Risk Management Presentation
Risk Management Presentation
General Data
Scope of Work
Input
Risk
Summary Management
Processes
SCOPE OF WORK
SCOPE OF WORK GENERAL DATA INPUTN RISK MANAGEMENT PROCESSES SUMMARY
Risk Response
Plan Risk Response Quantitative Risk Analysis
Implementation
DATA INPUT
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
Project schedule
(Management Risk)
WBS team
Procurement
documentation data
Procurement
(Commercial Risk) Management team
INPUT
Project charter: the high-level project description and boundaries, requirements, and risks.
Project management plan: all approved subsidiary management plans.
Project documents: details of the project’s stakeholders and overview of their roles & attitude toward risk on
this project
Enterprise environmental factors: overall risk thresholds set by key stakeholders.
Organizational process assets: organizational risk policy; risk categories; risk concepts and terms; statement
format; templates; etc.
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
METHOD
Expert judgement: Expertise with specialized knowledge in organization’s approach to managing risk and
tailoring risk management.
Data analysis: a stakeholder analysis to determine the risk appetite of project stakeholders.
Meetings: define plans for conducting risk management activities and documented in the risk management
plan.
OUTPUT
Risk management plan
Includes risk strategy, methodology, roles and responsibilities, funding, timing, risk categories,
stakeholder risk appetite, definitions of risk probability and impacts, probability & impact matrix, reporting
formats, and tracking.
Risk Identification
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
INPUT
Project management plan:
Components include requirements, schedule, cost, quality, resource, risk of management plan
and scope, schedule, cost of baseline.
Project documents
Components include assumption log, cost estimates, duration estimates, issue log, lessons
learned register, requirements documentation, resource requirements and stakeholder register.
Agreements
For external procurement of resources. It contain milestone dates, contract type, acceptance
criteria and awards & penalties.
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
Procurement documentation
For external procurement of resources. The initial procurement documentation should be
reviewed as procuring goods and services from outside the organization that may increase or decrease
overall risk projects or adds individual project risks.
Enterprise environmental factors
Include published material, academic studies, benchmarking results and industry studies of similar
projects.
Organizational process assets
Include project files, organizational and project process controls, risk statement formats and
checklists from previous similar projects.
METHODS
Expert judgement
Expertise with specialized knowledge in similar projects or business areas.
Data gathering
Techniques that can be used are brainstorming, checklists, and interviews.
Data analysis
Techniques that can be used are root cause, assumption and constraint, SWOT and document analysis.
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
OUTPUT
Risk register
Include list of identified risks, potential risk owners, list of potential risk responses.
Risk report
Include sources of overall project risk and summary information on identified individual project
risks.
Project documents updates
Include assumption log, issue log and lessons learned register.
.
Perform Qualitative Risk
Analysis
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
OUTPUT
1. Project documents updates: Assumption log, Issue log, Risk register, Risk report
Perform Quantitative Risk
Analysis
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
INPUT
1. Project Management Plan: Components Risk management plan, scope baseline, schedule baseline, cost
baseline
2. Project Documents: Consideration Assumption log, Basis of estimates, Cost estimates, Cost forecasts, etc
3. Enterprise environmental factors Factors: Industry studies of similar projects and Published material
including commercial risk databases or checklists
4. Organizational process assets Information from similar completed projects
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
OUTPUT
1. Project documents updates: Assumption log, Issue log, Risk register, Risk report
Plan Risk Response
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
INPUT
1. Project management plan: Components Resource management plan, Risk management plan, Cost
baseline
2. Project documents: Consideration Lessons learned register, project schedule, project team assignments,
Resource calendars, Risk register, risk report, stakeholder register
3. Enterprise environmental factors: The enterprise environmental factors that can influence the Plan Risk
Responses process include but are not limited to the risk appetite and thresholds of key stakeholders.
4. Organizational process assets : Assets Templates for the risk management plan, risk register and risk
report; historical databases ; lessons learned repositories
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
OUTPUT
1. Change requests Planned risk responses may result in a change request to the cost and schedule baselines
or other components of the project management plan
2. Project Management plan updates Components: Schedule management plan ; Cost management plan ;
Quality management plan; Resource management plan, etc
3. Project documents updates Updates: Assumptions log, Cost forecasts, lessons learned register, Project
schedule, etc
Risk Response
Implementation
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
INPUT
1. Risk management plan
2. Documents: lessons learned register, risk register, risk report
3. Organizational process assets
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
METHODS TO ACCOMPLISH
1. Expert Judgement : Expertise individuals/groups with specialized knowledge
- Validate or modify risk responses*
- Decide how to implement them in the most efficient & effective way
OUTPUT
1. Change requests
2. Project documents updates: issue log, lessons learned register, project team assignments, risk register, risk
report
WBS
RBS Level 0 RBS Level 1 RBS Level 2
1.1 Scope definition
WBS
1.2 Requirements definition
1.3 Estimates, assumptions, and constraints
1. Technical Risk 1.4 Technical processes
1.5 Technology
1.6 Technical interfaces
Etc.
2.1 Project management
2.2 Program/portofolio management
2.3 Operations management
All Sources of Project Risk 2. Management Risk 2.4 Organization
2.5 Resourcing
2.6 Communication
Etc.
4.1 Legislation
4.2 Exchange rates
4.3 Site/facilities
3. Commercial Risk 4.4 Environmental/weather
4.5 Competition
4.6 Regulatory
Etc.
CONCEPTUAL MAP
SCOPE OF WORK GENERAL DATA INPUT RISK MANAGEMENT PROCESSES CONCEPTUAL MAP
TERIMAKASIH !