Lo 2 - Demolition
Lo 2 - Demolition
DEMOLITION 1
Identify the
different
techniques used
in building
demolition
focusing on
processes, safety
precautions and
salvage values.
2
REASONS OF DEMOLITION
1. STRUCTURAL FAILURE
3. ECONOMIC CONSIDERATIONS
4
SURVEY
• Survey property and
adjoining buildings.
• Survey will help
choose a demolition
method.
• Record structural
condition of adjoining
buildings.
• Services cut off, check
for dangerous
substances.
• Inform authorities.
5
CHOICE OF METHOD OF DEMOLITION
• Type of structure:
high-rise, low rise?
• Type of construction:
steel, clay, concrete or
timber?
• Location of site:
near other buildings, out
on its own? (distance to
boundary >twice height of
building)
6
METHODS OF DEMOLITION
• Hand demolition
• Mechanical
demolition
• Deliberate
demolition
• Demolition ball
• Rope pulling
• Explosives
7
HAND DEMOLITION
• Reverse order to
construction.
• Hand held tools.
• Rubbish chute used.
• Material into skips.
• Some material may be
for scrap or reused.
• Slow process but safe
and less dust and noise.
• Lots of men.
8
MECHANICAL DEMOLITION
• Use of larger
machines and
cutting equipment.
• Quicker process.
• Cutting tools,
crushing tools and
breakers used.
• Machines outside
structure safer.
9
DELIBERATE COLLAPSE
• Removal of key
supports to
collapse building.
• Must be done by
experienced
people.
• Causes dust and
vibration.
• Use of ropes,
explosives or gas
or hydraulic
busters. 10
DEMOLITION BALL
• Weight swung or
dropped from
crane.
• Causes lots of dust
and vibrations.
• Needs lots of room
and experience.
• Dangerous method
for workers, must
leave building.
11
ROPE PULLING
• Use of wire rope to
pull out sections of
the building.
• Care must be taken
to be far enough
away from the
building.
• Machine with
winch or tracked
vehicle used to pull
members.
12
EXPLOSIVES
• Most dramatic and
dangerous process
used.
• Needs experience and
expertise.
• Control by authorities.
• Progressive collapse
of building.
• Lots of vibration and
dust and flying debris.
• May need debris nets.
13
BURSTING
14
THERMAL METHODS
15
DEMOLITION SAFETY
16
CONTROLLED DEMOLITION
The specialty of the group is
controlled blasting in populated
areas, where the avoidance of
vibrating of debris on damage to
nearby structures and the
scattering of debris is of paramount
importance. Through its numerous
projects, which have included
multi-storey buildings, minerals,
water towers and heavy
foundations, the group has justly
earned its reputation for providing
a professional onshore and offshore
controlled demolition service,
where safety is never compromised
and the result never in doubt.
17
MECHANICAL DEMOLITION_
18
HOW TO DEMOLISH DIFFERENT PARTS
OF A BUILDING AND TYPES OF
BUILDING STRUCTURES
1. PITCHED ROOFS
19
2. BRICK WALLS
If the bricks are to be cleaned for re-use, the wall will be taken
down by hand and the personnel usually work from a scaffolding
platform. The scaffold should be the independent tied form and
can be progressively dismantled as demolition proceeds,
providing the stability of the scaffold is not impaired.
When the bricks are not required for use again the wall may be
pushed down with a pusher arm, knocked down by a ball or
pulled down with a wire rope. A wall should never be
demolished by standing on top of it and belabouring it with
sledgehammer!
20
3. STEEL FRAME STRUCTURES
First the internal partitions are taken out. Then the roof, floors
and cladding are removed, generally using hand methods.
If the floors or any of the cladding panels or internal partitions
provide the frame with lateral restraint, temporary bracing
should be fixed as necessary.
Once the frame has been exposed it is dismantled by either
unbolting or cutting the members, usually working in reverse
order to the erection procedure and always in a sequence
which ensures that the remaining structure is stable.
21
4. IN-SITU REINFORCED CONCRETE STRUCTURES
22
5. PRE-CAST REINFORCES CONCRETE STRUCTURES
23
5. PRESTRESSED CONCRETE STRUCTURES
24
PRE-TENSIONED members are the simpler to deal
with since they often are similar to pre-cast
reinforced concrete members and, if they can be
released at their fixing points they can be lifted out
without disturbing the prestressed steel tendons.
As with prestressed concrete member, the released
beams and stanchions must be handled in the
attitude they occupy in the building. Beams must not
be turned over or lowered on end, columns must not
be laid flat before lifting. To do so adds the mass of
the concrete to the prestress forces and the member
will shatter.
25
POST-TENSIONED_ structures are very difficult to
demolish and the advice of Engineer, expert in this
form of construction, must be sought and closely
followed. It is essential that no indiscriminate
attempt is made to expose and de-stress the
tendons. Post-tensioned structures are composed of
pre-cast, often un-reinforced, concrete units which
are assembled end to end and wire reinforcing
tendons are threaded through prepared ducts in the
concrete.
When a tensile force is applied to the steel wires the
concrete units are pressed solidly together and act
as a structural unit.
27
The following are some of the criteria which can be
used to determine whether the structure has been
prestressed. It should be noted, however, that not all
prestressed members meet all criteria:
28
29