ME3608 Technopreneurship: Instructor: Mashal Tariq
ME3608 Technopreneurship: Instructor: Mashal Tariq
Instructor:
Mashal Tariq
5 Steps to Building a Successful Niche
Business
• Unlike conglomerates that target the masses,
niche businesses cater to highly defined
markets that are often over-looked,
underserved or disenfranchised by larger
competitors.
• There are two ways you can now identify the critical path. You can eyeball
your network diagram and simply identify the longest path throughout the
network .
• Be sure to look for the longest path in terms of longest duration in days, not
the path with the most boxes or nodes.
• You can also identify critical activities with the
Forward Pass/Backward Pass technique,
identifying the earliest start and finish times,
and the latest start and finish times for each
activity.
• If you have multiple critical paths, you will run
into network sensitivity. A project schedule is
considered sensitive if the critical path is likely
to change once the project begins. The more
critical paths in a project, the higher the
probability of a change in schedule.
Step 6: Update the Critical Path Diagram to
Show Progress
• As the project progresses, you will learn the actual
activity completion times. The network diagram
can then be updated to include this information.
• By updating the network diagram as new
information emerges, you may recalculate a
different critical path.
• You will also have a more realistic view of the
project completion due date and will be able to
tell if you are on track or falling behind.
Critical Path Method and PERT
• You can use PERT in your critical path method in step four of the
process, when you have to estimate activity completion times.
The purpose of using PERT is to bias time estimates toward the
most likely scenario and move away from unrealistically short
timeframes.
• To use PERT, you must estimate the shortest possible time each
activity will take, the most likely length of time, and the longest
time it might take if the activity lasts longer than expected.
• With that information, you can use this formula when you have
to estimate activity completion times in the critical path method
(step four).
• Shortest time + 4x likely time + longest time / 6 = expected
activity completion time
How to Find the Critical Path on a PERT
Chart
• You can identify the critical path on a PERT
chart because the chart includes the same
information needed for the network diagram
in the critical path method.
• How to Use the Forward Pass/Backward Pass
Technique
• The Forward Pass/Backward Pass technique is
another way to find the critical path. It is best
used when you have multiple branches, or
multiple entry points, for an activity.
• You may also need to use the Forward
Pass/Backward Pass technique if you are asked
to identify the earliest start or finish times, or
latest start or finish times, for an activity. Or,
to find the slack (or float) for each activity.
• Before you start using the Forward Pass/Backward Pass
technique, here are some terms that you first need to
understand:
• Earliest start time (ES): The earliest time an activity can
start once the previous dependent activities are
completed.
• Earliest finish time (EF): The earliest start time for the
activity plus the time required to complete the activity
(the earliest an activity can be completed).
• Latest finish time (LF): The latest time an activity can be
completed without delaying the entire project.
• Latest start time (LS): The latest finish time minus the time
required to complete the activity.
• As you run the Forward Pass/Backward Pass
technique through your network diagram,
arrange each value according to the following
legend (SL stands for slack).
• How to Do the Forward Pass: Finding the
Earliest Start Time and Finish Time
• There are two formulas in the Forward
Pass/Backward Pass technique.
• The first is the Forward Pass formula for you to
use as you move from beginning to end in your
network diagram (from your first activity to
your last).
• This formula will find the earliest start time
(ES) and the earliest finish time (EF) for each
activity.
• To start the Forward Pass, make the ES of the
first task zero. For all other tasks, the ES is the
same as its immediate predecessor’s EF.
• Use this formula to calculate EF:
• EF = ES + Duration
• So, for Design Tank Project, the ES is zero and,
the EF is 10 (10+ duration of 0). We also know
that the ES for Select Tank Supplier is 10 and
the EF is 18 (10 + duration of 8). Continue like
this throughout the network diagram.
• How to Do the Backward Pass: Finding the
Latest Start Time and Finish Time
• The second formula is for Backward Pass,
when you are moving from the last activity to
the first activity (you are moving backwards).
This formula will find the latest start time (LS)
and latest finish time (LF) for each activity.
• To start the Backward Pass, make the last
activities LF the same as its EF. For all other
tasks, the LF is the same as its immediate
predecessor’s LS.
• Use this formula to calculate LS:
• LS = LF - Duration
• For the Test & Commission Tank, the LF is 54 and, the
LS is 50 (54 - duration of 4). For Assemble Tank, the LF
is also 50 and, the LS is 35 (50 - duration of 15 days).
Continue this formula throughout the network
diagram.
• To check that you’ve done Backward Pass correctly, the
first activity (Activity A) should have an LS (latest start
time) of 0.
• Here’s the completed Forward Pass/Backward Pass
technique:
• Two Rules to Remember for Forward Pass/Backward Pass
• During the Forward Pass, if you find activities that join (multiple activities
that flow into one activity), you must run the Forward Pass formula for
each entry point and use the highest value from the formulas.
• During the Backward Pass, if you have activities that join, you must run
the formula for each entry point and use the lowest value.
• How to Calculate Float or Slack on the PMP Exam
• Now that you have calculated ES and LS for each activity, you can find the
float (or slack).
• The slack time, also known as float time, for an activity is the time
between the earliest and latest start time. Critical activities, activities on
the critical path, will always have zero slack.
• There are two formulas to calculate slack based on the values you
identified in the Forward Pass/Backward Pass technique.
• Slack = LF - EF
• Slack = LS - ES
Gantt chart