Week 11 Grounding Problem
Week 11 Grounding Problem
AØ BØ CØ AØ BØ CØ AØ BØ CØ
Zig-Zag
HRG
Grounding
Transformer
Generators are not often operated ungrounded. While this approach greatly
limits damage to the machine, it can produce high transient over-voltages
during faults and also makes it difficult to locate the fault.
KNR 3483 Power Quality and Reliability
Professor Dr. Musse Mohamud
Generator Grounding – IEEEIEEE Std. 142-1991 (Green Book)
1.8.1 Discussion of Generator Characteristics
…Unlike the transformer, the three sequence reactances of a generator are not equal.
The zero-sequence reactance has the lowest value, and the positive sequence
reactance varies as a function of time. Thus, a generator will usually have higher
initial ground-fault current than a three-phase fault current if the generator is
solidly grounded. According to NEMA, the generator is required to withstand
only the three-phase current level unless it is otherwise specified…
A generator can develop a significant third-harmonic voltage when loaded. A
solidly grounded neutral and lack of external impedance to third harmonic current will
allow flow of this third-harmonic current, whose value may approach rated current. If
the winding is designed with a two-thirds pitch, this third-harmonic voltage will be
suppressed but zero-sequence impedance will be lowered, increasing the ground-
fault current. Internal ground faults in solidly grounded generators can produce
large fault currents. These currents can damage the laminated core, adding
significantly to the time and cost of repair…Both magnitude and duration of these
currents should be limited whenever possible.
KNR 3483 Power Quality and Reliability
Professor Dr. Musse Mohamud
Amps Interrupting Current (AIC) Rating
Line to Ground Fault Current is 125% of the Phase Current Fault in this
example
Solution – Make sure you check your AIC rating of the equipment and use
a Neutral Grounding Resistor.
A large generator (> 20 MVA, 13,800 volt) may take 5 to 20 seconds to stop.
An IEEE working group wrote a series of four papers. They proposed a hybrid
system having a low resistance grounding system and when the fault occurred
switch to a high resistance grounded system.