GDR TPMC Bridge Presentation - Final
GDR TPMC Bridge Presentation - Final
Regd. Office : B-10, Krishna Industrial Estate, Opp. B.I.D.C. Gorwa Estate,
Vadodara-390016 (Gujarat) India.
MISSION
Connecting today and transforming
tomorrow is the mission of our
enterprise. GDRPL has taken up the
mission to provide world-class
services and ensure concrete
relationships with its customers.
Conceptual
Planning
Quality Control
& Assurance
Troubleshooting
Completion
WATER &
ENVIRONMENT
FIELD
TESTING
MATERIAL
TESTING PMC & THIRD
LABORATORY PARTY
INSPECTION
(3)Reporting:
•Submit Inspection report/Pour card/Check list with comments as an o
ut come of Inspection to Client.
•Mention specific remarks in Site Instruction Register as an out come
of Surveillance.
• Submit Comments on third party test report to Client
• Remember that our work is judged on our report. It must be clear, co
mprehensive, professional &
timely submitted.
TYPES OF REPORT
(1)Field Inspection Report: Generated at site as an out co
me of surveillance.
(2)Inspection Report: Generated at Third Party Lab or at
Vendor’s factory as an out come of witness.
(3)Non Conformity Report(NCR): Generated against non
conforming entity.
(4)Release note: Generated for release of specific batch
of product/material from factory to site on satisfactory c
onformity to the requirement.
(5)Inspection Certificate: Issued if specifically required by
Client.
ETHICS IN PMC JOB
(1)Independence: PMC must perform indep
endently with out external/internal influen
ce.
(2) Impartial: PMC must be impartial while p
erforming Inspection & reporting.
(3)Confidential: PMC must prevent disclosur
e of confidential information & honor Nondis
closure agreement(NDA) with Client if enter
ed into.
QUALITY IS NEVER A
N ACCIDENT, IT IS TH
E RESULT OF PLANNI
NG, TEAMWORK & A
COMMITMENT TO EX
CELLENCE.
COMPLETED
PROJECTS
- LC-32 : Kalol
Length of bridge is 760 meters in which length of railway portion is 66 meters with pile in
foundation. Crash barrier, covered drain and service road of length 1400mt is to be constructed.
- LC-51 : Vyara
Length of bridge is 756 meters in which length of railway portion is 64 meters with pile in
foundation. Crash barrier, covered drain and service road of length 1392mt is to be constructed.
- LC-69 : Umargaon
Length of bridge is 636 meters in which length of railway portion is 67 meters with pile in
foundation. Crash barrier, covered drain and service road of length 1160mt is to be constructed.