Variation Order REVISED FEB May 2017
Variation Order REVISED FEB May 2017
COURSE OUTLINE
DEFINITION
If the Project Engineer finds that a Change Order or Extra Work Order is
justified, proposed Order should be correspondingly prepared, accompanied
with the following:
1. Notices submitted by the Contractor,
2. The plans to effect the adjustments,
3. The Contractor’s computations as to the quantities of the additional works
involved per item indicating the specific stations where such works needed,
4. The date of the Project Engineer’s inspections and investigations,
5. The Project Logbook,
6. A detailed estimate of the unit cost of such items of work, together with his
justifications for the need of Change Order of Extra Work Order.
The Project Engineer upon receipt of notice, submits the same to the
Head of the Implementing Office who shall immediately instruct an
investigation to verify the Project Engineer’s report of the need for
variation order. If satisfied that such variation order is justified and
necessary, the Head of the Implementing Office shall after review,
forward the documents to the Central Office. If, after review of the
plans, quantities and estimated unit cost of the items of work involve
and finding that the Change Order or Extra Work Order to be in order
and covered by the CAF, it shall be approved by the appropriate
authority.
The Engineer shall, as soon as practicable after receiving such proposal, respond
with approval, disapproval or comments. The Contractor shall not delay any work
whilst awaiting a response. Each instruction to execute a Variation, with any
requirements for the recording of Costs, shall be issued by the Engineer to the
Contractor, who shall acknowledge receipt.
iii. D.O. No. 12, series of 2009-Revised Procedures in Seeking Prior Clearance
from the Secretary for Variation Orders on Civil Works and Consultancy
Service Contracts.
a. to be submitted directly to Usec for Operations concerned for review
and recommendation;
b. then to Asec for Planning for assessment and recommendation as to
availability of funds and if warranted, NEDA –ICC.
iv. D.O. No. 4, Series 2012 – Delegating the approval of prior clearance from the
Secretary to issue variation orders of locally funded civil works projects.
The following is the procedural flow of documents pertinent to the Request for
Prior Clearance in the DPWH Central Office in accordance with D.O. No. 156, Series
of 2015 – Implementation of the Document Tracking System (DoTs) for Civil Works
Projects.
Total 14
2. Variation Order Proper (Second Step)
Upon approval of the request for prior
clearance/authority, the Variation Order
Proper may now be submitted for processing
and approval if the supporting documents are
ready and complete.
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
1. Contractor’s Request The Contractor's request is being required as this shows the participatory role of
the Contractor in the proposed changes to the contract.
The request must bear the information of when the need for the variation order was
discovered and the request of the Contractor for an inspection must be conveyed to
confirm such need for variation order.
2. If with additional cost, Additional Performance Bond is required per IRR-A of RA 9184 which states that
Performance Security (duly the contractor shall post an additional performance security in accordance with the
verified by SAC) (If variance following schedule to cover any cumulative increase of more than ten per cent over
on the total amount of the the original value of the contract as a result of amendments due to variation orders.
contract is above 10% for Cash or cashier’s check, manager’s check, bank draft or irrevocable letter of
locally-funded and above credit- 5%
25% or as provided for in the Bank Guarantee-10%
conditions of contract for Surety Bond-30%
foreign Assisted Projects. Foreign government guarantee-100%
The Contractor shall cause the extension of the availability of the Performance
Security to cover proposed contract time extension due to variation order for it
shall be co-terminus with the final completion of the contract
For Variation Orders Without Additional Cost and/or Time Additional
Performance Bond or the extension of the previous Performance Bond is not
required.
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
3. Latest income tax and To provide proof /evidence that the contractor are paying taxes
business tax returns obligation timely for their income/proceeds of the project, in
duly stamped and compliance to executive order
received by the BIR
duly validated with the
tax payments made
thereon. Tax clearance
from the BIR to prove
full and timely
payments of taxes.
4. Certification under oath To provide proof /evidence that the contractor are paying taxes
stating that the obligation timely for their income/proceeds of the project, in
contractor is free and compliance to executive order
clean of all Tax
Liabilities to the
Government
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
5. Duly signed/approved plans for the The approved Plans is being used as reference
proposed changes in the review of items of work proposed for
the Variation Order, new unit prices for new
items of work.
It is likewise, referred to in the review of the
proposed time extensions in view of the
additional work to the contract.
6. Design Analysis & Computations for the It contains the analysis of the design and
proposed changes computation of the quantity involve in the
Variation Order as reference by BOD in the
conduct of review
7. Copy of the Complete set of the approved As reference by BOC and BOD in the review
plans (As-Staked, Original, Revised and of the items of work involved in the proposed
As-Built) Variation Order
8. Copy of approved contract including the As reference in determining the legal basis of
GCC, COPA and SCC (for applicable the Variation Order and its particular
clause/s) and previously approved application in its valuation.
variation orders(s) Also to check any duplication or overlapping
of items of work in the previously issued VO.
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
10.Where substitution of original specified To support the legal and technical merit of the
materials is involved, the following substitution of Materials requirement, and the
requirements shall be submitted (if there’s any) appropriateness/reasonableness of the cost
a. Certification on the non-availability of the estimate.
specified materials by 3 leading
Manufacturers or suppliers
b. Technical Specifications of the original
and substitute materials
c. Design computations for the substitute
material
d. Cost Estimate
11.Straight-line Diagram showing the proposed The Straight Line Diagram (color coded) should
works reflect the necessary additional works with due
reference to the original works in the contract.
It is suggested that the additional works be coded
with a different color against that of the original
ones to distinguish how much work is being
incorporated or deleted from the original contract.
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
12.Derivation of Time Extension for the The derivation of proposed time extension, if
proposed Variation Order (C.O./E.W.O.) there is any, should be based only on the items
of work which is along the critical path of the
previously approved PERT/CPM.
It is advised that to properly represent this
requirement, the contractor be made to submit
a draft revision of the PERT/CPM
incorporating the necessary changes, so that
the effect in the contract with respect to the
works, may be appropriately derived based on
reasoning.
13.Detailed Unit Cost Analysis for new items of As reference in the review of the costing of new
work items of work. The DUPA of original items of
a. Detailed Estimate of items of work work and previously approved Variation
under the original contract or previous Order will be used in the verification if such
approved V.O. figures reflected in the DUPA are the same
b. Canvass Price and/or derivation of figures used in the proposed new unit price in
Materials Cost delivered at site accordance with the contract requirements
c. Construction Methodology (for items
I hereby certify that
of the above which
work supportingare
documents
highlyare complete
technical or
unusual)
Print Name: ____________________________________
Designation: ____________________________________
Date: ____________________________________
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
14.Copy of Previously approved Time To further check the revised contract duration
Extension (If there’s any) and expiry date.
15.One set certified true copy of all documents For advance information/reference to the
submitted for accounting’s copy. accounting Division
2. Detailed Technical Justifications and legal The Project Engineer’s Report is being
basis for the proposed changes (prepared by required in compliance with the provisions of
consultant or implementing office) the IRR-A of RA 9184.
The Project Engineer’s Report therefore, must
be within the above mentioned guidelines which
state that if the Project Engineer finds the
variation order justifiable, he must prepare the
proposed order and submit same to the Director
together with the supporting documents.
CHECKLIST OF REQUIREMENT AS PER D.O. NO. 156, SERIES OF 2015
5. Itemized Cost of Revision It contains the detailed cost computation of all the changes in
the amount of the contract including the previous changes
that were approved in Variation Orders, if there is any.
Hence, it must include the Bill of Quantities of the original
contract, the previously approved variation orders and the
proposed work to be undertaken which is being presented on
an additive and subtractive basis to easily distinguish how
much work is being deleted and how much is being
introduced.
6. Complete Contractual Data with Project The Project Profile with updated status is
Status Report being required as this is going to be reflected
in the Executive Summary hence, the need to
update the status of the project since the
project must have progressed from the time
during the processing of the request for
clearance/authority to issue variation order.
7. Approved Price Adjustment/Escalation (If The Approved Price Adjustment/Escalation, if
there’s any) there is any, is being required to check if same
is correctly reflected in the Itemized Cost of
Revision and in the other documents
comprising the proposed change in the
contract.
Total 26
G. Additional/Extra Work Costing
The activities in the preparation and approval of variation order include
documentation, preparation of design/construction plan, quantification, valuation and
processing for approval. Valuation of Variation Orders is the act of estimating or setting
the value of the scope of works involved in the variation order. It is the essential
activity in the preparation of the variation order which provide beneficial information
to the owner and the contractor for appropriate consideration. The benefits to the
DPWH is that it will be known how much funds is needed to cover the total cost of a
variation order while the Contractor will know how much additional cash outflows
needed to undertake the works involved in the variation order and to know how much
additional income will be generated from the variation order.
The Bureau of Construction is responsible in the review/evaluation and
recommendation as to the reasonableness of the unit cost for items of work involved
and for the correctness/orderliness of the computation of the total amount involved for
all variation order as outlined in the Procedural Work Flow Chart in the processing of
Variation Orders per D.O 62, series of 1998, reiterated and stressed per D.O 242, series
of 2001 and later, D.O. No. 156, series of 2015-Implementation of the Document
Tracking System (DoTS) for Civil Works Projects.
As such, the Bureau of Construction provides check and balance to protect the
DPWH from possible overpriced unit cost of items of work or unjustifiable additional
cost that are to be approved by the authorized approving official.
1. Conditions When New Unit Cost is Necessary
a. Introduction of New Items of Work-when there are items of work that needs to be
introduced which are not previously included in the original contract.
b. Change in the Design- when there is a change in the actual site condition or
differing soil strata from what are reflected in the original design such that the use
of such information from the plans is already inappropriate. Example: Coco/timber
craneway to structural craneway, stone masonry to gabion slope protection, earth
ditch to lined ditch, pre-cast concrete piles to pre-stressed concrete piles, concrete
piles to spread footing, etc.
All new components of the new work item shall be fixed prices, provided the
same is acceptable to both the Government and the contractor, and provided
further that the direct unit costs of new components shall be based on the
contractor's estimate as validated by the procuring entity concerned via
documented canvass in accordance with existing rules and regulations.
The direct cost of the new work item shall then be combined
with the mark-up factor (i.e., taxes and profit) used by the contractor in his bid
to determine the unit price of the new work item.
b. FIDIC-General Condition Sub-clause 52.1-Valuation of Variations:
“All variations referred to in Clause 51 and any additions to the Contract
Price which are required to be determined in accordance with Clause 52
(for the purposes of this Clause referred to as “varied work”), a) shall be
valued at the rates and prices set out in the Contract if, in the opinion of
the Engineer, the same shall be applicable. b) If the Contract does not
contain any rate or prices applicable to the varied work, the rates and
prices in the Contract shall be used as the basis for valuation so far as
may be reasonable, c) failing which, after due consultation by the
Engineer with the Employer and the Contractor, suitable rates or prices
shall be agreed upon between the Engineer and the Contractor. d) In the
event of disagreement, the Engineer shall fix such rates or prices as are,
in his opinion, appropriate and shall notify the Contractor accordingly,
with a copy to the Employer. e)Until such time as rates or prices are
agreed or fixed, the Engineer shall determine provisional rates or prices
to enable on-account payments to be included in certificates issued in
accordance with Clause 60.”
c. FIDIC-General Conditions Sub-clause 52.2 – Power of the Engineer To
Fix Rates “ Provided that if the nature or amount of any varied work
relative to the nature of amount of the whole of the Works or to any part
thereof, is such that, in the opinion of the Engineer, the rate or price
contained in the Contract for any item of the Works is, by reason of such
varied work, rendered inappropriate or inapplicable, then, after due
consultation by the Engineer with the Employer and the Contractor, a
suitable rate or price shall be agreed upon between the Engineer and the
Contractor. In the event of disagreement, the Engineer shall fix such
other rate or price as is, in his opinion, appropriate and shall notify the
Contractor accordingly, with a copy to the Employer. Until such time as
rates or prices are agreed or fixed, the Engineer shall determine
provisional rates or prices to enable on-account payments to be included
in certificates issued in accordance with Clause 60.”
3. Checklist of Supporting Documents (For New Unit Costing)
a. Request of the Implementing Office to BOC for review and evaluation of the New Unit
Cost.
b. Evaluation and Recommendations of the Implementing Office and the Consultant.
c. Request of the Contractor to the Consultant or Implementing Office for the approval of
the New Unit Cost
d. Original copy of the detailed unit price analysis of the Contractor together with the
following supporting documents;
i. Derivation of the number of days for equipment and manpower
ii. Quantity calculation of the component materials
iii. Proposed Construction Methodology (for items of work which are highly
technical or unusual)
e. Copy of the approved design plans
f. Copy of the Detailed Estimate of Items of Work under the Original Contract with
component materials used and equipment utilized similar to the proposed new items of
work.
g. Contract Agreement to check what guidelines will be adopted for the costing of New
Items of Work (RA 9184, FIDIC)
h. Canvass Price of Construction Materials ( at least 3 suppliers)
i. Sketch Drawing showing the location of the old and new materials sources and disposal
sites indicating their hauling distance.
j. Matrix of quantities of items of work showing the original quantity and the revised
quantity and their overruns in figure and in percent.
k. Location plan, cross section drawing & photograph (for difficult site condition).
l. Additional justification, if necessary.
4. Procedural Flow-Review of New Unit Cost
The Implementing Office shall request from the Bureau of Construction the
review of proposed unit prices supported with the supporting documents and the BOC
shall reply with the proper review thru a memorandum to the Implementing Office.
Consultant
Implementing Office
Return
to
Implementing Office BOC
BOD
Legal Service
U/Sec. In-charge of BOC
U/Sec In-charge for Operation
Chief of Staff
Secretary
H. Problems Encountered in the Processing of Variation Orders
i. After Approval of the Authority, Another Authority Was Required Because of
the New Costing - This may be the result of inadvertent error in the cost
calculation or the additional scope of work or adjustment in new unit costs that
was incorporated during the finalization of the variation order. Whatever the cause,
this may be avoided by providing a more realistic estimate of the cost in the
request for Prior Clearance/authority to Issue Variation Order. A new authority is
no longer required after the approval of the previous authority. The new costs
could be reflected in the Variation Order proper since it was already established
that there was a need to undertake the proposed variation order. The Implementing
Office however have to explain in writing why there is additional cost to the
amount mentioned in the approved request for prior clearance/authority to issue
Variation Order.
ii. Lengthy Negotiations With the Contractor on the New Unit Price - Another
problem is that there will be lengthy negotiations with the Contractor on the new
unit price if he refuses to accept the review done by BOC hence, the request for
reconsideration which will only delay the approval of the variation order.
iii. Insufficient Certification of Availability of Funds - There are times that only
part of the proposed amount of variation order is being certified to be available by
the Department Budget Officer and the rest is being certified by the Planning
Service to be included in the next infrastructure program. This is not allowable as
it is clear that the funds should be available for the purpose before the variation
order is approved. There are times also that the variation order amount is a little bit
more than what is certified by the Department Budget Officer. This happens when
during the estimating of the costs, there were some inadvertent error committed
which lead to the insufficient amount of the CAF.
iv. Insufficient Performance Security- just like the CAF, there are times when the
amount specified in the Performance Security is not enough for the amount of the
additional cost of the variation order. The reason may be pointed to the fact that the
previous amount was the basis in the issuance of Performance Security but then,
cost recalculations may have resulted to the insufficiency due to things that were
not considered before. Likewise, the validity of the Performance Security is
sometimes found to be deficient as to coverage specially if there is a contract
extension due to the variation order. The Bondsman should express that he does
not in any way, object to the extension of the validity of the Performance Security
up to the date of the project completion which was extended due to the time
extension of the variation order. Further, Performance Security should be validated
and certified by the Special Action Committee.
v. Variation Order Not in the Standard Format- At times, the Itemized Cost of
Revision does not contain the contents of the previously approved variation orders or
does not contain the correct signatories. There are variation order documents that are
submitted not within the accepted format in the department.
vi. Invalid Justification - There are justifications submitted for the request for prior
clearance/authority to Issue Variation Order that is considered invalid as it lacks the
technical and legal basis to back up the said request. - For example a justification
being given that the congressman is requesting for the additional work to be done to
the project even if the work is not within the original scope of work of the contract.
ii. Ensure the Proposed Variation Order is in Compliance With the Contract
Documents, Other Guidelines and Laws of Infrastructure Implementation
-There are complete documents submitted but clarification is still needed since it
cannot establish compliance with the rules and regulations. Although there is an
established checklist, BOC cannot be faulted for returning documents with unclear
presentations.
iii. During Processing of Request for Clearance/Authority, There Are Parallel Activities That
May Be Pursued in Advance. Example: Processing of Plans and Drawing and Review of New
Unit Price of Items of Work -The Consultants and the Implementing Office need not wait for the
approval of the requests for prior clearance/authority before submitting the whole of the
documents which is expected to also take time for the evaluators to review.
iv. During Emergency Situation, the Two Step Procedure May Be Waived and
Instead, a Simultaneous Approval May Be Requested -There are times during
emergency situation that the project has already been visited by several higher
authorities of the Department and the need has already been physically verified
and established. In this instant case, the two step procedure may be waived and
instead, a simultaneous approval may be requested.
Project/Location :
You are hereby directed to make herein described changes from the plans and specifications of the following described work not included in the plans and specifications:
CHANGE REQUESTED BY :
(Work to be performed at agreed price.)
ITEMIZED QUANTITIES AND COST OF REVISION IS SHOWN ON THE ATTACHED BILL OF QUANTITIES AND COST ESTIMATE
We the undersigned Contractors have given careful consideration to the change proposed Difference in Cost due to this Change : PhP (+) or (-)
and hereby agree, if this proposal is approved that we will provide all equipment, furnish all Net Cost of Previous Change :
materials except as maybe otherwise be noted and perform all services necessary for work Total Cost of Change :
above specified and will accept as full payment thereto the prices shown on the second Original Contract Amount : PhP
page of the attached sheet. Estimated Revised Contract Amount : PhP
Percentage Change in Original Contract Value (+) or (-) :
CONTRACTOR :
District Engineer/
NOTE: This Variation Order is not effective until approved. Regional Director
Undersecretary
Secretary
ITEMIZED COST OF REVISION
(Proposed Variation Order No. __)
Project : ______________________
Location : ______________________
Contractor : ______________________
Project Engineer Chief, Planning & Design Section/ Chief, Construction Section
Conforme:
Contractor
LEVELS OF AUTHORITY
LEVELS OF AUTHORITY
D.O. No. 54, Series of 2011 – Revised Limits of Responsibilities and
Authorities of Concerned DPWH Offices and Official in the Conduct of
Pre-Procurement, Procurement, and Implementation Activities for DPWH
Locally – Funded Civil Works Projects.
Additional scope of works refers to works outside but contiguous to the original project
limits. The approval of VO covering addition/deletion of works within the original
project limits and the additional scope of works shall still be in accordance with
Department Order No. 54, series of 2011. The cumulative amount of the positive or
additive VO shall not exceed ten percent (10%) of the original contract price pursuant
to the Implementing Rules and Regulations of R.A. No. 9184.
This Order amends pertinent provisions of Department Order No. 54, series of
2011 and shall take effect immediately.
DEPARTMENT ORDER 04,
Series of 2012
SUBJECT : DELEGATING THE APPROVAL OF
PRIOR CLEARANCE FROM THE
SECRETARY TO ISSUE VARIATION
ORDERS OF LOCALLY-FUNDED
CIVIL
WORKS PROJECTS
In line with our continuing effort to simplify operating procedures and expedite the
implementation of projects, approval of requests for prior clearance from the Secretary
to issue Variation Orders on locally-funded Civil Works projects undertaken by
Regional and District Engineering Offices, is hereby delegated to Regional Directors.
It is understood, however, that Variation Orders shall still be processed and approved
following existing procedures and prescribed levels of authorities. Likewise, pursuant to
the Implementing Rules and Regulations of R.A. No. 9184, the cumulative amount of
the positive or additive Variation Order shall not exceed ten percent (10%) of the
original contract price.
This Order amends pertinent provisions of D.O. No. 12, series of 2009, and takeseffect
immediately.
D.O. 28, Series of 2015 – SPECIFIC GUIDELINES TO MANAGE AND
CONTROL VARIATION ORDERS FOR DPWH INFRASTRUCTURE
CONTRACTS
To reduce the incidence and improve the management of Variation Orders (VOs) for
infrastructure contracts undertaken by the DPWH, all concerned are hereby directed
to observe the following guidelines in relation to the provisions of Annex E
(Contract Implementation Guidelines for the Procurement of Infrastructure Projects)
of the Implementing Rules and Regulations(IRR) of Republic Act (RA) No. 9184:
b. Before procurement, the Implementing Office (IO) shall ensure that the
detailed engineering plans for the contract, especially if prepared more
than one year ago, are properly updated to reflect current physical
conditions.
D.O. 28, Series of 2015 – SPECIFIC GUIDELINES TO MANAGE AND
CONTROL VARIATION ORDERS FOR DPWH INFRASTRUCTURE
CONTRACTS
c. Upon the issuance by the DPWH of the Notice to Proceed (NTP) for a
contract, the Implementing Office shall provide the contractor an
electronic/soft copy of the approved plans for the project to facilitate the
preparation by the contractor of as-staked plans. Any disparity between
the as-staked plans and the approved plans may serve as the basis for
the initial VO.
a) (i) the measured quantity of the item is changed by more than 10% from
the quantity of this item in the bill of quantities or other schedule;
(ii) the change in quantity multiplied by such specified rate for this
item exceeds 0.01% of the accepted contract amount;
(iii) this change in quantity directly changes the cost per unit quantity of
this item by more than 1%; and
(iv) this item is not specified in the contract as fixed price.
or
b) (i) the work is instructed under Clause 13 (Variations and Adjustments);
(ii) no rate or price is specified in the Contract for this item; and
(iii) no specified rate or price is appropriate because the item of work is
not of similar character, or is not executed under similar conditions, as any
item in the contract.
Each new rate or price shall be derived from any relevant rates
or prices in the Contract, with reasonable adjustments to take
account of the matters described in sub-paragraph q) and/or
(b), as applicable. If no rates or prices are relevant for the
derivation of a new rate or price, it shall be derived from the
reasonable Cost of executing the work, together with
reasonable profit, taking account of any other relevant matters.