFTER C
A B
ANGULAR
BRACE
CORR. GI
SHEETS

C1-F1 C1-F1 C1-F1

WF-1 WF-1

WF-1

WF-1
LB LB
BASE PLATE W LONG
ANCHOR BOLTS

C1-F1
C1-F1
ROOF INSULATION CEILING
FIN. COMPRESSED BETWEEN SLAB ON FILL
PURLINS AND RAFTER
D-1 W-2

WF-1
WF-1
CORRIDOR
DOWEL
CLASSROOM FFL WF-1 WF-1
FGL
WELL COMPACTED NGL
COL. FTG. C1-F1 C1-F1 C1-F1
GRAVEL FILL
WALL FTG
DETAIL CROSS SECTION
FOUNDATION PLAN

LINTEL BEAM SPOT DETAIL


LINTEL BEAMS
FOOTING COLUMN WALL FOOTING

*PLANS BY BOD
STRUCTURAL PLAN
A A1
L

L/4 L/2 L/4


3 -16mmØ TOP BARS
2 -16mmØ ADD'L. BARS @ L/4

3 -16mmØ BOTTOM BARS 2 -16mmØ ADD'L. BARS @ L/2

TYPICAL BEAM DETAIL


SCALE 1 : 10m

9-12mmØ MATTING BARS


EQUALLY SPACED BOTHWAYS

4-16mmØ VERTICAL BARS W/


9mmØ TIES, SPACED 5 @
50mm, 5 @ 100mm, REST @
200mm ON CENTERS

4-12mmØ
9mmØ STIRRUPS
350mm THK. CONCRETE
FOOTING

N.G.L.

4-12mmØ MAIN BARS W/


9mmØ STIRRUPS
NATURAL GRADE LINE

4-16mmØ VERTICAL BARS W/


9mmØ TIES, SPACED 5 @
50mm, 5 @ 100mm, REST @
200mm ON CENTERS
9-12mmØ MATTING BARS
EQUALLY SPACED BOTHWAYS

SECTION
WF (4" CHB) PLAN
PLUMBING SYSTEM
WATER LINE INCLUDING DRAINAGE, WASTE AND VENTILATION SYSTEM OF BUILDING

VENTILATION THROUGH ROOF ( VTR )

DRY VENT

SHOWER W/ ACCESORIES MAIN VENT

BATH TUB LAVATORIES


FIXTURES

WATER CLOSET
HOT WATER RETURN
FLOOR DRAIN
KITCHEN SINK
FIXTURES

COLD WATER LINE


W/ ACCESORIES FITTINGS
WET VENT
HOT WATER LINE
CLEAN OUT
W/ ACCESSORIES

WATER HEATER WASTE / SOIL PIPE


CORRELATION BETWEEN PLANS & SPECIFICATIONS
(PER CLAUSE 52 OF DPWH STD. SPECS, VOL. 1 1988 ED.)

THE SPECIFICATIONS AND APPROVED PLANS, SPECIFIED PROVISIONS AND


ALL DOCUMENTS AFFECTING THE WORK, DULY ISSUED BY THE ENGINEER
TO THE CONTRACTOR ARE ESSENTIAL PARTS OF THE CONTRACT. THEY ARE
INTENDED TO BE MUTUALLY COMPLEMENTARY. IN CASE OF DISCREPANCY,
SPECIAL PROVISIONS SHALL PREVAIL OVER ALL PLANS AND
SPECIFICATIONS; PLANS SHALL GOVERN OVER SPECIFICATIONS;
SUPPLEMENTARY SPECIFICATIONS SHALL GOVERN OVER ORIGINAL
SPECIFICATIONS; ON ALL PLANS, THE FIGURED DIMENSION, UNLESS
OBVIOUSLY INCORRECT, SHALL GOVERN IN CASE OF ANY DISCREPANCY
BETWEEN FIGURED DIMENSIONS AND SCALED DIMENSIONS.
MANPOWER REQUIREMENT

TECHNICAL SAFETY & HEALTH SKILLED / UNSKILLED


(DO 56 S.2005)

PROJECT ENGINEER SAFETY ENGINEER CONST. FOREMAN


RESIDENT ENGINEER SAFETY OFFICER LEADMAN
FIRST AIDER CARPENTER
MTQC ENGINEER
NURSES MASON
QTY./COST ENGINEER
STEEL MAN
SANITARY ENGINEER
WELDER
ELECTRICAL ENGINEER TINSMITH
MECHANICAL ENGINEER INSTALLER
PAINTER
PLUMBER
ELECTRICIAN
LABORER
PILE FOUNDATION DRILLING, DRIVING, BORING, GRABBING EQUIPMENT

SMALL DRILLING EQPT. DROP HAMMER DRIVING HEAVY BORING RIG W/ VIBRO HEAVY CABLE GRAB
USE FOR MICRO PILES RIG FOR PRE CAST PILES HAMMER FOR BORED PILES FOR BARRETTE PILES

EXCAVATOR-USE IN TRUCK MIXER TANDEM WITH TRUCK MOUNTED/CRAWLER CRANE -


LARGE DIMENSION PUMPCRETE USE IN POURING OF USE TO CARRY & MANEUVER PRE CAST
EXCAVATION & DIGGING HEAVY FOUNDATIONS. PILE & STEEL CAGES.

WHEEL LOADER TANDEM W/ DUMP TRUCK - GENERATOR SET / WELDING MACHINE –


USE FOR HAULING & DISPOSAL OF DEBRIS USE AS CONNECTORS ON HEAVY
AND OTHER EXCAVATED MATERIALS. STRUCTURAL STEEL MEMBERS.
WHEEL LOADER TANDEM W/ DUMP TRUCK-USE
FOR HAULING & DISPOSAL OF DEBRIS AND
MOBILE CRANES – USE TO OTHER MATERIALS WITHIN THE PERIPHERAL
MANEUVER AROUND & OUTSIDE OF THE BUILDINGS
THE BUILDING TO HOIST
MATERIALS & EQUIPMENT FROM
VARIOUS LOCATIONS

TRUCK MIXER TANDEM WITH PUMPCRETE USE


IN POURING OF HEAVY SUPERSTRUCTURE
MEMBERS.

FORMS & SCAFFOLDING – USE


TOWER CRANE – USE AS AS GUIDE & SUPPORT
CIRCUMFERENTIAL LIFTING SYSTEM IN FORMING &
MECHANISM TO TRANSPORT CHECKING ALIGNMENT OF GENERATOR SET / WELDING MACHINE –
VITAL CONSTRUCTION STRUCTURAL MEMBERS IN & USE AS CONNECTORS ON HEAVY
MATERIALS & EQUIPMENT AROUND THE BUILDINGS. STRUCTURAL STEEL MEMBERS.
WHEEL LOADER EXCAVATOR/BREAKER BULLDOZER GRADER

ROLLER TRUCK MIXER DUMP TRUCK


TRAILER TRUCK
RING AND BAR BENDER
SAMPLING MOLD BAR CUTTER CONCRETE VIBRATOR

1- BAGGER 2 – BAGGER PORTA LIFT HOLLOW BLOCK MACHINE


CONCRETE MIXER CONCRETE MIXER

PLATE COMPACTOR TAMPING RAMMER WALK BEHIND ROLLER SUBMERSIBLE PUMP


14. PREPARATION OF MINIMUM REQUIREMENTS FOR A CONSTRUCTION
SAFETY AND HEALTH PROGRAM FOR THE PROJECT BEING CONSIDERED

PURPOSE
THIS DEPARTMENT ORDER SETS THE GUIDELINES, RULES AND PROCEDURES, TO BE FOLLOWED
BY ALL CONCERNED IN THE IMPLEMENTATION OF DEPARTMENT OF LABOR AND EMPLOYMENT D.O.
No. 13(DOLE D.O. No.13), SERIES OF 1998 OTHERWISE KNOWN AS THE “GUIDELINES GOVERNING
OCCUPATIONAL SAFETY AND HEALTH IN THE CONSTRUCTION INDUSTRY”, WITH EMPHASIS GIVEN
ON THE METHODOLOGY TO BE USED IN ESTIMATING THE COST OF CONSTRUCTION SAFETY AND
HEALTH PROGRAM AS REQUIRED IN SECTION 17.

GENERAL GUIDELINES
IN COMPLIANCE WITH SECTION 17 OF DOLE D.O. No. 13, THE IMPLENTATION OF CONSTRUCTION
SAFETY SHALL BE CONSIDERED IN ALL STAGES OF PROJECT PROCUREMENT ( DESIGN,
ESTIMATE, AND CONSTRUCTION ) AND ITS COST SHALL BE INTEGRATED TO THE OVERALL
PROJECT COST UNDER PAY ITEM “SPL- CONSTRUCTION SAFETY AND HEALTH” AS A LUMPSUM
AMOUNT, TO BE QUANTIFIED IN THE DETAILED ESTIMATE. LIKEWISE, ALL REQUIREMENTS,
PROVISIONS, AND INSTRUCTIONS PERTAINING TO THE IMPLEMENTATION OF CONSTRUCTION
SAFETY AND HEALTH IN EVERY PROJECT SHALL BE INCLUDED IN THE PROJECT BIDDING
DOCUMENTS SPECIFICALLY UNDER THE INSTRUCTION TO BIDDERS.
CONCTRUCTION PROJECT
(D.O. No. 56 S. 2005)

CONSTRUCTION SAFETY AND HEALTH PROGRAM ( CSHP )


THE REQUIRED CSHP FOR SPECIFIC PROJECT SHALL INCLUDE BUT NOT LIMITED TO THE FF :
1. COMPOSITION OF SAFETY & HEALTH PERSONNEL RESPONSIBLE FOR THE IMPLENTATION OF CSHP;
2. SPECIFIC SAFETY POLICIES W/C SHALL BE UNDERTAKEN IN THE CONSTRUCTION SITE INCLUDING
FREQUENCY OF & PERSONS RESPONSIBLE FOR CONDUCTING TOOL BOX AND GANG MEETING;
3. PENALTIES AND SANCTIONS FOR VIOLATIONS OF THE CSHP;
4. FREQUENCY, CONTENT AND PERSONS RESPONSIBLE FOR ORIENTING, INSTRUCTING AND TRAINING
ALL WORKERS AT THE SITE WITH REGARD TO THE CSHP WHICH THEY OPERATE; &
5. THE MANNER OF DISPOSING WASTE ARISING FROM THE CONSTRUCTION.

MANPOWER EQUIPMENT/FACILITIES

1. SAFETY ENGINEER / OFFICER


2. SAFETY MAN / OFFICER 1. PERSONAL PROTECTIVE EQUPMENT (PPE)
-AS RECOMMENDED BY DOLE, FOR EVERY -FOR GENERAL CONST. THE REQUIRED BASIC
CONST. PROJ. W 100 & ABOVE WORKERS, AN PPE FOR ALL WORKERS SHALL BE SAFETY
ACCREDTED SAFETY OFFICER BY DOLE-BWC HELMET, SAFETY GLOVES AND SAFETY SHOES.
SHALL BE EMPLOYED. ONLY THE COST FOR THE SPECIALTY PPE SHALL BE PROVIDED IN ADDITION
CONST. SAFETY & HEALTH OFICER , WHETHER TO OR IN LIEU OF THE CORRESPONDING PPE AS
ON FULL OR PART TIME BASIS ASSIGNED ON THE WORK ACTIVITY REQUIRES.
SITE SHALL BE INCLUDED IN THE ESTIMATE. 2. SIGNAGES AND BARRICADES
3. HEALTH PERSONNEL -SHALL BE PROVIDED AS A PRECAUTION TO
-ONLY THE MEDICAL AND DENTAL ADVICE THE WORKERS & THE GENERAL PUBLIC
PRACTITIONERS ACTUALLY ASSIGNED IN THE OF THE HAZARDS EXISTING AT THE WORKSITE.
PROJECT SHALL BE INCLUDED IN THE COST OF 3. FACILITIES
SAFETY. - W ADEQUTE SAFE DRINKING WATER;
SANITARY & WASHING FACILITIES: LIVING
ACCOMODATIONS FOR WORKERS.

COSTING
PAY ITEM “SPL – CONSTRUCTION SAFETY AND HEALTH” AS
A LUMP SUM AMOUNT, TO BE QUANTIFIED IN THE DETAILED
ESTIMATE.
NOTE : DERIVED FROM CPES MANUAL
BUILDING CONSTRUCTION METHODOLOGY
( BY PERT/CPM DIAGRAM)
PROJECT: ONE(1) STOREY TWO(2) BEDROOM LOW COST HOUSING

PROCUREMENT/DELIVERY OF CONSTRUCTION MATERIALS


D
26

ELECTRICAL/SANITARY ROUGH-IN
J
16
14 INST. ELECT/
12 MECH/SANITARY
CARPENTRY WORKS FIXTURES
P S
2 1
1 2 6
MOVE- 4 13 17
IN
EARTH CONCRETE MASONRY 8 1O 15 MOVE
WORKS WORKS WORKS ROOF FRAMING ROOFING FINISHES PAINTING OUT
A B C F H M N Q T V
2 2 5 3 5 4 4 3 2
WAIT WAIT
WAIT WAIT WAIT
2 4
E G K O R U
1 2 2
SOIL BACKFILL INST. OF PURLINS INST. GUTTER & INST. FAB. MATLS &
HARDWARE
POISONING 5 WAIT 9 FLUSHING
3 11 14
I W
3
DAMPROOFING/SLAB ON FILL
7
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
CALENDAR DAYS
LEGEND:

NETWORK - A B
ES LS EF LF
ACTIVITY -

EVENT - A
ES LS
DUMMY -

CRITICAL PATH -
STAGE II

CONSTRUCTION

NVPILAR 2008
NVPILAR 2008
CONSTRUCTION METHODOLOGY FOR BUILDINGS
STAGE I – WORK ACTIVITIES BELOW / ON GROUND

PART A – MOBILIZATION
-MOVING IN OF MANPOWER,
EQUIPMENT & MATERIALS AT
THE PROJECT SITE.
PART A-FACILITIES FOR THE ENGR
A.1.1- OFFICES & LABORATORIES
A.1.2- VEHICLES FOR THE ENGR
A.1.3- ASSISTANCE TO THE ENGR
A.1.4- PHOTOGRAPH

PART E – DAMPROOFING/
MOISTURE CONTROL
ABOVE/ON GROUND
PART C – TERMITE CONTROL -POLYETHELENE SHEETS
& WOOD PRESERVATION BELOW GROUND
DPWH SPECS VOL III- ITEM 1000 DPWH SPECS VOL III ’95 ED.
UPPER- WOOD PRESERVATION ITEM 1016-WATERPROOFING
LOWER- SOIL POISONING -HYDROLITHIC WATERPROOFNG

PART B- EARTHWORKS PART D – FOUNDATION WORKS


-COVERS MINOR/MAJOR A. SHALLOW FOUNDATION-
EXCAVATION & BACKFILL SPREAD,STRIP, MAT FOUNDATION
EARTHFILL & GRAVELFILL B. DEEP PILE FOUNDATION
DPWH SPECS VOL III ’95 ED. DPWH SPECS VOL II ’04 ED.
ITEM 800-CLEARING & GRUBBING ITEM 400- PILING
ITEM 801-REMOVAL OF STRCTURE DPWH SPECS VOL III ‘95 ED.
AND OBSTRUCTIONS ITEM 1300-PILING TO INCLUDE
ITEM 802-EXCAVATION SHEET PILING
ITEM 803-STRUCTURE EXCVATION ITEM 1301-TEST PILE
ITEM 804-EMBANKMENT
NVPILAR 2008
CONSTRUCTION METHODOLOGY FOR BUILDINGS

STAGE II – WORK ACTIVITIES ON THE BUILDING FRAMEWORKS

PART H – CARPENTRY WORKS


-PARTITIONS, CEILINGS,CABINETS, PART K – ROOFING WORKS
WOOD STAIRS AND OTHERS. DPWH SPECS VOLIII ’95 ED.
DPWH SPECS VOL III ’95 ED. ITEM 1013-CORR. METAL ROOFING
ITEM 1003-CARPENTRY AND ITEM 1014-PREPAINTED METAL SHTS
JOINERY WORKS. ITEM 1015-CLAY ROOF TILES
ITEM 1016-ROOF DRAINS & STRAINERS
PART G – MASONRY WORKS
-CONCR. HOLLOW BLOCKS PART J – ROOF FRAMING WORKS
BRICKWORKS, TILEWORKS DPWH SPECS VOL II ’04 ED.
& OTHERS. ITEM 402-TIMBER STRUCTURE
DPWH SPECS VOL II ’04 ED. ITEM 403-METAL STRUCTURE
ITEM 506(1)A-MASONRY UNITS ITEM 712-STRUCTURAL METAL
ITEM 713-TREATED & UNTREATED
TIMBER
PART F – CONCRETE WORKS
-FOUNDTION FOOTINGS,COLUMNS,
PART I – FABRICATED
GIRDERS, BEAMS & SLABS.
MATERIALS & H’WARE
DPWH SPECS VOL II ’04 ED.
DPWH SPECS VOL III ’95 ED.
ITEM 311-PCCP
ITEM 1004-HARDWARE
ITEM 404-REINFORCING STEEL
ITEM 1005-STEEL WINDOWS
ITEM 405-STRUCTURAL CONCRETE
ITEM 1006-STEEL DOORS & FRAMES
ITEM 406-PRE-STRESSED CONCRTE
ITEM 1007-ALUMINUM GLASS DOORS
STRUCTURES
ITEM 1008-ALUMINUM GLASS WDOW
ITEM 407-CONCRETE STRUCTURES
ITEM 1009-JALOUSIE WINDOWS
ITEM 700-HYDRAULIC CEMENT
ITEM 1010-WOODEN DOORS & WDOW
ITEM 703-AGGREGATES
ITEM 1011-ROLLING-UP DOORS
DPWH SPECS VOL III ’95 ED.
ITEM 1012-GLASS AND GLAZING
ITEM 900-REINFORCED CONCRETE

NVPILAR 2008
CONSTRUCTION METHODOLOGY FOR BUILDINGS
STAGE III – FINISHING WORKS / COMPLETION OF THE STRUCTURE

PART R – CONST. SAFETY AND HEALTH (DO. 56)


PART N – WATERPROOFING WORKS
DPWH SPECS VOL III ’95 ED.
ITEM 1016-WATERPROOFING
TYPES OF WATERPROOFING PART Q – MECHANICAL WORKS
1. CEMENT BASE WATERPROOFING DPWH SPECS VOL III ’95 ED.
2. MEMBRANE WATERPROOFING ITEM 1200- AIR CONDITIONING AND
3. LIQUID WATERPROOFING REFRIGERATION SYSTEM
4. HYDROLITHIC WATERPROOFING ITEM 1201-WATER PUMPING SYSTEM
ITEM 1202-AUTOMATIC WATER
SPRINKLER SYSTEM
PART M – PAINTING / VARNISHING ITEM 1203-ELECTRIC ELEVATOR
DPWH SPECS VOL III ’95 ED. ITEM 1204-ELECTRIC DUMBWAITER
ITEM 1032-PAINTING/VARNISHING AND ITEM 1205-OXYGEN, NITROUS OXIDE,
OTHER RELATED WORKS VACUUM & FUEL SYSTEM
-EXTERIOR & INTERIOR ITEM 1206- HEATING SYSTEM
ITEM 1207-BOILER
PART L – FINISHES
DPWH SPECS VOL III ’95 ED. PART P – ELECTRICAL WORKS
ITEM 1018-CERAMIC TILES DPWH SPECS VOL III ’95 ED.
ITEM 1019-WOOD TILES ITEM 1100-CONDUITS, BOXES
ITEM 1020-VINYL FLOOR TILES AND FITTINGS
ITEM 1021-CEMENT FLOOR TILES ITEM 1101-WIRES & WIRING DEVICES
ITEM 1022-STUCCO FINISH ITEM 1102-POWERLOAD CENTER,
ITEM 1023-GRANOLITHIC MARBLE FIN. SWITCHGEAR & PANEL BOARD
ITEM 1024-PEA GRAVEL WASH-OUT FIN
ITEM 1025-BUSH HAMMERED FINISH PART O – SANITARY WORKS
ITEM 1026-PEBBLE WASH-OUT FINISH DPWH SPECS VOL III ’95 ED.
ITEM 1027-CEMENT PLASTER FINISH ITEM 1001-STORM DRAINAGE AND
ITEM 1028-SYNTHETIC ADOBE FINISH SEWERAGE SYSTEM
ITEM 1029-GRANATITE WASH-OUT FIN ITEM 1002-PLUMBING

NVPILAR 2008
1. WORKMANSHIP
2. MATERIALS
3. TIME
4. FACILITIES
5. ENVIRONMENTAL, SAFETY & HEALTH
6. RESOURCE DEPLOYMENT

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


1
THE METHODOLOGY, TECHNIQUE AND CRAFTMANSHIP APPLIED BY
THE CONTRACTOR OR THE IMPLEMENTING OFFICE TO ATTAIN THE
HIGHEST QUALITY CALLED FOR IN ACCORDANCE WITH THE APPROVED
PLANS AND SPECIFICATIONS.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


2
THE QUALITY, QUANTITY AND TYPE OF CONSTRUCTION MATERIALS AND
COMPONENTS SUPPLIED BY THE CONTRACTOR OR THE IMPLEMENTING
OFFICE OR BY OTHER ENTITIES MEETING THE STANDARD SET IN THE
QUALITY ASSURANCE (QA) AND QUALITY CONTROL PROGRAM (QCP) OF
THE PROJECT.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


3
THE DURATION IN WHICH THE CONTRACTOR OR THE IMPLEMENTING
OFFICE WILL SATISFACTORILY COMPLETE THE PROJECT IN ACCORDANCE
WITH APPROVED SCHEDULE INDICATED IN THE PERT/CPM, BAR CHART
WITH S-CURVE OR APPROVED PROGRAM OF WORKS.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


4
THE TEMPORARY FACILITIES SET UP AND MAINTAIN BY THE
CONTRACTOR FOR THE ENTIRE DURATION OF THE PROJECT WHICH
CONFORM TO THE BEST STANDARD SET FORTH IN THE CONDITIONS AND
SPECIFICATIONS OF THE CONTRACT.
THIS INCLUDES PROJECT SIGNBOARD, FIELD AND OFFICE FACILITIES,
TRANSPORTATIONS, AND OTHER EQUIPMENT REQUIRED IN THE
CONTRACT.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


5
THE MANDATORY PROVISIONS OF A CONSTRUCTION SAFETY AND
HEALTH PROGRAM IN ACCORDANCE WITH D.O. No. 13 s. 1998 OF DOLE
AND D.O. No. 56 S. 2005 OF DPWH AS REQUIRED IN THE CONTRACT TO
ENSURE PROTECTION OF WORKERS AND THE GENERAL PUBLIC
WITHIN THE DURATION OF THE PROJECT.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


6
THE CAPACITY AND ABILITY OF THE CONTRACTOR OR THE
IMPLEMENTING OFFICE TO BALANCED THE MOBILITY OF RESOURCES
SUCH AS MANPOWER, MATERIALS, AND EQUIPTMENT AT A GIVEN
TIME BASED ON THE APPROVED SCHEDULE (PERT/CPM, CASH FLOW,
MANPOWER SCHEDULE, EQUIPTMENT SCHEDULE, AND BAR CHART)
WITHIN THE DURATION OF THE PROJECT.

NOTE : DERIVED FROM CPES MANUAL NVPILAR 2008


STAGE III

COMPLETION/POST COMPLETION
PREPARATION OF AS – BUILT PLANS & SPECS.
( RULE II OF THE I.R.R. OF PD. 1096 )

AS – BUILT PLANS AND SPECIFICATIONS JOINTLY SIGNED AND SEALED


BY THE DESIGNING ARCHITECT OR CIVIL ENGINEER AND THE
ARCHITECT OR CIVIL ENGINEER IN – CHARGE OF THE CONTRUCTION
AND SIGNED BY THE CONTRACTOR ( IF THE CONSTRUCTION IS
UNDERTAKEN BY CONTRACT ) AND CONFIRMED BY THE OWNER. SAID
PLANS AND SPECIFICATIONS SHALL REFLECT FAITHFULLY ALL
CHANGES, MODIFICATIONS AND ALTERATIONS MADE ON THE
ORIGINALLY APPROVED PLANS AND SPECIFICATIONS WHICH ARE THE
BASIS OF THE ISSUANCE OF THE ORIGINAL BUILDING PERMIT.
WARRANTY
( R.A. 9184, RULE XIX, SECTION 62 )

SECTION 62.2
For the procurement of infrastructure projects, the contractor shall assume full responsibility for
the contract work from the time project construction commenced up to final acceptance by the
government and shall be held responsible for any damage or destruction of the works except
those occasioned by force majeure. The contractor shall be fully responsible for the safety,
protection, security and convenience of his personnel, third parties, and the public at large, as
well as the works, equipment, installation and the like to be affected by his construction work
and shall be required to put up a warranty security in the form of cash, bank guarantee, letter of
credit, GSIS or surety bond callable on demand, in accordance with the following schedule:

FORM OF WARRANTY Minimum Amount in % of Total


Contract Price
1. Cash deposit, Cash bond or letter of credit Five Percent ( 5% )
2. Bank Guarantee Ten Percent ( 10 % )
3. Surety bond Thirty Percent ( 30% )

The warranty security shall be stated in Philippine pesos, shall remain effective during the
applicable warranty period provided in section 62.2.2 hereof, and shall be returned only after the
lapse of the said warranty period.
WARRANTY
( R.A. 9184, RULE XIX, SECTION 62 )
62.2.2.
After final acceptance of the project by the Government, the contractor shall be held
responsible for structural defects and/or failure of the completed project within the
following warranty periods from final acceptance, except those occasioned by force
majeure and those cause by other parties:
A) Permanent Structures: Fifteen (15) years
Buildings of types 4 (steel, iron, concrete, or masonry construction with walls,
ceilings, and permanent partitions of incumbustible fire resistance) and 5 (steel,
iron, concrete, or masonry construction), steel and concrete bridges, flyovers,
concrete aircraft movement areas, ports, dams, diversion tunnels, causeways,
wharves, piers, dikes, filtration and treatment plants, sewerage systems, power
plants, transmission and communication towers, railway system, and other
similar structures;

B) Semi-Permanent Structures: Five (5) years


Buildings of types 1 (wooden), 2 (wood with 1 hour fire resistance), and 3 (masonry
and wood construction), concrete roads, asphalt roads, river control, drainage,
irrigation and drainage canals, municipal ports and river landing, deep wells, rock
causeway, pedestrian overpass, and other similar structures; and

C) Other Structures: Two (2) years


Bailey and wooden bridges, shallow wells, spring developments, and other similar
structures.
62.2.1.
The defects liability period for infrastructure projects shall be one year from
project completion up to final acceptance by the Government. During this period,
the contractor shall undertake the repair works, at his own expense, of any
damage to the infrastructure projects on account of the use of materials of
inferior quality within ninety (90) days from the time the head of the procuring
entity has issued an order to undertake repair. In case of failure or refusal to
comply with this mandate, the Government shall undertake such repair works and
shall be entitled to full reimbursement of expenses incurred therein upon demand.
Any contractor who fails to comply with the preceding paragraph shall suffer
perpetual disqualification from participating in any public bidding and his property
or properties shall be subject to attachment or garnishment proceedings to
recover the costs. All payables of Government in his favor shall be offset to
recover the costs.
Field Engineer’s Course

Building Construction Methods,


Equipment Requirements,
Proper Supervision,
Common Problems and Safety Measures

• EDGARDO C. GARCES • DANIEL A. PABLICO • ROSELYN C. NIEBRES • LEONARDO E. JARAPLASAN DPWH | Bureau of Construction
Scope of Works in Building Construction

A – MOBILIZATION,

B – EARTHWORKS

C – TERMITE CONTROL & WOOD PRESERVATION

D – FOUNDATION WORKS

E – DAMP PROOFING / MOISTURE CONTROL

F – CONCRETE WORKS

G – MASONRY WORKS

H – CARPENTRY WORKS

I – FABRICATED MATERIALS AND HARDWARES

DPWH | Bureau of Construction


Scope of Works in Building Construction

J – ROOF FRAMING WORKS

K – ROOFING WORKS

L – FINISHES

M – PAINTING / VARNISHING

N – WATER PROOFING

O – SANITARY WORKS

P – ELECTRICAL WORKS

Q – MECHANICAL WORKS

DPWH | Bureau of Construction


COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
I. MOBILIZATION
1. Insufficient manpower deployed in the project site. - Work overtime to catch-up with the schedule and
2. Inadequate equipment deployed in the project site. programs.
-Thoroughly review/check PERT/CPM and schedule then
make the necessary adjustment on the number of
manpower and equipment to avoid delay.
-Impose sanction if necessary.
3. Lack/Inadequate supply of construction materials. -Review/Check the flow and the acquisition of supply by
the contractor, if found inadequate, require the contractor
to make the necessary adjustment to catch-up with the
requirement.
-Review the financial status of the contractor.
-If possible prioritize construction activities based on the
availability of the construction materials.
-Impose sanction if necessary.

4. Inadequate/lack of testing equipment on the project - Require the contractor to strictly follow the requirement
site. of the contract.
5. Inadequate/lack of safety measures and signboards -Conduct briefing and trained contractors personnel on
including Personal Protective the necessity of these requirement as part of the
Equipment of workers on the project site. contract.
6. Improper disposal of waste materials and debris within -Provide/set-up guidelines and procedures for immediate
the project site. implementation of the contractor.
7. Lack of the necessary permit and clearances from -Imposed sanctions if necessary.
local officials.

DPWH | Bureau of Construction


COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
II. EARTHWORKS
ITEM 800-CLEARING AND GRUBBING -Verify plan if the structure to be constructed will be
ITEM 801-REMOVAL OF STRUCTURES AND directly affected by the underground utilities.
OBSTRUCTIONS -Report/coordinate to proper authorities for removal and
1. Presence of underground utilities such as power or relocation.
lines, PLDT, existing MWSS lines. -Check construction schedule and prepare necessary
2. Presence of underneath existing structure such as adjustment in the contract duration or prepare revised
existing footing foundation. PERT/CPM incorporating said encountered problem.
3.Cut-off elevation not clearly established.
ITEM 802: EXCAVATION
ITEM 803: STRUCTURE EXCAVATION -Review/checked plan as against field measurements and
1. Non conformance to the make the necessary corrections and adjustments.
requirements for lines, grades, dimension and -Don’t allow the contractor to continue the work
elevations. unless otherwise said defect had been corrected.
2. Non conformance to the excavation support -Strictly enforced shoring and bracing requirements
system for major excavation works. to avoid accident.
-Issue instruction/directive to the contractor regarding
said defects.
-Imposed sanction if necessary.
ITEM 804- EMBANKMENT -Conduct visual inspection to determine actual
1. Presence of unsuitable materials. classification of soil, recommends removal and
disposal of unsuitable materials and replaced with
suitable materials in accordance with specifications.
2. Non-conformance with the required thickness of -Conduct inspection and require the contractor to
gravel filling. comply with requirements.
3. Non-conformance to the required density of -Conduct compaction test until the materials reached
compaction. the require density.
DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
III. TERMITE CONTROL AND WOOD PRESERVATION
ITEM 1000.3.1-SOIL POISONING
ITEM 1000.3.3-WOOD PRESERVATION -Verify and supervised the preparation and mixing of soil poisoning
and wood preservation solution to ensure compliance with
1. Non-conformance to the specifications.
required concentration
and rate of application
of the soil poisoning
solution and wood
protection.
IV. FOUNDATION WORKS
A. PRE-STRESSED, PRECAST CONCRETE PILES
1. Non-conformance to the required length, width, thickness and/or -Hold delivery and casting, conduct inspection and make the
diameter. necessary adjustment.

2. No-graduation marks -Do not allow driving of piles unless otherwise graduation is clearly
marks on the piles for accuracy of pile driving records and data.

3. Non-conformance to -Call the attention of the Project Engineer, direct rigger to have the
specified splicing splicing on a staggered basis for cluster piles.
requirements.
4. Presence of cracks -Removed and replaced.
B. CAST-IN-PLACE BORED PILES
1. Non-conformance to the required level of excavation. -Monitor and check elevation through actual measurement.
2. Improper disposal of spoils and debris. -Require the Project Engineer to immediately disposed/spread spoils
before it becomes an obstructions and delay the project.

3. Non-conformance to the required spacing of tie, stiffener bar and -Call the attention of the Project Engineer and properly adjust spacing
spacer. to meet requirements.
4. Improper curing of concrete samples. -Require the Materials Engineer to thoroughly check and supervise
the curing and handling of samples as this was critical in the
determination of the actual strength of concrete.
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES

V. DAMPPROOFING/MOISTURE CONTROL WORKS.


1. Non-conformance to the required thickness and -Require the contractor to make the necessary
number of layers of polyethylene materials. adjustment on the materials to conforms with
2. Non-conformance to the required thickness and specifications.
number/layer of waterproofing materials.

VI. CONCRETE WORKS


A. FORMWORKS
1. Formworks has loose knots, splits, cracks and other -Use only on minor works and not as support or braces
defects. to major structures.
-Removed and replaced if necessary.
2. Plywood forms not coated with mould oil. -Instruct Project Engineer not to install unless otherwise
coated with mould oil.
-If allowed to install, use only once.
3. Unaligned formworks/non-conformance to require -Immediately call the attention of the Project Engineer,
concrete cover. don’t allow pouring unless correction had been made
as this may affect the entire structures.
4. Formworks are inadequately supported and braced. -Instruct Project Engineer to make the necessary
installation of additional brace and support, never allow
pouring as this was dangerous.
5. Premature stripping and shore removal. -Immediately call the attention of the Project Engineer,
reinstall shoring and bracing as this was dangerous to
both the worker and to the structures.
6. No provision of clean-out/opening at the bottom of -Instruct Project Engineer to make the necessary
column and wall formworks. corrections.
7. Insufficient concrete/steel spacer for slabs and beams.

DPWH | Bureau of Construction


COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
B. STEEL REINFORCEMENTS
1. Use of corroded and/or dirty rebars -Conduct inspection, clean and apply rust remover if necessary.
-Removed and replaced if necessary.
-Elevate stockpile of rebars above-ground and in rack according to
sizes.
1. Rebars not securely tied in place. -Require the Project Engineer to make the necessary correction
2. Non-compliance with the required spacing of the stirrups. and adjustment to conform with the plans and specifications.
3. Unaligned rebar installation -Reject works if necessary.
4. No/improperly placed(irregular spacing) steel/dowel bars.
5. Improper splicing.
6. Non-conformance to the required concrete cover for rebars.

C.CONCRETE
1. Concrete structure failed to meet the strength requirements as per - Conduct investigation and in-place testing to determine actual
concrete sample specimens. strength.
- If structure failed to meet strength requirement through in-place
testing, refer to Structural Engineer/ Designer to assess extent of
remedial and corrective works.
2. Appearance of hairline cracks - Chipped off concrete to determine extent of cracks.
- Apply concrete epoxy.
3. Appearance of honeycomb or spalling - Chipped off concrete to removed honeycomb portion.
- Apply concrete epoxy prior to re-concreting.
4. Sagging or bulging of concrete. - Provide additional shoring and bracing if concreting is still on
going.
- For minor sagging or bulging removed affected portion and plaster.
- For major bulging, removed and replaced if necessary.
5. Non-conformance to finishing/ plastering requirement. - Require the Project Engineer to make the necessary
adjustments.
- Removed and replaced plastering works if necessary.
6. Improper curing -Call the attention of the Materials Engineer to make the
necessary adjustment to conform to standard requirements.
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
VII. MASONRY WORKS
1. Non-conformance to the required strength for both non-load - Non-load bearing, 500 psi and load bearing at 800 psi.
bearing and load bearing CHB. - Removed and replaced all CHB that does not conform to the
strength requirements.
- Conduct visual inspection and field testing.
2. Non-provision of lintel beam and stiffener column. - Chipped off laid CHB and install stiffener columns.
- Require the Project Engineer to make the necessary
adjustment.
- Reject/removed and replaced if necessary.
3. Non-conformance to the vertical and horizontal dowel. - Require the Project Engineer to make the necessary
adjustments.
- Reject/removed and replaced if necessary.
VIII. CARPENTRY AND JOINERY WORKS
1. Undersize lumber and plywood. - Require the Project Engineer to removed and replaced all
undersize materials.
2. Non-conformance with the required spacing for ceiling joist, - Require the Project Engineer to make the necessary
nailers, vertical studs and horizontal studs. adjustments.
3. Non-conformance to the required species of lumber. - Require the Project Engineer to make the necessary
adjustments.
- Reject/removed and replaced if necessary.
IX. FABRICATED MATERIALS AND HARDWARE
A. DOORS
1. Doors are not well fitted to the door frames. - Require the Project Engineer to make the necessary
2. Door accessories and other hardwares items were installed adjustment.
not according to schedule. - Conduct frequent inspection and verification to monitor
B. WINDOWS fabrication prior to installation.
1. Windows are not well fitted to the window frames. - Reject/removed and replaced if necessary.
2. Window accessories and other hardwares item were
installed not according to schedule.
3. Installed doors and windows were not in accordance with
specifications. DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/REMEDIAL MEASURES
X. ROOF FRAMING WORKS
A. STEEL FRAMING
1. Use of corroded structural elements. - Conduct visual inspection, verification and monitoring of
2. Undersize structural steel elements. fabrication prior to installation and erection of steel
3. Non-conformance to the required spacing of purlins trusses to ensure compliance to materials and
and trusses. specifications.
4. Insufficient welding at critical joint. - Require the Project Engineer to make the necessary
adjustment on the materials and workmanship.
- Reject/removed and replaced if necessary.
B. TIMBER TRUSSES
1. Use of low quality, untreated timber materials. - Conduct visual inspection, verification and monitoring of
2. Undersize timber materials. fabrication prior to installation of wooden trusses
3. Non-conformance to the required spacing of purlins including bolts, nuts and nails to ensure compliance to
and trusses. materials and specifications.
- Require Project engineer to make the necessary
adjustment on the materials and workmanship of the
structure.
- Reject/removed and replaced if necessary.
XI. ROOFING WORKS
1. Non-conformance to the required gauge and length. - Removed and replaced.
2. Non-conformance to the specified overlapping( end - Conduct inspection and monitoring to ensure
lap, side lap ). compliance with the plans and specifications.
3. Non-conformance to the approved method of fastening - Require the Project Engineer to make the necessary
and joining. adjustment on the workmanship.
1. Occurrence of leaks. - Conduct further leak test, provide silicon sealant.
2. Non-conformance to the approved material - Reject/removed and replaced if necessary.
requirements such as downspouts, gutter, flashing and
ridge roll. DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
XII. FINISHES
ITEM 1018- CERAMIC TILES
1. Occurrence of cracks on the materials. - Conduct inspection, verification and monitoring of the
2. Uneven laying of tiles. materials and methods of installation to ensure compliance
ITEM 1019- WOOD TILES to specifications.
1. Non-conformance to the design lay-out. - Require/instruct the Project Engineer to make the necessary
2. Uneven laying of tiles. adjustment to the materials and workmanship.
ITEM 1021- CEMENT FLOOR FINISH - Reject/removed and replaced if necessary.
1. Uneven surface. - Defer payment of accomplishment until contractor complied
2. Presence of temperature cracks. with requirements.
3. Weak mixture of fine and course aggregate.
ITEM 1026- PEBBLE WASHOUT FINISH
1. Uneven surface
2. Pebbles are not uniformly distributed.
3. Presence of temperature cracks.
XIII. PAINTING/VARNISHING
ITEM 1032- PAINTING/VARNISHING
1. Non-application of surface neutralizer. - Conduct inspection, verification and monitoring of painting
2. Non-conformance to the number of coat/application of materials to ensure conformance to specifications.
paint. - Require/instruct the Project Engineer to make the necessary
3. Occurrence of feeling-off of paint. adjustment to conform with the specifications.
4. Non-conformance to the approved brand and - Reject/removed and replaced if necessary.
specifications of paint. - Defer payment of accomplishment until the contractor
complied with the requirements.

XIV. WATERPROOFING WORKS


1. Non-conformance to the specified methods of application. - Require/instruct the Project Engineer to make the necessary
2. Non-conformance to the specified number of coat/layer adjustment to conform with specifications.
required. -Defer payment of accomplishment until the contractor
3. failure in the leak test. complied with the requirements.
DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/REMEDIAL MEASURES
XV. SANITARY WORKS
A. ITEM 1002- PLUMBING
1. Clogged pipes - Conduct visual inspection, verification and monitoring of the
2. Pipes, fixtures and other sanitary accessories were installation of pipes to ensure compliance to specifications.
installed not in accordance with the plans, e.g. slope, - Require Project Engineer to make the necessary adjustment
alignment. on sanitary works.
3. Failure to pass the leak test. - Require the contractor to rectify defective work and conduct
another test until such time that it passes the requirements.
- Reject/removed and replaced defective works if necessary.
- Defer payment of accomplishment until the contractor
complied with the requirements.

B. PIPES CULVERT AND STORM DRAIN


1. Appearance of cracks on the materials. - Reject/removed and replaced defective materials.
2. Inadequate collaring of reinforced concrete. - Conduct visual inspection, verification and monitoring of the
3. Inadequate bedding materials. installation of pipes, culvert and storm drain to ensure
4. Non-conformance to the required tolerance for elevation, compliance to specifications.
slope and alignment. - Require the contractor to rectify defective works.
- Require the Project Engineer to make the necessary
adjustment to conform with specifications.
- Reject work/removed and replaced if necessary.
C. MANHOLES, INLETS AND CATCH BASIN
1. Non-conformance to the required tolerances for elevations - Require contractor to rectify the defective works.
and dimensions. - Conduct visual inspection, verification and monitoring to
2. Covers and gratings are not well fitted with the opening of ensure compliance to specifications.
manholes and catch basin. - Require Project Engineer to make the necessary adjustment
to conform with specifications.
- Defer payment of accomplishment until the contractor
complied with the requirements.
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/ REMEDIAL MEASURES
XVI. ELECTRICAL WORKS
1. Pipes not properly installed and laid as per plan and - Reject/removed and replaced defective materials.
schedule. - Conduct visual inspections, verifications and monitoring
2. Pipes, hangers, boxes, cable trays not properly of the installation of electrical pipes, fixtures and
installed and painted. accessories to ensure compliance to specifications.
3. Sharp edges of pipes not removed. - Require contractor to rectify defective works and
4. Over crowded wires in pipes. conduct another test until such time that it passes the
5. Inadequate and under gauge of pull boxes. requirements.
6. Non-provisions of black-out and sleeves. - Require the Project Engineer to make the necessary
7. Pipes not properly bended. adjustment to conform with specifications.
8. Lighting fixtures, panelboard, circuit breakers, etc. not - Reject work/removed and replaced if necessary.
properly installed. - Defer payment of accomplishment until the contractor
9. Failure to meager test and load test. complied with the requirements.
XVII. MECHANICAL WORKS
A. AIR CONDITIONING SYSTEMS
1. Airconditioning units, transfer fans, pipes ducts, - Reject/removed and replaced defective materials.
condenser installed not according to plan. - Require the contractor to rectify defective works and
2. Defective materials and accessories. conduct test until such time that it passes the
3. Pipes and ducts not sufficiently braced. requirements.
4. Failed to meet performance test. - Conduct visual inspection, verifications and monitoring
5. Leaks on pipes. of all materials and installation of mechanical works to
B. GENERATOR SET ensure compliance to the required specifications.
1. Installation of auxiliary piping and control not according - Reject work if necessary.
to plan. - Defer payment of accomplishment until the contractor
2. Defective and damaged materials. complied with the requirements.
3. Pipes not sufficiently braced.
C. ELEVATORS
1. Improper handling of elevator component resulting to
damage on accessories. DPWH | Bureau of Construction
COMMON PROBLEMS
PROBLEMS/COMMON DEFECTS CORRECTIVE ACTION/
REMEDIAL MEASURES
XVIII. MISCELLANEOUS AND OTHER RELATED WORKS
ITEM 604 – FENCING AND GATES
1. Defective/damaged materials. - Reject/removed and replaced defective materials.
2. Non-conformance to the required tolerance for - Require the contractor to rectify defective works.
alignment, dimensions and elevations. - Conduct visual inspection, verifications, monitoring
and close supervision on the installation of fencing
and gates to ensure compliance to specifications.
- Require the Project Engineer to make the necessary
adjustment to conform with the specifications.
- Reject work if necessary.
- Defer payment of accomplishment until the contractor
complied with the specifications.

DPWH | Bureau of Construction


A MOBILIZATION
Is best described as the deployment of resources at the
project site. This also involves any work that is necessary
to provide access to the site including, but not limited to,
grading, clearing and grubbing.

MANPOWER MATERIALS

EQUIPMENT
DPWH | Bureau of Construction
A MOBILIZATION

Application in DPWH Projects

Mobilization and demobilization shall be treated as a


separate pay items of works as prescribed in D.O. 72,
Series of 2012. It shall be computed based on the
equipment requirements of the project stipulated in the
proposal and contract booklet. In no case shall mobilization
and demobilization exceed 1% of the Estimated Direct
Cost of the civil works items.

DPWH | Bureau of Construction


A MOBILIZATION
D.O. 44 Series of 2012 – STANDARD PROJECT
DURATION OF DPWH PROJECTS
(Duration of Mobilization and Demobilization)

ESTIMATED DIRECT COST OF THE PROJECT TIME DURATION


Up to P5 Million 10 c.d.
Above P5 Million up to P20 Million 15 c.d.
Above P20 Million up to P50 Million 20 c.d.
Above P50 Million up to P100 Million 25 c.d.
P100 Million up to P150 Million 30 c.d.

No standard duration was established for projects costing


more than P150 Million. Computation shall be based on the
PERT/CPM schedule, considering the use of optimum additional
resources.
DPWH | Bureau of Construction
A Safety and Health

Occupational Safety and Health is the Promotion and


maintenance of highest degree of physical, mental and
social well-being of workers in all occupation.

DPWH | Bureau of Construction


A Safety and Health
1 General Requirements

1. Construction Safety and Health Program (CSHP) refers


to a set of detailed rules to cover the processes and
practices that should be utilized in a specific construction
site in conformity with the OSH.

 Part of the first envelope (Technical Proposal) during the


bidding process

 Shall include but not limited to the following:


a. Composition of the Safety and Health personnel
b. Specific safety policies
c. Penalties and sanctions for violations
d. Manner or disposing waste
DPWH | Bureau of Construction
A Safety and Health
1 General Requirements
2. Construction Safety and Health Organization
2.A Safety Engineer/ Officer

DPWH | Bureau of Construction


A Safety and Health
1 General Requirements

2.B Health Personnel


2.C Personal Protective Equipment (PPE) & Devices
2.D Signage and Barricades
2.E Facilities
2.F Safety and Health Training

DPWH | Bureau of Construction


B EARTHWORKS

-Involves clearing and grubbing,


excavation, backfilling and
gravel bedding of all structural
foundation footings for
columns, walls, stairs and other EARTHFILL
structural members.
FINISH FLR. LINE
-Also involves the embankment F.G.L

of suitable materials to meet N.G.L


EXCAVATION
the required elevation
established on the line and BACKFILL
grade of the building structure.

GRAVEL BEDDING

DPWH | Bureau of Construction


B EARTHWORKS

Application in DPWH Projects

 ITEM 803 – STRUCTURE EXCAVATION


As applied to public works structures, this item shall
consist of the necessary excavation for foundations of
buildings in reasonably close conformity with the
plans or as established by the engineer.

 ITEM 804 – EMBANKMENT


This item shall consist of the construction of
embankment in accordance with the specification and
in conformity with the lines, grades, and dimensions
shown on the plans established by the engineer.

DPWH | Bureau of Construction


B EARTHWORKS

1 General Requirements
1.1 Earth- Moving Equipment

2 Methodology
2.1 Construction Survey
2.2 Finding Grade Level
2.3 Setting Batterboards

DPWH | Bureau of Construction


B EARTHWORKS
Construction procedure and lay-out
1. Locate the boundaries of the construction site.
2. Clear the site of any obstructions.
3. Determine the building set back from the road line.

NYLON CHORD

BATTER BOARD

PLUMB BOB
STAKES

STAKING AND BATTER BOARD LAYOUT

DPWH | Bureau of Construction


B EARTHWORKS

4. Fix the intersections ESTABLISHING THE SQUARE

or corners at 90 1/2" x 4’ x 8’
PLYWOOD BOARD
degrees.

2” x 3”

BATTER BOARD
5. Verify the measure- 2” x 2”
STAKES
ment in the plan.
a) Center to Center,
b) Center to Outer Side a c
c) Outer to Outer side
d) Inside to inside. b d

DPWH | Bureau of Construction


B EARTHWORKS

Method on Layout and Staking with the Aid of Instrument

DPWH | Bureau of Construction


B EARTHWORKS

Method on Layout and Staking with the Aid of Instrument

Staking out is done before establishing the grade level. It begins with
locating the lot lines. Corners of the lot should normally be marked with
stakes. Then, proceed:

1. Center and level the instrument (builder’s level or transit) over the lot
corner stake. Measure the setback called for by local codes. Sight across to
the opposite corner stake.

2. Drive a 2 × 2 stake at the setback in line with the lot stakes. Use the
transit or builder’s level to check alignment. The vertical and horizontal
crosshairs should center on the top of the stake. Drive a nail on the top-
center of the stake.

3. Place another stake at the correct setback for one side of the property
line. You are now ready to stake out the building lines.

DPWH | Bureau of Construction


B EARTHWORKS
Method on Layout and Staking with the Aid of Instrument

Staking Procedure
Staking out building lines requires two persons. When a builder’s level is
used, the second person will use a rod that must be plumbed along the line of sight.
Since a transit can pivot up and down, the second person uses a stake to locate
corners along the building line.

1. Attach a plumb bob to the center screw or hook on the underside of the
instrument. Some instruments have an optical plumb for zeroing in over a
point. Shift the tripod until the point of the plumb bob is directly over
the point marking the corner of the building lines. This is at point A on line
AB, as shown in the figure.
2. Level the instrument before proceeding further. Recheck for plumb.
3. From point A (or station A), turn the telescope so the vertical crosshair is
directly in line with the edge of a stake or rod held at point B. When using a
transit, sight the telescope on the stake.
4. Use a measuring tape along line AB to locate distance to the corner. Drive a
corner stake at this point.

DPWH | Bureau of Construction


B EARTHWORKS

3 Quality Control
*For Clearing and Grubbing, Removal of Structures, Structure
Excavation:

- If excavated materials are wasted, the volume involved shall be


reported so that Quality Control requirements may be adjusted
accordingly.
*Submit Project Engineer Certificate of Waste

- If excavated materials are incorporated into the work:


*For every 1,500 cu.m. or fraction thereof:
1-G, Grading Test
1-P, Plasticity Test (LL, PL, PI)
1-C, Laboratory Compaction Test
*For every 150 mm layer in uncompacted depth:
1-D, Field Density Test

DPWH | Bureau of Construction


B EARTHWORKS

3 Quality Control
*For Embankment:

*For every 1,500 cu.m. or fraction thereof:


1-G, Grading Test
1-P, Plasticity Test (LL, PL, PI)
1-C, Laboratory Compaction Test
*For every 200 mm layer in uncompacted depth:
1-D, Field Density

DPWH | Bureau of Construction


C TERMITE CONTROL & WOOD PRESERVATION

-Are methods to prolong


and protect wood products
and structures from termite
infestation
UPPER LOCATION:
Soil poisoning WOOD PRESERVATION
A process wherein the soil is
treated with chemical solutions to
control and prevent the entry of
termite into the structure

Wood preservation
a process wherein the wood is also
treated with chemical solution and
are applied directly either external
or internal on wood surfaces. LOWER LOCATION :
SOIL POISONING

DPWH | Bureau of Construction


C TERMITE CONTROL & WOOD PRESERVATION

1 General Requirements
1.1 All labor, materials and equipment to be used in
the completion of the job shall be furnished by the
pest control provider.

1.2 Product demo should be presented which includes


product data and methods of application

1.3 All work shall be done in the order of progress


required by the Owner’s construction program.

DPWH | Bureau of Construction


C TERMITE CONTROL & WOOD PRESERVATION

2 Treatment Procedures
2.1 Pre-Construction Treatment
2.1a Soil Treatment

Bottom surface and the sides


of the excavation made from
masonry foundations and
basements shall be treated
with termicide concentrate at
a rate of 5 L/ m2 surface area
or as specified by the product
data

Treatment for Foundation Pits

DPWH | Bureau of Construction


C TERMITE CONTROL & WOOD PRESERVATION

2 Treatment Procedures

Treatments for Masonry Foundation,


Reinforced Concrete Foundation
DPWH | Bureau of Construction
C TERMITE CONTROL & WOOD PRESERVATION

2 Treatment Procedures
2.2 Post- Construction Treatment

2.2. a Soil Treatment

 Cordoning Method
- When there is no visible evidence
of termite infestation

Drenching Method
- When the soil shows termite
infestation

Drenching Method along the


perimeter of the building
DPWH | Bureau of Construction
C TERMITE CONTROL & WOOD PRESERVATION

2 Treatment Procedures
2.2 Post- Construction Treatment

2.2. b Drilling Service

- Is done in order to treat the soil


under cemented floor slabs.

Termicide solution is injected through


soil injector using the power machine
deep under the surface to penetrate
the hidden areas susceptible to
subterranean termites

DPWH | Bureau of Construction


C TERMITE CONTROL & WOOD PRESERVATION

2 Treatment Procedures 2.3a Pressure Treatment Method

Pressure treating is a process that


forces a chemical preservative deep
into the wood. The wood product is
placed into a humongous
cylindrical holding tank, and the tank is
depressurized to remove all air. The
tank is then filled with the preservative
under high pressure, forcing it deeply
into the wood. The tank is then drained
and the remaining preservative reused.
The wood is removed from the tank
and prepared for shipment to your
local lumberyard.
Pressure Treatment Method 2.3b Non-pressure Treatment Method
- Hot-Cold Bath, Vacuum Process,
Double Diffusion, Cold Soaking,
Superficial Methods
DPWH | Bureau of Construction
C TERMITE CONTROL & WOOD PRESERVATION

3 Quality Control
Minimum Test Requirements:

1- IR (Inspection Report for materials used)

DPWH | Bureau of Construction


D FOUNDATION WORKS

(2) main structures


 Superstructure- the structural
elements above the ground.
 Substructure-usually called the
“Foundation” which is the chief
means of supporting a building.
They carry both the dead load
and the live loads and their
primary purpose is to transmit
the collective building loads to
the underlying soil or rocks.

DPWH | Bureau of Construction


D FOUNDATION WORKS

1 General Requirements
Considerations:
1. Check the foundation base or soil condition if it
complies with the boring data.
2. Check the depth if it complies with plans.
3. Check alignment and distances.
4. No footing shall rest on fill.
5. All footings and tie beams shall rest on a well
compacted gravel bed
6. Back fill shall be place in layers at 200mm thk. and
shall be compacted to 95% Maximum Dry Density.

DPWH | Bureau of Construction


D FOUNDATION WORKS

2 Types of Building Foundation


2.2 SHALLOW FOUNDATION

Strip foundation

Spread footing Mat


Foundation

DPWH | Bureau of Construction


D FOUNDATION WORKS

2 Types of Building Foundation


2.2 DEEP FOUNDATION

Micropiles Bored Piles Pre-cast Piles

DPWH | Bureau of Construction


D FOUNDATION WORKS

2 Types of Building Foundation


2.3 JET GROUTING
Ground stabilization procedure
that works on plastic granular
materials using the principle of
Ultra High Pressure Injection of
Cement Grout

DPWH | Bureau of Construction


D FOUNDATION WORKS

3 Quality Control
3.1 Pile integrity test

Crosshole Sonic Logging (CSL) Low Strain High Strain


Dynamic Testing Dynamic Testing

3.2 Minimum Testing Requirement


(Same with Concrete Works)

DPWH | Bureau of Construction


E DAMP PROOFING/ MOISTURE CONTROL

- is a process designed to contain and eliminate the


penetration of moisture discharged by the
earth/soils on the building structures.
- Damp proofing membrane/vapor barrier is a
vertical, horizontal or sloping water proof skin
such as asphalt 20mm thick, copper sheets,
polyethylene film or any other materials of various
designs and manufacturing specifications.
- It is placed directly on the slab on fill (SOF) for low
rise building or on the basement floor for high
rise building to form a protective barrier between
the soil and the concrete structure which, in turn,
ensure protection to its architectural finishes.

DPWH | Bureau of Construction


E DAMP PROOFING/ MOISTURE CONTROL

DPWH | Bureau of Construction


F CONCRETE WORKS

1 General Requirements
1.1 Formworks and Scaffoldings
1.2 Steel Reinforcement
1.3 Cement
1.4 Aggregates
1.5 Water
1.6 Admixture
1.7 Storage of Materials

DPWH | Bureau of Construction


F CONCRETE WORKS

1 Methods
FORMWORKS AND SCAFFOLDINGS
1. Formworks Construction

Concrete forms shall be mortar-tight, true to the dimensions,


lines and grades of the structure. They should have the sufficient
strength, rigidity, shape and surface smoothness.

Form fasteners consisting of form bolts, clamps or other devices


shall be used as necessary to prevent wrecking the forms during
concrete placement. The use of ties consisting of twisted wire
loops to hold forms in position will not be permitted.

DPWH | Bureau of Construction


F CONCRETE WORKS

FORMWORKS AND SCAFFOLDINGS


2. Removal of Forms
Forms shall not be removed without the consent of the Engineer.
Minimum %
Minimum Time
Design Strength
Centering under girders,
14 days 80%
beams frames or arches
Floor slabs 14 days 70%
Walls 1 day 70%
Columns 2 days 70%
Sides of beams and all other
1 day 70%
vertical surfaces

Forms and falsework shall not be released from under the


concrete without first determining if the concrete has gained adequate
strength without regard to the time element. In the absence of strength
determination, the forms and falsework are to remain in place until
removal is permitted by the Engineer.
DPWH | Bureau of Construction
F CONCRETE WORKS

B. STEEL REINFORCEMENTS
Steel is considered as an excellent partner of concrete in
resisting tension and compression. The design of reinforced
concrete assumes that concrete and steel acts together in
carrying load in the state of simultaneous deformation.

1. ) Bar splicing
a. Tension Bar
b. Compression Bar

2. ) Bar Spacing
- shall not be less than the normal diameter of the bars or
40 mm for column, or as specified in the structural design notes.

DPWH | Bureau of Construction


FF CONCRETE WORKS
a. Splice location on suspended slab

b. Splice location for continuous beams

DPWH | Bureau of Construction


E CONCRETE WORKS
a. Splice location for cantilever beams

DPWH | Bureau of Construction


F CONCRETE WORKS
a. Splice location for columns

DPWH | Bureau of Construction


F CONCRETE WORKS

3. Concrete Protection For Reinforcement


Structure Minimum cover (mm)
A. Footing, Footing Tie Beams 75 mm
B. Beams and Columns (to stirrups and ties) 40mm
C. Walls, side of FTB (cast against forms) 40mm
D. Suspended Slab 20mm

DPWH | Bureau of Construction


F CONCRETE WORKS

4. Details of Reinforcement

a. ) Standard Hooks
• 180 deg. Bend plus 4 bar diameter extension, but not less
than 65 mm at free end of bar.
• 90 deg. Bend plus 12 bar diameter extension at free end
of bar.
•For stirrup and tie hooks
A. 16mm bar and smaller, 90 deg. Bend plus 6 bar
diameter at free of bar or
B. 20mm and 25mm bar, 90 deg. Bend plus 12 bar
diameter extension at free end of bar or
C. 25mm bar and smaller, 135 deg. Bend plus 6 bar
diameter at free end of bar, or
D. As specified in the structural design notes

DPWH | Bureau of Construction


F CONCRETE WORKS

DPWH | Bureau of Construction


F CONCRETE WORKS

5. Minimum Bend Diameter


MINIMUM DIAMETER OF BEND
Bar size Minimum Diameter
10mm to 25mm 5 bar diameter
28mm to 32mm 8 bar diameter
36mm 10 bar diameter

6. Bending

1. All reinforcements shall be bent cold, unless otherwise


permitted by the Engineer.

2. Reinforcement partially embedded in concrete shall not be field-


bent except as shown in the design drawings or as permitted by
the engineer.

DPWH | Bureau of Construction


F CONCRETE WORKS
C. CONCRETE
1. Mixing and Delivery
Concrete may be mixed at the site of construction or at the
batching plant.

Mixer Capacity Mixing Time


1.5m3 not less than 60 seconds
Greater than 1.5 m3 not less than 90 seconds

Delivery of concrete shall be timed and regulated to sustain


continuous placing unless there is delay in the actual placing
operations. The intervals between deliveries of batches shall
not be so long allowing the concrete in place to harden
partially. In no case shall such gap exceed 30 minutes.

 Retempering of concrete will not be permitted.


DPWH | Bureau of Construction
F CONCRETE WORKS

2. Storage of Materials

Cement and aggregates shall be stored in such a manner as to


prevent their deterioration or the intrusion of foreign matter.
Cement shall be stored, immediately upon arrival on the site of the
work, in substantial, waterproof bodegas. The floor must be
sufficiently elevated to deter dampness. Aggregates shall be stored
separately from other foreign materials.

DPWH | Bureau of Construction


F CONCRETE WORKS

Aggregate Tests
Samples of the fine and coarse aggregates to be used shall be
selected by the engineer for test at least 30 days before the start of
the concreting operations.
No aggregates shall be used unless certified to have satisfactory
passed all tests, and a written authority has been served for their use.

Admixtures
Admixture Shall Conform to
Air-entraining admixtures ASTM C 260
Water-reducing admixture
Retarding
ASTM C 494.
Water-reducing/retarding
Water-reducing/accelerating

DPWH | Bureau of Construction


F CONCRETE WORKS
3. Conveying/ Transporting

Buckets or Hoppers

Manual or Motor Propelled


Buggies

DPWH | Bureau of Construction


F CONCRETE WORKS
3. Conveying/ Transporting
Chutes

Pipes

DPWH | Bureau of Construction


F CONCRETE WORKS
3. Conveying/ Transporting

Conveyor Belt

Concrete Pump

DPWH | Bureau of Construction


F CONCRETE WORKS
4. Depositing of Concrete
a. Column

Drop
Chute

Maximum
Drop
Height
1.50 meter or
less

PROPER IMPROPER
DPWH | Bureau of Construction
F CONCRETE WORKS

DPWH | Bureau of Construction


F CONCRETE WORKS
b. Slab

DPWH | Bureau of Construction


F CONCRETE WORKS
c. Wall
F CONCRETE WORKS
5. Compaction of Concrete

Concrete during and immediately after placing shall be


thoroughly compacted. Compaction shall be done by
mechanical vibration. The intensity of vibration shall be such
as to visibly affect a mass of concrete with a 3 cm slump over
a radius of at least 50 cm

DPWH | Bureau of Construction


F CONCRETE WORKS

6. Construction Joints
Construction joints shall be made only as shown in the Plans or as
called for in the pouring schedule, unless otherwise approved by
the Engineer. It shall be thoroughly cleaned of foreign matter and
laitance.

DPWH | Bureau of Construction


F CONCRETE WORKS

DPWH | Bureau of Construction


CONCRETE WORKS
F A A1
L

L/4 L/2 L/4


3 -16mmØ TOP BARS
2 -16mmØ ADD'L. BARS @ L/4

3 -16mmØ BOTTOM BARS 2 -16mmØ ADD'L. BARS @ L/2

TYPICAL BEAM DETAIL


SCALE 1 : 10m

9-12mmØ MATTING BARS


EQUALLY SPACED BOTHWAYS

4-16mmØ VERTICAL BARS W/


9mmØ TIES, SPACED 5 @
50mm, 5 @ 100mm, REST @
200mm ON CENTERS

4-12mmØ
9mmØ STIRRUPS
350mm THK. CONCRETE
FOOTING

N.G.L.

4-12mmØ MAIN BARS W/


9mmØ STIRRUPS
NATURAL GRADE LINE

4-16mmØ VERTICAL BARS W/


9mmØ TIES, SPACED 5 @
50mm, 5 @ 100mm, REST @
200mm ON CENTERS
9-12mmØ MATTING BARS
EQUALLY SPACED BOTHWAYS

SECTION
WF (4" CHB) PLAN
F CONCRETE WORKS

1. Floor Framing Plan


2. Typical Section of Concrete Slab
F CONCRETE WORKS

7. Curing of Concrete

All newly placed concrete shall be cured in accordance


with this Specification unless otherwise directed by the
Engineer. The types of curing methods are the following:

1. Water Method
2. Curing Compound
3. Waterproof Membrane Method
4. Forms-in-Place Method

DPWH | Bureau of Construction


F CONCRETE WORKS

3 Quality Control
Minimum Test Requirements:
a) CONCRETE:
1. Design Mix
1.a Batching Plant – to be prepared by the Supplier
1.b Jobsite – to be prepared by the contractor
2. Conduct Trial Mix (reference only)
3. Submit Samples for:
3.a Portland Cement
1- Q (Quality Test) for every 2,000 bags or fraction thereof
3.b Fine Aggregates:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.c Coarse Aggregate:
1- Q (Quality Test) for every 1,500 cu.m. or fraction thereof
1- G (Grading Test) for every 75 cu.m. or fraction thereof
3.d Water:
1- Certificate from Project Engineer
DPWH | Bureau of Construction
F CONCRETE WORKS

Minimum Test Requirements:

3.e As work progresses, at least one (1) set of sample consisting of


three (3) concrete cylinder test specimens, shall be taken from
each class of concrete placed each day. Each set represents not
more than 75 cu. m of concrete. The age strength test shall be
28 days, or where specified.

DPWH | Bureau of Construction


G MASONRY WORKS
- is a form of construction work equipped with stone, bricks,
concrete, hollow clay tile, concrete block or tile, or other similar
building units or material or a combination of these materials laid
up unit and set in mortar.
Concrete Hollow Blocks
Concrete hollow blocks are classified as load bearing and
non- load bearing blocks.
1 Requirements
A. Strength Requirements
a) Non load bearing concrete masonry units – ASTM C 129
- 100 mm thick
Individual – 3.45 Mpa ( 500 Psi )
Average - 4.14 Mpa ( 600 Psi )
b) Load bearing Concrete masonry units – ASTM C 90
- 150 mm to 200 mm thick
Individual - 5.5 Mpa ( 800 psi )
Average - 6.9 Mpa ( 1000 Psi )
DPWH | Bureau of Construction
G MASONRY WORKS

2 Methods
Block laying after the
concreting of tied
column

Concreting of column
after block laying of
walls

DPWH | Bureau of Construction


G MASONRY WORKS

DPWH | Bureau of Construction


G MASONRY WORKS

DPWH | Bureau of Construction


G MASONRY WORKS

DPWH | Bureau of Construction


G MASONRY WORKS

3 Quality Control
Minimum Test Requirements:

Concrete Hollow Blocks (CHB )


1- Q, Quality Test for every 10,000 units or fraction thereof

a) Non load bearing concrete masonry units – ASTM C 129


Individual – 3.45 Mpa ( 500 Psi )
Average - 4.14 Mpa ( 600 Psi )

b) Load bearing concrete masonry units – ASTM C 90


Individual - 5.5 Mpa ( 800 psi )
Average - 6.9 Mpa ( 1000 Psi )

For Portland Cement, Fine Aggregates, Water and Steel Bars:


-same requirements as in Concrete Works

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

1 Requirements

Quality of Materials
All materials to be incorporated in the carpentry and joinery works
shall be of the quality specified in the approved plans and
specification. Before incorporation in the work, all materials shall
have been inspected / accepted by the Engineer or his authorized
representative.

Storage and Protection of Materials


All materials under this item shall be protected from dampness or
bad weather conditions during and after delivery at the site.
Materials shall be delivered in advance of actual use and in
adequate quantity to preclude delay in the work. It shall be piled in
orderly stack at least 150 mm above ground and at a sheltered place
where it will be of least obstruction to the work.

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

Shop Drawings
Shop drawings complete with essential dimensions and details of
construction, as may be required by the Engineer in connection with
the carpentry and joinery work, shall be submitted for approval
before proceeding with the work.

Prior to enclosure of drywall partitions and ceiling, the following


controls should be properly complied:

a. Drywall Partition
1. Vertical and horizontal alignment
2. Material specification
3. Complete installation of Electro-mechanical rough-ins
4. Rigidly connected to the flooring, walls and at the bottom of the
ceiling frames.
5. Appropriateness of tools to be used.

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

Ceiling
1. Dimension and alignment of nailers/metal frames
2. Material specification
3. Complete installation of sanitary/plumbing and electro-
mechanical rough-ins
4. Properly anchored to the carrying metal channel/wood runner.
5. Complete installation of roof framing and roofing
6. Appropriateness of tools to be used.

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

Metal
Steel Stud Furring
Furring Channel
DPWH | Bureau of Construction
H CARPENTRY & JOINERY WORKS

DPWH | Bureau of Construction


H CARPENTRY & JOINERY WORKS

1 Quality Control

Minimum Test Requirements:

1-IR (Inspection Report for each material used)

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

TYPES OF WINDOWS

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

1. WINDOWS
A. Steel Casement Window
B. Awning Window
C. Jalousie Window
D. Sliding Aluminum Framed Window
E. Fixed Aluminum Framed Window
F. Wooden Windows
G. Others

Installation
a. Steel windows
- shall be plumb set and true in the openings. The joints
between the window frame and masonry shall be carefully
caulked. Windows shall be designed for glazing from the
outside with spring wire glazing clips and glazing putty.

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES
Installation
b. Glass Jalousie Windows

1. Jalousie metal frames shall be temporarily fixed at the


bottom and top ends using wood screw.

2. Glass slats are lugged into the slat clips starting from
way down and up until the whole unit is entirely glazed.

3. Actual test the unit and make adjustments where


required taking into consideration that all units are
properly aligned and satisfactory operational.

4. Close the slat clips in a manner that the glasses are


securely fixed. Permanently fix all the units with wood
screws.

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

2. DOORS
A. Hollow Core Flush Door
B. Panel Door
C. PVC Door
D. Glass Door
E. Steel Door
F. Others
WOODEN DOORS
Material Requirements
1. Lumber
Lumber doors, windows jambs, and panels when required, shall be
kiln-dried with moisture content of not less than 14% and shall be of
the specie indicated in the Plans and/or specifications.
2. Plywood
Plywood for hollow core flush doors shall be 3-ply, rotary cut, 6mm thick
ordinary plywood or as indicated in the plans.
3. Adhesive
Adhesives shall be water resistant resins and shall be non-staining.
DPWH | Bureau of Construction
I FABRICATED MATERIALS & HARDWARES

Construction Requirements

Fabrication
Wooden doors, including frames, shall be fabricated in accordance
with the designs and sizes shown in the Plans. The fabricated products
shall be finished square, smoothly sanded and free from damage.

Installation

1. Frames shall be plumb set and squared in the concreting/masonry


work, frameworking of walls or building partitions.
2. Frames shall be plumb set and squared in the concreting/masonry
work, frameworking of walls or building partitions.
3. Locks of doors shall be fitted at the lock block, 1000 mm above the
finished floor level. Locks shall be installed in conformity with the
templates and instructions supplied with the locksets

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

DPWH | Bureau of Construction


I FABRICATED MATERIALS & HARDWARES

Minimum Test Requirements:

1-IR (Inspection Report for each material used)

DPWH | Bureau of Construction


J ROOF FRAMING WORKS

1 Procedure
1. Steel frames are attached together by means of a rivet, a bolt or by
welding. Before assembly, a sample of all the steel members shall be
tested if they conform to the desired strength specified in the plans and
specifications.

2. Fabrication of steel frames can be done in the field during erection of


the building or at the shop.

3. When punching and drilling steel make sure that the hole drilled or
punched is 1.5 to 3 mm greater than the diameter of the bolt to make it
easy in inserting and bolts through it.

4. Verify if the welding work needs a partial or complete penetration. The


metal surface is set in accordance with the shape needed in welding. Be
sure that the metals are in their proper position before welding.
DPWH | Bureau of Construction
J ROOF FRAMING WORKS

1 Procedure
5. When the work is completed, inspect if it is welded in accordance
with the penetration length and thickness needed in the
construction.

6. Purlins are then placed equidistantly as specified in the plans.


Purlins should have an angle strap and a sag rod to prevent lateral
buckling.

7. If all works are done in accordance with plans and specifications,


paint all metals with metallic paint for rust protection.

DPWH | Bureau of Construction


J ROOF FRAMING WORKS

DPWH | Bureau of Construction


J ROOF FRAMING WORKS

LENGTH OF WELD

DPWH | Bureau of Construction


J ROOF FRAMING WORKS

1 Quality Control
Minimum Test Requirements:

1- Q (Quality Test for each type/size of Structural Steel)


1- IR (Inspection Report for other materials
not required for testing)

DPWH | Bureau of Construction


K ROOFING WORKS

1 Requirements

Material Requirements

1. Corrugated and Plain Galvanized Iron Sheets

2. Roofing nails, Washers and Burrs

3. Fabricated Metal Roofing Accessories

DPWH | Bureau of Construction


K ROOFING WORKS

Construction Requirements
A. Preparatory Works
Preparatory to the installation of the corrugated G.I. roofings,
purlins should have been placed and spaced properly to fit the
length of the roofing sheets. The top of the purlins should be
at the same plane.

B. Installation of Roofing Sheets


Installation of Roofing sheets with end laps shall start at
the lower part of the roof. The sheets should have side laps
of two-and-a-half (2-1/2) corrugations. Succeeding upper rows
of corrugated G.I. sheets shall be installed in the same manner
until the entire roof area is covered. Screw holes shall be
drilled using a 5 mm (13/64”) diameter bit.
Sheets should be handled carefully to prevent damage.

DPWH | Bureau of Construction


K ROOFING WORKS

DPWH | Bureau of Construction


K ROOFING WORKS

C. Installation of Roofing Accessories

a) Ridge and Hip Rolls


Ridge and hip rolls shall lap at least 250mm over the roofing
sheets and, together, shall be riveted at every second
corrugation.

b) Valleys
Valleys shall lap at least 450 mm each way under the roofing
sheets and shall be secured to the framework with
galvanized nails. The nails are placed below the roofing
sheets. Rivets along the side of the valley shall be fastened
at every second corrugation.

DPWH | Bureau of Construction


K ROOFING WORKS

c) Flashing
Flashing, of gauge 26 plain G.I. sheets, unless otherwise specified,
shall be installed along intersections of roofs and concrete or
masonry walls. Flashing running parallel to sheet corrugations must
have its edge turned down. Flashing across sheet corrugations or at
an angle thereto, shall lap at least 250 mm and the edge of flashing
turned down at each corrugation.
d) Gutters
Gutters, of gauge 24 plain G.I. sheets, shall be fabricated to the
shape and dimensions indicated in the Plans. Gutter joints shall be
flat seam folded in the direction of flow and soldered evenly. Gutter
shall be attached to fascia board with appropriate nails or screws
spaced of not more than 900 mm on centers. As additional support,
gutters shall have plain G.I. strap hangers 25 mm wide fastened to the
roof nailers and shall be spaced at not more than 900 mm on centers.
The gutter shall be installed with a pitch of 1 in 100 sloped toward
the downspout.

DPWH | Bureau of Construction


K ROOFING WORKS

2 Methods
a. Lay-outing
In laying out the placement for the J-
Bolts, make sure that it will be aligned
near enough to the lip of the purlin
avoiding it to be drilled when making
holes. A guide chord may be stretched
out from end to end of the purlin to
establish alignment.

b. Drilling

After lay outing, drilling points should be located at the crown


every two other corrugations of the roofing material (G.I. Sheet)
DPWH | Bureau of Construction
K ROOFING WORKS

c. Installation
In the installation of J-Bolt, two (2)
manpower is required to work
concurrently. One will insert the bolt
through the hole from the indoor
and the other will fasten the nut out
door.

Before fastening the nut, fit a


neoprene gasket then a washer
bigger than the gasket.

In fastening the nut, a nut driver


must be used with precautious
control on the gun to avoid warping
of the G.I. Sheet.

DPWH | Bureau of Construction


k ROOF FRAMING WORKS

3 Quality Control
Minimum Test Requirements:

1- Q (Quality Test for each type of Roofing Sheets)


1- IR (Inspection Report for other materials not
required for testing)

DPWH | Bureau of Construction


L FINISHES

1 Requirements
CERAMIC TILES

Material Requirements
a. Glazed Tiles and Trims
b. Unglazed Tiles
c. Trims
d. Accessories
e. Cement
f. Sand
g. Lime

DPWH | Bureau of Construction


L FINISHES

Construction Requirements

A. Surface Preparation

The surface where the tile is laid must be level, true to


elevation, dry, and free from dirt, oil and other
sediments. Allow at least seven days curing of the
scratch coat and setting bed.

On masonry or concrete surface, first apply a thin coat


with pressure, then bring it out sufficiently to a
thickness not less than 10mm at any point to
compensate for the major irregularities of the surface.

Evenly rate the scratch coat to provide good mechanical


key before the mortar mix has fully hardened.

DPWH | Bureau of Construction


L FINISHES
Construction Requirements

B. Installation Procedure
• Before the tile is applied the floor surface shall be tested for
levelness or uniformity of slope by flooding it with water.
• Ceramic tiles shall be soaked in clean water prior to
installation for a minimum duration of one hour.
• Determine and mark the layout of ceramic tiles, joint
location and position of trims and fixtures so as to minimize
the incidence of a tile being cut less than one half of its size.
• All lines shall be kept straight and true to profiles, plumbed
and internal corners rounded using the appropriate trims.
• Pitch the floor to drain as shown in the Plans or as directed
by the Engineer
C. Grouting and Pointing - Tiles shall have been laid in place for
at least 24 hours before grouting of the joints is started
D. Cleaning
E. Protection from Construction Dirt
DPWH | Bureau of Construction
L Ceramic Wall Tiles

1. Layout 2. Apply a bond coat mix (Tile Adhesive)

3. Lay tiles true to profile 4. Keep straight w/ tile spacer


DPWH | Bureau of Construction
L Vitrified Unglazed Floor Tiles

DPWH | Bureau of Construction


L Tiles

C. Grouting and Pointing


Tiles shall have been laid in place for at
least 24 hours before grouting of the
joints is started

D. Cleaning

E. Protection from Construction Dirt

Grouting and Pointing

DPWH | Bureau of Construction


L FINISHES

CEMENT FLOOR FINISH


This Item shall consist of furnishing all materials, labor, tools
and equipment in undertaking cement floor finishing where
shown in the Plans and in accordance with this Specification.

Material Requirements Construction Requirements


a. Cement
b. Fine Aggregates
a. Mixture
c. Coloring Material
b. Preparation of Concrete Surface
d. Metallic Floor Hardener (Premix)
c. Application
e. Non-Metallic Floor Hardener
d. Protection of Finished Surface
e. Workmanship

DPWH | Bureau of Construction


L Cement Floor Finish

1 2

3
DPWH | Bureau of Construction
L FINISHES

PEBBLE WASHOUT
This Item shall consist of furnishing all materials, labor,
tools and equipment required in undertaking the proper
application of pebble washout finish as shown in the
Plans and in accordance with Specifications.

Material Requirements Construction Requirements


a. Pebble
b. Cement
a. Surface Preparation
c. Colored Cement
b. Application
c. Workmanship
d. Curing and Protection

DPWH | Bureau of Construction


L Pebble Washout

1 2 3

4 5
DPWH | Bureau of Construction
L FINISHES

CEMENT PLASTER FINISH


This Item shall consist of furnishing all cement plaster
materials, labor, tools and equipment required in
undertaking cement plaster finish as shown in the Plans
and in accordance with Specifications.

Material Requirements Construction Requirements


a. Cement
b. Hydrated Lime a. Surface Preparation
c. Fine Aggregates b. Application
c. Workmanship
d. Curing and Protection

DPWH | Bureau of Construction


L Cement Plaster Finish

1. Roughen surface to improve


adhesion of cement plaster

2. Clean surface to receive


cement plaster

3. Apply mortar mix with


sufficient pressure

4. Trowel finish

DPWH | Bureau of Construction


L FINISHES

3 Quality Control
Minimum Test Requirements:

a) Floor & Wall Cement Plaster Finish


-same tests for Concrete Works on Cement, Fine Agg.
and Water
b) Tile Finish
- IR (Inspection Report for each type of material used)

DPWH | Bureau of Construction


M PAINTING/ VARNISHING WORKS

1 Requirements
Material Requirements Construction Requirements
a. Paint Materials a. Surface Preparation
b. Tinting Colors b. Application
c. Concrete Neutralizer c. Mixing and Thinning
d. Silicon Water Repellant d. Storage
e. Patching Compound e. Cleaning
f. Varnish f. Workmanship
g. Lacquer g. Method of Measurement
h. Shellac h. Basis of Payment
i. Sanding Sealer
j. Glazing Putty
k. Natural Wood Paste Filler

DPWH | Bureau of Construction


M PAINTING/ VARNISHING WORKS

Surface Preparation

Surface preparation
for Boards Surface preparation
for Concrete &
Masonry Surface

DPWH | Bureau of Construction


M PAINTING/ VARNISHING WORKS
Safety Concerns

Appropriate platform, scaffolds


and supports while working on
elevated areas
Quality Control
Minimum Test Requirements:
1- Q (Quality Test) for each type for every 100 cans
(4-Liters or 20-Liters can) or fraction thereof

DPWH | Bureau of Construction


N WATERPROOFING

A. Types of Waterproofing
 Cement-base Waterproofing

Cement-base waterproofing powder mix shall be cement-


base, aggregate type, heavy duty, water-proof coating for
reinforced concrete surface and masonry exposed to water.
The aggregates are graded and sized so as to mesh perfectly
and are selected for purity, hardness, strength and are non-
metallic. When mixed with other ingredients, they are free
flowing, water-proof coatings that possess strength,
durability and density.

DPWH | Bureau of Construction


N WATERPROOFING
A. Types of Waterproofing

 Membrane Waterproofing

Primer shall be of asphalt cold applied free from water and


other foreign matters, and shall conform to the
specifications requirement defined in ASTM D-41.

Built-up membranes shall be made of smoothly woven


fibers that are impervious to acid, heat, dampness and
totting. They should permit complete penetration of
asphalt compound or bituminous coating in the woven
glass fiber.

DPWH | Bureau of Construction


N WATERPROOFING
A. Types of Waterproofing

 Liquid Waterproofing

Alternate material shall be elastomeric or other


substance applied in liquid form and cured to an
impervious membrane.
B. Quality Control
Minimum Test Requirements:

1-IR (Inspection Report of materials used and if


completed conduct Flood Test)

DPWH | Bureau of Construction


O SANITARY WORKS

Storm Drainage and Sewerage System


This Item shall consist of furnishing all materials,
equipment and labor for the complete installation of the
storm drainage system inclusive of all pipings, gutters,
canals, catch basin, junction boxes, handholes, manholes
and other appurtenant structures, as well as the sewerage
system inclusive of all sanitary sewer pipings and septic
vaults where no public sewer exist, from the building to the
point of discharge.
Construction Requirements

a. Installation of Pipes
b. Sewer Connections and Clean-outs
c. Inspection and Quality Control
d. As-built drawings
DPWH | Bureau of Construction
O SANITARY WORKS

Plumbing
This Item shall consist of furnishing all materials, tools,
equipment and fixtures required as shown in the Plans for
the satisfactory performance of the entire plumbing system
including installation in accordance with the latest edition
of the National Plumbing Code and Specifications.

Material Requirements
a. Water supply pipes and fittings
b. Approved alternate pipe and fittings
c. Septic Tank
d. Plumbing fixtures and fittings
e. Roof Drains, Downspout

DPWH | Bureau of Construction


O SANITARY WORKS

Plumbing
Construction Requirements

a. Installation of Soil, Waste, Drain and Vent Pipes


b. Water Pipes, Fittings and Connections
c. Inspection, Warranty Test and Disinfection
d. Drainage System Test
e. Water Test on System
f. As-built Drawings

DPWH | Bureau of Construction


DPWH | Bureau of Construction
O SANITARY WORKS

Quality Control
Minimum Test Requirements:

1-IR (Inspection Report of materials used and if completed


conduct Pressure/Leak Test (PT)

DPWH | Bureau of Construction


QUALITY CONTROL PROGRAM

JOB CONTROL FORMS

COMMON PROBLEMS

DPWH | Bureau of Construction


DPWH | Bureau of Construction

You might also like