Introduction To Construction Contract
Introduction To Construction Contract
CONSTRUCTION CONTRACT
1
Objectives
This short course is designed to give an overview
of the Construction contract requirements for
construction works contracts.
2
Contracts
What? Is the document that specifies the rights,
obligations and responsibilities of the major parties
involved in the contract:
Indirect stakeholders’ boundary
Users
Contractor
Regulatory/Statutory
bodies Suppliers
Client
4
Contracts
Major risks in construction projects
Project integration
Communication
Scope
Defaulting
Delays Cost overrun
Time
Procurement
Cost
5
Contracts
Risk of defaulting by a contracting parties
Non performance
Default performance
Non [on time] payment
Risk management
Respond to risks
Identify objectives Identify risks Quantify risks Avoid Transfer
Mitigate Accept
Mitigate risk
Transfer risk
Avoid risk
6 Accept risk
Contracts
Risk transfers in contracts
Project
Owner
Risk Banks
Risk
General
Contractor
Risk
Risk
Sub-Contractor
Insurance
Risk
The Contractor
The Consultant
8
Contract Relationships
9
Major types of contracts common in Construction
Client
Contractor Consultants
“Works" Contract “Service" Contract
Suppliers
“Goods” contracts
The procurement procedures, evaluation criteria adopted, etc vary substantially
among the above procurements
10
Major types of contracts common in
Construction
11
Tender & Contract Documents
The Legal Part
• The Contract Agreement;
• Others, if any;
Tender & Contract Documents
The Commercial Part
The Performance Security Form;
The Payment Security Form;
The Retention Money Security Form;
Others, if any
Tender & Contract Documents
The Technical Part
The Contract Agreement shall also declare the priority of the Contract Documents i.e.
which Contract Document shall have precedence or priority over the other in case of
ambiguity or discrepancy between or among the relevant Contract Documents.
Construction (Work) contracts
Major Components:
Agreement, if any
Usually made to cater for the ‘acceptable corrections and
modifications’ made during negotiation of the two parties
Most GCC’s provide a model for the form of agreement: Eg. in
section 9 of PPA’s SBD);
Letter of Acceptance
Forms part of the contract and is furnished (PPA) at least five
working days after notification of successful bidder
15
Construction contracts
Contractor’s Bid
Usually supplied in bid submission form
It stipulates summary of the major requirements of the bid
documents like:
Bid price and validity period (usually from 60-120 days
depending on complexity of process)
Declaration of eligibility of contractor and proposed
subcontractors and suppliers (legal, conflict of interest, etc)
Amount of advanced payment (up to 20% for buildings and
30% for roads)
Declaration of full consent with the terms of the documents
and acceptance of PE’s right not to accept lowest bidder
16
Construction contracts
Construction contracts
Special Conditions of Contract
General Conditions of Contract
Specifications
Drawings
Bill of Quantities or Activity Schedule
17
Contents Function and broad outline of contents
Number Heading
Agreements and contract data
Form of Offer and This form formalizes the legal process of offer and acceptance. The following provisions are
Acceptance common to most agreement forms:
Identification and full address of the signing parties, short description of the project and the
work, date of commencement and signature, completion time of the project, the contract
price, and enumeration of contract documents constituting the entire agreement.
Standard or General States the applicable conditions of contract and associated contract specific data that
Conditions of collectively describe the risks, liabilities and obligations of the contracting parties and the
Contract: procedures for the administration of the contract.
Particular or Special This document provides more specific and relevant information and conditions to a particular
Conditions of project. It is a supplementary and modified section of the general conditions of contract.
Contract Special conditions include additional owner requirements.
Pricing data
Activity Schedule / Bill of Records the contractor's prices for providing supplies / services / engineering and construction
Quantities works which are described elsewhere in a specification within the Scope of Work section
of the contract.
Scope of Work
Technical Specifications Specifies and describes the supplies, services, or engineering and construction works which are
& Methods of to be provided and any other requirements and constraints relating to the manner in which
Measurement the contract work is to be performed.
Drawing These are intended to describe the size and dimensional requirements of the project. Many
professionals are involved in developing drawings. These include the architectural,
structural, sanitary, mechanical, electrical, topographic survey, land profile, and detailing.
Miscellaneous
Appendix to Construction Comprises tabulated and narrative information of the project such as amount and liquidated
Agreement: damages, interest rates, completion time, amounts of bond and insurances, defects
18 liability period, retention, progress payments, advance payment, etc. Some of this
information might be left blank to be filled by the contractor or might be readily provided
by the client.
Contents Function and broad outline of contents
Number Heading
Agreements and contract data
Form of Offer and This form formalizes the legal process of offer and acceptance. The following provisions are
Acceptance common to most agreement forms:
Identification and full address of the signing parties, short description of the project and the
work, date of commencement and signature, completion time of the project, the contract
price, and enumeration of contract documents constituting the entire agreement.
Standard or General States the applicable conditions of contract and associated contract specific data that
Conditions of collectively describe the risks, liabilities and obligations of the contracting parties and the
Contract: procedures for the administration of the contract.
Particular or Special This document provides more specific and relevant information and conditions to a particular
Conditions of project. It is a supplementary and modified section of the general conditions of contract.
Contract Special conditions include additional owner requirements.
Pricing data
Activity Schedule / Bill of Records the contractor's prices for providing supplies / services / engineering and construction
Quantities works which are described elsewhere in a specification within the Scope of Work section
of the contract.
Scope of Work
Technical Specifications Specifies and describes the supplies, services, or engineering and construction works which are
& Methods of to be provided and any other requirements and constraints relating to the manner in which
Measurement the contract work is to be performed.
Drawing These are intended to describe the size and dimensional requirements of the project. Many
professionals are involved in developing drawings. These include the architectural,
structural, sanitary, mechanical, electrical, topographic survey, land profile, and detailing.
Miscellaneous
Appendix to Construction Comprises tabulated and narrative information of the project such as amount and liquidated
Agreement: damages, interest rates, completion time, amounts of bond and insurances, defects
19 liability period, retention, progress payments, advance payment, etc. Some of this
information might be left blank to be filled by the contractor or might be readily provided
by the client.
The GCC
Why GCC:
Helps in a fair and adequate method of handling construction projects;
Many of the terms of the standard conditions of the contract may have been
tested by courts and hence can be relied upon to provide similar protection
to all who use them;
As contracting parties get used to them, can help in stabilizing the industry
and bid prices;
Reduces time and effort exerted in preparing contracting documents
What do GCCs do?
Provide the general framework by which construction projects are
governed;
Are usually drafted to cover common aspects of construction while specific
aspects are left for SCC,s
Generally accused to favor the party who promulgates them
FIDIC- Engineers
AGC- contractors
20
Major terms covered in GCCs &PCCs will be
discussed later
21
Contract Relationships
The Client:
Is the project initiator and usually the owner
Is responsible for appointing the Consultant (“The Engineer”)
Selects the Contractor
Ensures the Site is available for the Contractor
Agrees to any necessary changes to the Contract
Arranges payments as required under the Contracts to both the Contractor
and Consultant
22
Contract Relationships
The Contractor:
Is required to carry out the Works within the specified time in accordance with the
Contract’s requirements and to the satisfaction of the Engineer
Is required, through a competent and authorised person to manage/control the
construction of the Work. This involves:
o obtaining required materials
o programming the Works/tasks
o Setting targets for both productivity and costs
o organising necessary resource
23
Contract Relationships
The Engineer:
Is not party to the construction Contract, but to a separate agreement with the Client
Is required to exercise all reasonable skill, care and diligence and act fairly as an
intermediary between the Client and the Contractor
The Conditions of Contract define the powers and responsibilities of the Engineer.
These powers and responsibilities involve two distinct roles”
24
Contract Relationships
The Engineer:
Normally delegates many of his powers, although not all, to the Engineer‘s
Representative, formally notifying the Client and Contractor
Provides general Contract Administration, ensuring compliance by the Contractor
with time and quality obligations
Acts as a Certifier
25
Contract Relationships
The Rights and Obligations of the Client, the Contractor and the Engineer:
It is important that all involved in a Contract are aware of their rights and
obligations
It is particularly important that the Client is aware of his involvement and
where he is required to act.
Untimely action may lead to delays and increases in cost. The main
requirements are:
o those clauses defined in the Conditions of Contract and in the consultant’s services agreement
where the Engineer is required to seek the specific approval of the Employer before exercising
such authority
o the provision of drawings and instructions relating to the Employer’s design of the permanent
works within a reasonable time
o handing over the Site and access to enable the contractor to commence and proceed with the
execution of the works in accordance with the programme
o payment to the Contractor, and possibly sub-contractors, of the amount certified by the Engineer
by the due date.
in addition:
o the obligation upon the Engineer to consult with the Employer (and Contractor) on some 25
occasions within the Contract, prior to making decisions as to time and money.
26
Contract Relationships
Rights
To be notified of the appointment of Engineer’s Representative and assistants
To give consent to assignment of the Contract
To require the Contractor to complete a Contract Agreement
To require the Contractor to provide a Performance Security
To be jointly named on insurance policies
To be consulted by the Engineer on determinations of additional costs and/or extensions of time
To take out insurances (at the Contractor’s cost) in the event of the Contractor’s failure to do so
To deduct Liquidated Damages for delay from payments due to Contractor
To employ others to carry out remedial works if Contractor doesn’t do them
To terminate the Contract upon the outbreak of war
To proceed to arbitration if dissatisfied with an Engineer’s decision
27
Contract Relationships
Obligations
To appoint the Engineer
To define those duties of the Engineer which require prior approval
To make the Site available
To make available site investigation data
To be responsible for his own workmen on Site
To be responsible for his own workmen on Site
To define time(s) for completion
To make payments within 28 days of receipt of Interim Payment Certificates
To attempt to reach amicable settlement prior to arbitration
28
Contract Relationships
Rights
To be notified of the appointment of Engineer’s Representative and assistants
To be consulted by the Engineer on determinations of additional costs and/or extensions of
time
To seek consent for work at night or on rest days
To give notice of substantial completion
To be paid the value of the Works determined by measurement
To receive payments within 28 days of receipt of Interim Payment Certificates
To proceed to arbitration if dissatisfied with an Engineer’s decision
To determine employment under the Contract in the event of default by the Employer
29
Contract Relationships
Obligations
To seek the Employer’s prior consent to assignment of the Contract
To execute the Works with due diligence, remedy defects, and provide all things required
To take full responsibility for operations and methods
To execute and complete the Works in accordance with the Contract and comply with the Engineer’s instructions
To accept instructions only from the Engineer
To submit a programme and (if required) method statement
To submit a revised programme if requested
To provide full-time superintendence and representative, and replace the representative if required by the
Engineer
To replace any person when required by the Engineer
To take out necessary insurances
To comply with statutes etc. and indemnify the Employer against penalties
To keep the Site clear
To suspend the Works if instructed
To expedite progress if required by the Engineer
To submit detailed particulars of claims
To submit monthly statements of amounts due
To attempt to reach amicable settlement prior to arbitration
30
Contract Relationships
Rights
To exercise the authority to be implied from the Contract
To delegate powers to the Engineer’s Representative
To issue instructions to the Contractor as necessary
To request a revised programme
To withdraw approval of the Contractor’s representative if necessary
To require replacement of any member of the Contractor’s staff if necessary
To instruct tests on materials
To instruct a suspension of the Works
To notify the Contractor to expedite progress
To make variations he considers appropriate
To value claims in the absence of details from the Contractor
To correct or modify Interim Payment Certificates
To certify if the Contractor is in default
31
Contract Relationships
Obligations
To obtain the Employer’s specific approval when required
To appoint the Engineer’s Representative
To determine additional costs and/or extensions of time when appropriate
To issue the Taking-Over Certificate or instruct the contractor to complete outstanding works
To make variations he considers necessary
To value variations
To determine the value of the Works by measurement
To prepare Interim Payment Certificates
To issue the Defects Liability Certificate
To give an Engineer’s Decision within the stipulated time stated in the Contract
32
Contract Supervision
The Engineer
On Site
The Engineer’s Representative (Resident Engineer)
Assistant Resident Engineer
Structural Engineer
Materials Engineer
Measurement Engineer
Surveyor
Inspectors
Materials technicians
Survey Technician
33
Contract Supervision
The Specification
Supplies a detailed description of the works to be carried out
Gives the character and quality of the materials and workmanship required
Method Specification
Dictates the way to carry out the work
Risk of liability falling on Client if completed work is unsatisfactory
e.g. The number of passes can be specified for a given type pf plant on different soils
for a specified layer thickness and moisture content.
34
Contract Supervision
The Specification
The layout of a Specification can vary and various forms have been used by ERA
in the past; all future work will use ERA’s:
Standard Technical Specifications - 2002
This is divided into the following sections:
35
Contract Supervision
36
Contract Supervision
Supervision Requirements
37
Time and the Contract
38
Time and the Contract
The Importance of Records
Put it in Writing
As Built Drawings
39
Contract Administration System
Time
Quality
40
Contract Administration System
States clearly who does What, Where, When, How and Why.
• See your notes for an example of a procedure for the preparation and responsibilities
for Daily Diaries and Reports.
41
Contract Administration System
Start-Up Procedures
During the first few days and weeks of a contract, there are a number of important actions
which must be undertaken by the Employer, by the Contractor and by the Engineer (and,
where appropriate, the Engineer’s Representative, acting on behalf of the Engineer).
The actions listed below are those that are the responsibility of the Client:
• If the Engineer is not named in the Contract, the Employer must promptly notify the
Contractor of his identity.
• The Contractor must be given possession of such portions of the site as are necessary to
proceed with the Works programmed in accordance with the Clause 14 Programme,
(including, in those cases when it is the Employer’s responsibility under the Contract, any
areas of land required for temporary works.) Further possessions of Site, in accordance with
the Contractor’s programme of works must not be delayed.
• The Contractor must supply, to the Employer, any performance securities required. The
formats and acceptability of these securities must be checked (the Employer may wish to get
the national bank of the country to advise on this). When a satisfactory performance security
has been submitted, the Employer should be advised to return the Tender Bond.
42
Contract Administration System
Start-Up Procedures
The actions listed below are those that are the responsibility of the Client:
• The Employer must issue to the Engineer copies of all relevant documentation,
including all contract documentation, drawings and other design information.
The Engineer (and the Engineer’s Representative) must keep secure any
confidential documentation (particularly including the Contractor’s Bills of
Quantities) and must decide which documents are appropriate to issue to his
site staff.
• If there is any delay in finalising the Contract Agreement, copies of the tender
documentation, tender notices, the completed tender, the Letter of Acceptance
and other relevant correspondence must be supplied to the Engineer’s
Representative, as a basis for administering the contract.
43
Contract Administration System
Start-Up Procedures
The actions listed below are those that are the responsibility of the Client:
• Contact should have previously been made with any utility authorities whose
installations may be affected by the Works. The Engineer’s Representative
should familiarise himself with the current situation in this respect and should
ensure that any requirements of the Contract are followed.
44
Contract Administration System
Concluding a Contract
The following requirements are necessary towards the end of the Contract:
• Taking-Over Certificate - When the Contractor considers that the Works are
substantially complete, he may give notice to the Engineer, under the provisions
of the Contract, together with an undertaking to complete any outstanding
Works “with due expedition”. This may be done for sections of the Works
- Any further defects the Engineer’s Representative may notice during inspections
45
Contract Administration System
Concluding a Contract
The following requirements are necessary towards the end of the Contract:
• The Final Statement - Following the issuing of the Defects Liability Certificate
and in the stipulated time, the Contractor shall submit to the Engineer for
consideration a draft final statement with supporting documents showing in
detail:
- Progress the Contractor is making on completing those Works outstanding at
the time of issue of the Taking-Over Certificate
- Any further defects the Engineer’s Representative may notice during inspections
• Discharge - Upon submission of the Final Statement, the Contractor shall give to
the Employer, with a copy to the Engineer, a written discharge confirming that
the total of the Final Statement represents full and final settlement of all monies
due to the Contractor arising out of or in respect of the Contract
• The Final Payment Certificate - Within the stipulated time after receipt of the
Final Statement, and the written discharge, the Engineer shall issue to the
Employer (with a copy to the Contractor) a Final Payment Certificate stating:
- the amount which, in the opinion of the Engineer, is finally due under the Contract or otherwise, and
- after giving credit to the Employer for all amounts previously paid by the Employer and for all sums
to which the Employer is entitled other than under Clause 47, the balance, if any, due from the
Employer to the Contractor or from the Contractor to the Employer as the case may be.”
46
Contract Programme
The Contractor is required to submit a programme for the execution of the Works to the Engineer for
his consent:
• The time for submission is stated in the Part II of the Condition of Contract
• The Engineer will prescribe the form and detail required
• The Engineer thoroughly checks the submitted programme before giving
consent for its use
• The Contractor is required to submit information on methods of working as
requested by the Engineer
• The Contractor can be required to submit a revised programme if they are
behind schedule or are not following the original programme
• The Engineer usually gives consent (but is not obliged to) for the revised
programme
• The Contractor is required to submit a cash flow estimate with the Programme
• The submission or consent of the submitted programmes and cash flows does
not relieve the Contractor of any of his contractual responsibilities
47