This document provides details on the design and construction of a 69kV substation for KCC Mall of Cotabato City. It outlines the contractor, methodology, standard composition, yard requirements, safety protocols, proposed construction schedule, manpower schedule, and equipment to be used. The key components of the substation include disconnecting switches, lightning arresters, current and potential transformers, gas circuit breakers, a 10MVA power transformer, XLPE cable, and a grounding system. Standard practices for substation construction including following the project documents, electrical and building codes, and manufacturer standards are also described.

Uploaded by

Romie Araza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
357 views18 pages

KCC MALL - Rev 05

This document provides details on the design and construction of a 69kV substation for KCC Mall of Cotabato City. It outlines the contractor, methodology, standard composition, yard requirements, safety protocols, proposed construction schedule, manpower schedule, and equipment to be used. The key components of the substation include disconnecting switches, lightning arresters, current and potential transformers, gas circuit breakers, a 10MVA power transformer, XLPE cable, and a grounding system. Standard practices for substation construction including following the project documents, electrical and building codes, and manufacturer standards are also described.

Uploaded by

Romie Araza
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 18

KCC MALL OF COTABATO CITY

69KV SUBSTATION DESIGN AND BUILD

10 QUEZON AVE. ROSARY HEIGHT 2, COTABATO


CITY, 9500 MAGUINDANAO

Contractor : ALTERNATIVEPOWER SOLUTIONS, INC.


Methodology Flow Chart
Methodology Flow Chart
Substation’s Primary Parts
 Disconnecting Switch (DS)
 Lightning Arrester (LA)
 Current Transformer (CT)
 Potential Transformer (PT)
 Gas Circuit Breaker (GCB)
 Power Transformer 10MVA
 XLPE Cable
 Grounding System
 MVSG (by owner)
Standard Substation Composition
Standard Fallow in Constructing Substation

 The project documents, the approved drawings


 The End Client Standard Civil Works, sets out the majority of
the requirements for civil design and construction
 National Building Code of the Philippines
 Philippines Electrical Code
 Environmental Compliance Certificate of the Philippines
 National and Locally Permits and bylaws
 Department of Public Works and Highway (DPWH)
 Manufacturer and other standard which is Internationally
accepted
Substation Yard Requirements
 Materials; Base Course, Sub Base, Subgrade, and Selected fill 
 Sealed base course; Fine crushed rock (FCR) layer consisting of base
course material as per acceptable standard of NBC/DPWH
 Unsealed base course; natural gravel layer consisting of unsealed
material
 Sub-base course; FCR layer(s) below base course and overlaying
subgrade or select fill consisting of sub-base course material
Standard
 Sub-grade; Soil below the sub-base course and must be either
suitable in site material or must be built up using select fill
 Select fill; Material free of vegetable and other deleterious matter,
free of clay lumps
Compaction Table
Safety Protocol
 Safety issue on the builders area are typically
nominated on the plan, it must be
verified/identified by the Substation
Construction Safety officer during the pre-
start meeting
 The Safe Work Areas must be demarcated by

the appropriate barrier (i.e. fences, bunting,


flags) as defined in OSHA, EH&S contruction
safety standard
 Excavations
Extreme caution must be exercised when excavating inside or
adjacent to substations to avoid damage to or contact with
existing underground services. Excavation inside/outside the
substation a Permit to Dig is required for all excavations
>300mm
SAFETY MEASURE
 APSI Worker are required to wear PPE
 APSI fallow International Safety Standard
also with the end client safety & electrical
standard

 APSI exercise OSHA’s Electrical & Safety


Standard, NFPA 70E Electrical safety
requirements for workers and workplace.
Electrical Safety Test Prior to Energization

 Power Quality Analyzer


 Protection Relay Testing
 CT and PT Testing
 Hi pot Testing
 Power Circuit Breaker Test
 Insulation Resistance Test (IR)
 Ground Resistance Test
Proposed Construction Schedule
Manpower Schedule
Equipment/Tool Schedule
THANK YOU