Lec-12 Development Length
Lec-12 Development Length
In the above fig, the moment, and therefore the steel stress
is maximum at point ‘a’ and zero at the supports, if the bar
stress is fs at ‘a’, then the total tension force Abfs must be
transferred from the bar to the concrete in the distance l by
bond forces.
To fully develop the strength of the bar, Abfy, the distance l
must be at least equal to the development length of the bar.
However, if the actual available length is inadequate for full
development, special anchorage, such as by hooks, must be
provided.
Modification Factors
ld 3 fy
db 40 f c c K tr
db
c k tr
In which the term shall not be taken greater than 2.5
db
Where
α = reinforcement location factor
Horizontal reinforcement so placed that more than 12” of fresh
concrete is cast in the member below the development length or
splice 1.3
Other reinforcement 1.0
β = Coating factor
Epoxy-coated bars or wires with cover less than 3db or
clear spacing less than 6d 1.5
Basic Equation For Development length of Tension Bars
All other epoxy-coated bars or wires 1.2
6.7 f c
However, when fct is specified, use
f ct
but not less than 1.0
When normal weight concrete is used 1.0
Basic Equation For Development length of Tension Bars
C = spacing and cover dimensions, in.
Use the smaller of either the distance from the center of the
bar to the nearest concrete surface or one-half the center-to-
center spacing of the bars being developed.
A tr f yt
Ktr=Transverse reinforcement index = 1500Sh
For 900 hooks of #11 and smaller bars that are either enclosed
with ties or stirrups perpendicular to the bar being developed,
spaced not greater than 3db along the development length ldh of
the hook; or enclosed within ties or stirrups parallel to the bar
being developed, spaced not greater than 3db along the length of
the tail extension of the hook plus bend. 0.8
For 180o hooks of #11 and smaller bars that are enclosed
within ties or stirrups perpendicular to the bar being developed,
spaced not greater than 3db along the development length ldh of
the hook. 0.8
Modification factors applied to ldh
Where anchorage or development for fy is not specifically
required, reinforcement in excess of that required by analysis.
A s required
A s provided
β:
For epoxy-coated bars 1.2
For other bars 1.0
λ:
For lightweight aggregate concrete 1.2
For normal weight concrete 1.0
Mechanical Anchorage
For some special case, e.g. at the ends of main flexural
reinforcement in deep beams, there is not room for hooks or the
necessary confinement steel, and special mechanical anchorage
devices must be used. These may consists of welded plates,
manufactured devices, or T-headed bars, the adequacy of which
must be established by tests.
For these
top bars,
uncoated
and with
normal
density
concrete
α=1.3
β=1.0
λ=1.0
Center to center spacing of #11 bars
is 1.41
10 2(1.5 0.38 ) 4.83 in.
2
One half of which is 2.42 in.
Solution
The side cover to bar center line is 1.5 0.38 1.41 2.59 in.
2
d b
3 60,000 1.3 1.0 1.0 1.0
1.41
40 4000 2 . 34
55 .7 in.
In this case, side cover for the No.11 bars exceeds 2.5” and the
cover beyond the bent bar is adequate, so a modifying factor of
0.70 can be applied. The only other factor applicable is for excess
reinforcement. Accordingly, the minimum development length for
the hooked bars is
Solution
2 .9
dh 26.75 0.7 17.4 in.
3.12
With 21-2 = 19” is the available, thus the required length is
contained within the column.
8x1.41=11.28 in.
The bar will continue for 12x1.41=16.9 in. past the end of the
bend in the vertical direction.
Anchorage requirements for web reinforcement
The tensile strength of the stirrups must be developed for
almost their full height. Clearly, it is impossible to do this by
development length.
For this reason, stirrups normally are provided with 90o or 135o
hooks at their upper end (see back for hook details) and at their
lower end, are bent 90o to pass around the longitudinal
reinforcement.
A s required
A s provided
Bars must extend the longer of d or 12db past the flexural cut
off.
At least one-third of the positive moment steel (one fourth
continuous spans) must be continued uninterrupted along the
same face of the beam a distance at least 6” into the support.
ACI Code Requirements
For nearly equal spans, uniformly loaded, in which not more than
about one-half the tensile steel is to be cut off or bent, the
locations shown in above fig. are satisfactory.
ACI Code Requirements
ACI Code Requirements
In the above fig, the beam at the exterior support at the left is
shown to be simply supported.
If the beam is monolithic with exterior columns or with a
concrete wall at that end, details for a typical interior span could
be used for the end span as well.
When the bars are cut off in a tension zone, there is a
tendency toward the formation of premature flexural and
diagonal tension cracks in the vicinity of the cut end. This may
result in a reduction of shear capacity.
ACI code requires special precautions, specifying that no
flexural bar shall be terminated in a tension zone unless one of
the following conditions is satisfied:
ACI Code Requirements
The shear is not over two-thirds that normally permitted,
including allowance for shear reinforcement, if any.
Stirrups in excess of those normally required are provided
over a distance along each terminated bar from the point of cut
3
off equal to d. These binder stirrups shall provide an area
4
bw s
A v 60
fy . In addition, the stirrup spacing shall not exceed
d
8b ,where βb is the ratio of the area of bars cut off to the
total area of bars at the section.
The continuing bars, if #11 or smaller, provide twice the area
required for flexure at that point, and the shear does not exceed
three-quarters of the design strength Vn.
Bar Splices
In Tension.
Two types of splice
1. A-class splice requires 1.0ld lap
2. B-class splice requires 1.3 ld lap.
Splice should not be less than 12”
Generally B-Class.
A s provided
When 2 and one-half or less of the total
A s required
For f’c less than 3000 psi, the required lap is required to be
increased one-third.
When bars are different sizes are lap spliced in compression,
the splice length is to be larger of the development length of the
larger bar and splice length of the smaller bar.
Column Splice