IBS SCORING BCT504 - Sharifah - Ainie - Aidil - Zamirul
IBS SCORING BCT504 - Sharifah - Ainie - Aidil - Zamirul
PREPARED BY:
IBS SCORE – Upper Roof Area, Precast Columns & Beams + No Slabs
PART 1:
= 71m2 = = 71/869.18 = 0.08
Upper Roof Area, Precast Beam & In-Situ Column with Reusable Fwk + No Slabs
STRUCTURAL
= 50m2 = = 50/869.18 = 0.06
SYSTEM 50
NO ELEMENTS AREA/LENGTH IBS COVERAGE IBS SCORE
FACTOR
PART 1: STRUCTURE
ELEMENT
1ST FLOOR
Precast columns & beams + 264.6m2 1.0 0.3 50 x 1.0 x 0.3 = 15
precast half slab
WATER TANK AREA
Precast columns & in-situ 230.76m2 0.6 0.27 50 x 0.6 x 0.27 = 8.1
beams + no slab
Precast columns & in-situ 24.82m2 0.6 0.03 50 x 0.6 x 0.03 = 0.9
beams + in-situ concrete
reusable formwork
LOWER ROOF AREA
Prefabricated metal roof 227m2 1.0 0.26 50 x 1.0 x 0.26 = 13
trusses
UPPER ROOF AREA
Precast Columns & Beams + 71m2 1.0 0.08 50 x 1.0 x 0.08 = 4
No Slabs
Precast Beam & In-Situ 50m2 0.6 0.06 50 x 0.6 x 0.06 = 1.8
Column with Reusable Fwk +
No Slabs
TOTAL PART 1 869.18m2 1.00 42.8
1st Floor, Area of External wall using precast concrete panel
Total Construction Area, Qst = 552m = 72m = = 72/552 = 0.13
1st Floor, Area of Internal wall using precast concrete panel
= 284m = = 284/552 = 0.51
Water Tank, Area of External wall using precast concrete panel
= 72m = = 72/552 = 0.13
Water Tank, Area of Internal wall using precast concrete panel
= 24m2 = = 24/552 = 0.04
IBS SCORE –
Lower Roof Area, Area of External wall using precast concrete panel
= 36m2 = = 36/552 = 0.07
PART 2: WALL Upper Roof Area, Area of External wall using precast concrete panel
= 64m2 = = 64/552 = 0.12
SYSTEM 20
NO ELEMENTS AREA/LENGTH IBS COVERAGE IBS SCORE
FACTOR
PART 2: WALL SYSTEM
1ST FLOOR
External wall using precast 72m 1.0 0.13 20 x 1.0 x 0.13 = 2.6
concrete panel
Internal wall using precast 284m 1.0 0.51 20 x 1.0 x 0.51 = 10.2
concrete panel
WATER TANK AREA
External wall using precast 72m 1.0 0.13 20 x 1.0 x 0.13 = 2.6
concrete panel
Internal wall using precast 24m2 1.0 0.04 20 x 1.0 x 0.04 = 0.8
concrete panel
LOWER ROOF AREA
External wall using precast 36m2 1.0 0.07 20 x 1.0 x 0.07 = 1.4
concrete panel
UPPER ROOF AREA
External wall using precast 64m2 1.0 0.12 20 x 1.0 x 0.12 = 2.4
concrete panel
TOTAL PART 2 867m2 1.00 20
NO ELEMENTS AREA/LENGTH IBS FACTOR COVERAGE IBS SCORE
PART 3: OTHET SIMPLIFIED
CONSTRUCTION SOLUTION
100% of beam sizes follow MS 1064 100% 4
Part 10:2001
86.67% of column sizes follow 86.67% 4
MS:1064 Part 10:2001
100% wall and slab sizes follow MS 100% 4
1064 Part 4:2001
80% door sizes follow MS 1064 Part 80% 4
4:2001
80% window sizes follow MS 1064 Part 80% 4
4:2001
Horizontal Repetition of 50% 2
Structure=50%
TOTAL PART 3 22
IBS CONTENTS SCORE OF PROJECT (PART 1 + PART 2 + PART 3) 84.8