Temperature Measuring Instruments Selection & Application
Temperature Measuring Instruments Selection & Application
2
Course/Learning Objectives
3
INTRODUCTION
4
Introduction
• Standards
• Cost
• Accuracy
• Stability over time (esp. for high temperatures)
• Sensitivity
• Size
• Contact/non-contact
• Temperature range
• Fluid
• Any particular functional requirements (like fast response, surface
temperature measurement, average temperature etc.)
5
THERMOCOUPLES (TC’s)
6
Thermocouples (TC’s)
7
Thermocouples (TC’s)
8
Thermocouple Resolution
9
Thermocouple
10
Thermocouple
11
Thermocouples- Application Notes
As a general rule of thumb, the below listed thermocouple material
combinations should be selected for the temperatures indicated:
12
Advantages of Thermocouples
Fast Response.
Wide Range.
13
Disadvantages of Thermocouples
14
RTD’s
15
RTD Selection
Temperature Notes
of turbine inlet steam whose design temperature is close
to the maximum allowable temperature for piping and equipment.
Applications requiring high accuracy like Custody flow metering and Tank
gauging.
16
Advantages of RTD
High accuracy.
Interchangeability.
17
Disadvantages of RTD
Susceptibility to mechanical damage.
Sometimes expensive.
18
RTD – Types , Ranges, Accuracy
19
RTD’s & TC’s COMPARISON
20
RTDs and T/Cs : Properties Comparison
21
RTD vs TC Accuracy Overview
22
THERMISTORS
23
Thermistors
Thermistors also measure the change in resistance with temperature.
Thermistors are very sensitive (up to 100 times more than RTDs and
1000 times more than thermocouples) and can detect very small
changes in temperature. They are also very fast.
Due to their speed, they are used for precision temperature control and
any time very small temperature differences must be detected.
24
CHOICE BETWEEN RTD’s TC’s & THERMISTORS
25
Choice Between RTDs, Thermocouples,
Thermistors
26
THERMOWELL DESIGN & MATERIAL
27
Thermowell Design & Material
Considerations for Thermo well selection:
• Process temperature
• Flow velocity
• Based on the above thermo well length and diameter are decided.
• Insertion length is normally within mid two third of the pipe inner diameter.
Smaller lengths are used for high velocity process stream.
28
Thermowell- Application Notes
Interface
In case, if material of construction (MOC) of Thermo well is different than
the pipe class material, the flange rating of Thermo well shall be suitable
& withstand pipe line design condition i.e. pressure & temperature.
For example, if pipe class is Carbon Steel (CS) and MOC for Thermo
well is SS316, then Instrument Engineer should check the rating required
for Thermo well based on line design pressure & temperature.
Incase if the flange rating of Thermo well is different than the pipe rating ,
it should be communicated to Piping & Process to take necessary action
at their end ( Provide nozzle with same rating as thermo well rating .)
29
Thermowell- Application Notes
Interface
Requirement of Insulating Gasket shall be communicated to Mechanical
and process in case material of construction for thermo well is different
than piping material.
In case, if Thermo wells are with collar to protect it from failure due to
high vibration, then the nozzle ID shall be checked with respect to collar
diameter. This information should be communicated to Mechanical to
avoid any mismatch during installation.
Care shall be taken when Thermo wells are selected with collars for lined
vessels and cladded vessels. In these cases nozzle ID shall be checked
with equipment drawings to avoid mismatch of Thermo well during
installation.
30
Thermowell- Application Notes
Interface
Additional nozzles due to SIL study: It is possible that SIL review may
demand additional temperature instrument for shutdown loops. As the
nozzles on the equipment are normally frozen much before the SIL
study, it is necessary to see whether the Feed documents like Feed
P&IDs which are used to prepare the detailed P&IDs have already
considered the recommendation of Feed stage SIL review.
NDE requirement for Thermo well shall be checked and specify as per
piping requirement.
31
Thermowell- Application Notes
Interface
When the Thermo wells are installed on the equipment & vessel, care
shall be taken while deciding insertion length of these Thermo wells to
avoid fouling with equipment/vessel internals.
Equipment/vessel internal arrangement drawing & nozzle location shall
be reviewed by Instrument engineer to avoid any mismatch.
Otherwise it is necessary to review with the Process group for safety
critical applications where the P&IDs do not indicate multiple
temperature instruments participating in voting logic. If necessary
additional nozzles should be provided as spare for use in future in case it
is recommended by the SIL study at a later date.
To meet the SIL level, two or more than two temperature elements may
be required in a safety protection loop. Duplex temperature elements
may be used for such purpose; however use of duplex temperature
element (i.e. two temperature elements in a single thermo well or
encapsulation) must be carefully reviewed, as the duplex element may
be more vulnerable to common mode failure than two simplex elements.
32
Thermowell- Application Notes
Interface
If the temperature to be measured is not required for automatic control,
recording, or indication in the control room, a bimetallic thermometer
should be used.
33
Thermowell- Application Notes
Interface
34
BIMETALLIC THERMOMETERS
35
Bimetallic Thermometers- Selection Notes
36
FILLED THERMAL SYSTEM
37
Filled Thermal System- Selection Notes
Occasionally a temperature transmitter, recorder and/or controller has to
be installed in a location or under circumstances where electrical power
is not available or inconvenient to use, while instrument air (at 20 psig or
above) is present. Under these circumstances, a filled system
thermometer is an ideal choice because it can be combined with a
commercially available pneumatic transmitter, recorder and/or controller.
38
Filled Thermal System- Selection Notes
39
DIAL THERMOMETERS
40
Dial Thermometers- Standard ranges
41
INFRARED PYROMETERS
42
Infrared Pyrometer-Selection Notes
The Infrared Pyrometer can measure temperatures in the range from
-100 to 3500 deg C (standard) and up to 5000 deg C with an accuracy of
± 1/2 % full scale. Therefore, it is used when a temperature
measurement must be made that is above the capability of
thermocouples.
43
Infrared Pyrometer-Selection Notes
44
TEMPERATURE CONTROL
45
Basic Temperature Control
• Furnace
• House is too cold
• furnace turns on
• heats the house
• is • house temperature
temperature
• below
• measured
setpoint?
• setpoint = 72°F
46
PETROFAC WORK PROCESS
47
PETROFAC WORK PROCESS
Temperature Measurement System
Basic Data:
• Check tag no. of the temperature measuring instrument from P&ID. Example
– TIT-100 or TI/TG-100
• Check piping specification for the particular line in which the instrument is
being installed and enter the material of construction, flange rating, flange
facing etc for thermowells. MOC for thermowell shall be minimum SS316.
(Refer project Piping specification for this requirement.)
• Complete the datasheet by filling all other required details such as accuracy,
type of instrument, immersion length, output etc. (Piping & Instrument
interface drawing, Equipment internal arrangement drawings to be referred.).
49
PETROFAC WORK PROCESS
Temperature Measurement System
50
TEMPERATURE GAUGE & TRANSMITTER DATA SHEET
51
Instrument Datasheet- Temperature Gauge
52
Instrument Datasheet- Temperature
Transmitter
53
WAKE FREQUENCY
54
Wake Frequency Calculation
Some of parameter can increase the drag force are velocity and density
whereas Large thermo well surface areas and lengths also contribute to
increase this force. Calculations
• Thermowell
1) Ensure that:
55
LESSONS LEARNED
56
Lesson Learned- session 1
• RTD Cables are laid inside Electrical Trench as per routing layout at Site.
• Error was identified during inspection & shifted to route in Instrument Trench
• Most of the Cables are re-ordered due to length mismatch when routed over
Instrument Trench.
57
Lesson Learned- session 1
58
Lesson Learned- session 2
59
QMS DOCUMENTS
60
QMS documents – Technical Bid evaluation
61
QMS documents – Datasheets
62
QMS documents – SUPPLIER DOCUMENT
REQUIREMENT LIST (SDRL)
63
PETROFAC DOCUMENTS REFERANCES
64
Petrofac Document References
65
INTERNATIONAL STANDARDS
66
International Standards
North America
• NEMA (National Electrical Manufacturers Association), UL (Underwriters
Laboratories), CSA (Canadian Standards Association
67
References
ISA MC 96.1: Temperature Measurement Thermocouples
PIP PCETE001: Temperature Measurement Guidelines
PIP PCFTE100: Thermo well Fabrication Details
ASME PTC 19.3: Temperature Measurement
ASME B40.200: Thermometers, Direct Reading and Remote Reading
IEC751: Industrial Platinum Resistance Thermometers & Platinum
measuring Resistors.
ISA-MC 96.1: Temperature Measurement Thermocouples
WIKA Handbook for Pressure and Temperature Measurement.
Liptak, Bela G. "Instrument Engineers' Handbook" : Process
Measurement.
Claire Soares (McGraw-Hill) : “Process Engineering Equipment
handbook”
68
Review
69
QUESTIONS?
70