Material Quality Control and Production
Material Quality Control and Production
Quality Control (QC) – Depends on the contract but best practices require;
• The Construction Contract defines the quality standards and the QC testing
requirements
• The contractor must prepare a detailed quality control plan for each definable
feature of work detailing how the quality standards will be achieved. The plan
must be approved before work can begin.
• The contract requires that the QC testing lab be validated by the approved
source
• Employs Three-Phase Inspection System
– Preparatory : Before the work starts the QC manager conducts a meeting to
go over all the approved submittals, work plan, safety plan, etc with all parties
involved in order to make sure the feature of work is ready to begin and makes
sure everyone is on the same page.
– Initial: As the work is beginning the QC manager conducts an inspection of the
work to make sure the work is being performed as plan. The crew is working
safely and with the correct material.
– Follow-up: Throughout the work the QC manager conducts inspection as per
contract and as required.
• Document QC activities into a Management System which includes;
1. Non compliance Reports
2. RFIs (Request for information)
3. Change orders requests
4. Safety violations
5. Daily field reports
6. Test results
7. Permits
8. Close Documents
9. QA/QC plan - Testing program
Quality Assurance : Usually done by a third party or the Government
• Performed to ensure the contractor’s QC system is functioning properly
• QA testing at least 5% frequency of QC testing
• QA surveys spot check TBMs, baselines and grade shots
www.learncivilengineering.com