0% found this document useful (0 votes)
41 views

Che 422: Process Evaluation, Design and Project Management: Lecture One

This document provides an overview of a chemical engineering course titled "Process Evaluation, Design and Project Management". The course is divided into three sections: process evaluation, process design, and project management. It outlines the topics that will be covered in each section, the course prerequisites, assessment criteria, recommended textbooks, learning objectives, and an overview of the basis and content of the course. The course utilizes knowledge from prerequisite chemical engineering courses and applies it to the design of chemical processes and plants as well as chemical engineering project management.

Uploaded by

Asasira Irad
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views

Che 422: Process Evaluation, Design and Project Management: Lecture One

This document provides an overview of a chemical engineering course titled "Process Evaluation, Design and Project Management". The course is divided into three sections: process evaluation, process design, and project management. It outlines the topics that will be covered in each section, the course prerequisites, assessment criteria, recommended textbooks, learning objectives, and an overview of the basis and content of the course. The course utilizes knowledge from prerequisite chemical engineering courses and applies it to the design of chemical processes and plants as well as chemical engineering project management.

Uploaded by

Asasira Irad
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 67

CHE 422: PROCESS EVALUATION,

DESIGN AND PROJECT


MANAGEMENT
LECTURE ONE

31-Dec-14 Chem Eng Design 1


Introduction
The course unit consists of three sub-
sections:
• Process evaluation
• Process design, and
• Project management

31-Dec-14 Chem Eng Design 2


Course Outline
A. Process Evaluation
1. Cost estimation:
2. Start-up expenses:
3. Interest & investment costs:
4. Taxes & insurance:
5. Depreciation:
6. Profitability, alternative investments &
replacement:
7. Balance sheets & income statement
31-Dec-14 Chem Eng Design 3
B. Process Design
1. Introduction
2. Anatomy of manufacturing process
3. Process design fundamentals
4. Use of process simulator(s) to:
– Model chemical process plants (PFD and
P&ID)
– Troubleshoot issues
– Optimize energy/material use & costs
5. Design of chemical engineering plant (case
study)
31-Dec-14 Chem Eng Design 4
C. Project Management
1. Introduction
2. Project management
3. Project planning

31-Dec-14 Chem Eng Design 5


Course Prerequisite
1. Transport phenomena
2. Heat and mass transfer
3. Engineering thermodynamics
4. Chemical engineering economics
5. Reaction engineering kinetics
6. Any other chemical engineering units

31-Dec-14 Chem Eng Design 6


Assessment
1. Course work to be graded as follows:
a) Test: 20%
b) Assignment: 10%
c) Group Project:10%
2. Final exam: 60%
NB: Group projects will be assigned at the
beginning of semester

31-Dec-14 Chem Eng Design 7


Recommended Books
1. W.D. Seider, J.D. Seader, and D.R. Lewin, Product
& Process Design Principles, 2e, John Wiley and
Sons, New York (2003), ISBN 0-471-21663-1.
2. Gavin Towler and Ray Sinnott, Chemical
Engineering Design: Principles, Practice and
Economics of Plant and Process Design, Elsevier,
Amsterdam (2008), ISBN 13: 978-0-7506-8423-1.
3. Coulson & Richardson’s Chemical Engineering.
Vol. 6., Design
31-Dec-14 Chem Eng Design 8
Objectives and Expected Outcomes
By the end of the unit, learners should be
able to:
• Explain principles of project management
and the general characteristics of chemical
engineering process design problem and
strategy for the solution

• Manage a project of chemical engineering


nature
31-Dec-14 Chem Eng Design 9
• Generate a chemical engineering project
plan
• Ensure that all tasks of a given project are
completed on time and within budget
• Fulfill quality requirements of a given
project and satisfy stakeholders
• Accurately estimate project resources, time,
cost and risk by creating work breakdown
structures

31-Dec-14 Chem Eng Design 10


• Identifying project risks and developing
plans to minimize, eliminate or handle
them
• Incorporate the techniques in their final
year projects
• Produce a project report detailing the
design and documentation of a given
project.
• Create designs for chemical, biological and
manufacturing processes.
31-Dec-14 Chem Eng Design 11
• Theoretically and practically design
equipment by determining the sizes and
material/energy balances
• Estimate investment & production costs and
the associated taxes for a chemical
engineering project
• Draw balance sheets & write down income
statements for chemical engineering
projects.

31-Dec-14 Chem Eng Design 12


• Determine the economic feasibility of
chemical engineering projects
• Use process simulation programs, project
planning and cost estimating tools in
chemical process & plant design.
• Evaluate the safety and environmental
issues related to a design.

31-Dec-14 Chem Eng Design 13


Basis of the study
• Chemical engineers concern themselves
with the management of chemical and
physical processes that turn raw materials
into valuable products.
• The necessary skills encompass all aspects
of design, testing, scale-up, operation,
control, and optimization

31-Dec-14 Chem Eng Design 14


Overview
• The course unit utilizes knowledge of
several chemical engineering course units
studied from year one to-date
• Applies to the design of chemical
engineering plants and processes of
manufacturing and processing industries.

31-Dec-14 Chem Eng Design 15


The study is divided into three sections:
A. Process evaluation
B. Chemical engineering process design
C. Chemical engineering project
management

31-Dec-14 Chem Eng Design 16


• Process evaluation involves the economic
evaluation and feasibility of a given
chemical engineering project.
• Process design is the step-by-step
arrangement of how the process will be
implemented.
• Chemical engineering project management
deals with application of project
management principles to Chem. Eng.
project
31-Dec-14 Chem Eng Design 17
A) PROJECT MANAGEMENT
Introduction
• The ability to manage complex projects is
vital to keep up with the chemical industry’s
demands and needs.
• Many chemical engineers have no formal
training in project management
• Therefore the need for skills required to
manage projects in time and within budget.
31-Dec-14 Chem Eng Design 18
• A project is an individual or collaborative
undertaking that is carefully planned to
achieve a particular aim
• It is a planned set of interrelated activities
that are to be executed in a given period of
time and within given costs and other
limitations such as personnel
• The key steps of successful project
management are: initiation, planning,
execution, monitoring, control and closing
31-Dec-14 19
Characteristics of a Project
Projects are usually self contained and
involve a set of related activities. They
therefore:
• Have clearly defined set of aims and
objectives
• Have a set completion date
• Are often unique or at least different from
routine activities

31-Dec-14 20
• Involve a set of related activities which
make up “the project”
• Have resources specifically allocated to
them often in form of a project budget
• Involve a team of people, rarely completed
by an individual

31-Dec-14 21
• The objectives, called specifications, are
imposed on the project manager from
above and may often be varied and in
conflict with each other
• The project can be large, such as
construction of a dam; establishing an oil
refinery plant; building a sugar factory;
construction of road highway; etc.

31-Dec-14 22
• It may also be small, such as purchase and
installation of distillation unit; cracker;
pyrolyzer; construction of a rural water
well; painting the administration block;
etc.
• A manager is therefore central for the
successful completion of a given project

31-Dec-14 23
Project Management Process

• Project management is the art of handling


resources, processes, methods, knowledge,
skills and experience in order to achieve the
project objectives.
• The project objectives could be defined in
terms of outputs, outcomes or benefits.

31-Dec-14 24
• The project manager is expected to deliver
the project on time; within budget; and on
target in terms of objectives of quality
standards
• The project specifications frequently clash
during project life.
• For example, if the project falls behind
schedule in terms of completion date, it
should be rectified and the project brought
back to schedule
31-Dec-14 25
• This can be done by increasing the costs;
reducing targets; etc.
• Similarly, if the project becomes over
budget, it can be brought back under
control by altering requirements
• The project management task therefore
becomes simultaneous achievement of the
three requirements and not just a trade-off.
• The following are therefore major tasks of a
project manager:
31-Dec-14 26
• Ensuring that individual activities are
completed on time so that overall project is
completed on time
• Identifying potential problems before they
occur so that appropriate corrective actions
can be taken
• Have an effective monitoring system for the
project so that progress can be assessed
easily and effectively at any time

31-Dec-14 27
• React promptly to planned or accidental
deviations from the project and assess
options for re-establishing control
• Plan resource requirement to fit into the
project time scale to ensure that critical and
scarce resources are in the right place and
at the right time

31-Dec-14 28
• Prioritize between different activities and
their resource requirements
• To meet these requirements and
simultaneously achieve the three project
features, the following steps will be
required for effective project management.

31-Dec-14 29
Define the Scope
• The very first question to a project manager
is: what is it that is supposed to be achieved
or accomplished in the project?
• What is/are the project objective(s)?
• What is not to be included in the scope of
the project.
• All these are obtained from the CEOs if not
then seek clarification where assumed
31-Dec-14 30
Determine Available Resources
• What human resource, equipment and finances
are available for achieving project objectives?
• As a project manager you may not have direct
control over these resources but have to
manage them.
• Find out how difficult/easy that will be. These
may constitute project limitations.
• Employ principles of matric management to
effectively manage the resources
31-Dec-14 31
Check Timelines
• When is the project supposed to
commence and end?
• Fix deadlines but have flexibility in using
time in your plan.
• If overtime is utilized check it against
budget limitations

31-Dec-14 32
Assemble Project Team
• Put the project team together and begin
discussions.
• These are usually technical experts assigned
to the project by your supervisor or the
project owner.
• Your task is to manage so that project
objectives are achieved effectively, efficiently
on time and within budget.
31-Dec-14 33
List the Big Steps
• What are the major parts or tasks of the
project, the answer can be from team
discussions.
• These should be listed chronologically as
they will occur in the project although the
order may be changed later

31-Dec-14 34
List Smaller Steps
•  List the smaller steps in each of the bigger
tasks, chronologically to help remembering
them.
• The depth and detail of each step depends
on the project size and complexity

31-Dec-14 35
Develop Preliminary Project Plan
• Assemble all the steps above into a plan
beginning with what is to be done first, the
next step, etc.
• Identify which steps can be done at the same
time with different resources,
• Who is to perform each step, how long will it
take.

31-Dec-14 36
• Software packages can be employed to
automate the detail.
• Enquire from other project managers what
they are using if possible.
• The plan should include activity (scope),
schedule (duration) and cost as performance
measures.

31-Dec-14 37
Create Baseline Plan
• Obtain response and feedback about the
preliminary plan from the project team
and other stake holders.
• Adjust the timelines and work schedules
where necessary to fit the project in the
available time, people and budget.

31-Dec-14 38
• Make other adjustments incorporating all
feedback to the preliminary plan and
generate baseline plan.
• Baseline plan provides roadmap/direction
for project managers and other
stakeholders to follow,
• It is a tool for controlling and
communication throughout the project life
and sets the course of action for the
project.
31-Dec-14 39
• It is a major work product that is
communicated to all stakeholders before
start of project.
• Other products include risk management
plan, quality plan, procurement plan
staffing and communication plans.

31-Dec-14 40
Request Project Adjustments
•  In most cases, project resources are never
enough and the project manager is usually
tasked to do more with the limited
resources than expected.
• This may create unrealistic demands and
unlikely limits placed on the project by the
project owners.

31-Dec-14 41
• The project manager needs to make his/her
case clear and present it to the bosses
• Request for changes at the beginning of the
project and not later in the middle of during
project life

31-Dec-14 42
Work Your Plan
• Project plans can be changed where need
arises, keeping the scope and resources in
mind.
• Work your plan, don’t be rigid on it
• There are three steps to get your project
done on time:

31-Dec-14 43
Build Work Breakdown Structures
• A Work breakdown structure (WBS) is the
breakdown of the deliverables into manageable
units of work
• It is a list of project tasks organized in a manner
that lets you understand and visualize the
connections between the various tasks and
sub-tasks.
• It is used to define and organize the tasks
needed to complete the project.
31-Dec-14 44
• This is accomplished through the following
steps:
– Determine the desired project results
– List the major steps, this gives the
framework that can be used to think and
organize the smaller tasks
– Determine the smaller tasks of each major
step
– Continue the process

31-Dec-14 45
• The WBS are small activities or parts that
constitute the entire project objective.
• It is the breakdown of the big task into
small manageable activities.
• It is the process of continuously reducing
an immense task or objective into its
component parts that can be handled and
estimated in terms of effort; resources;
cost and duration.
31-Dec-14 Chem Eng Design 46
• The WBS provides an understanding
needed to handle complex and
overwhelming tasks or projects.
• It also provides the foundation for
planning; monitoring and controlling the
project.

31-Dec-14 Chem Eng Design 47


• It is best done through team work and
provides a common understanding of
how to go about a given project.
• It is the foundational or first activity and
provides basis for project planning and
other project management functions.

31-Dec-14 Chem Eng Design 48


• The WBS provides the project manager
and his/her team with necessary
framework required for making detailed
cost estimates and activity scheduling.
• The WBS process helps to generate and
capture the necessary tasks based on
project requirements or objectives

31-Dec-14 Chem Eng Design 49


Assignment
State the Advantages and Disadvantages of WBS
• Forces the team to create details about the
project and eliminate ambiguities and unclear
situations about the project.
• The activity creates dialogue that clarify
ambiguities and identify critical issues
• It lays the foundation for developing proper
project budgeting and appropriate activity
scheduling.
31-Dec-14 Chem Eng Design 50
Characteristics of WBS
• The WBS involves organizational levels or
hierarchies.
• The key characteristics of WBS are:
– Hierarchical Levels: contains three levels
of work in a top-down decomposition of
outputs

31-Dec-14 Chem Eng Design 51


– Defines outputs and not processes
– Numbering Sequence – uses outline
numbering as a unique identifier for all
levels:
• Level one is 1.0, which illustrates the
project level.

31-Dec-14 Chem Eng Design 52


• Level two is 1.X (1.1, 1.2, 1.3, etc.),
which is the summary level, and often
the level at which reporting is done.
• Level three is 1.X.X (1.1.1, 1.1.2, etc.),
which illustrates the work package
level.
• The work package is the lowest level
of the WBS where both the cost and
schedule can be reliably estimated.

31-Dec-14 Chem Eng Design 53


• Lowest Level Descriptions – expressed
using verbs and objects.
• The lower levels and inputs to the higher
levels
• Responsibility for each activity is assigned
to individuals
• Budgets is assigned to each output
• Can be structured e.g., in form of tree
diagram or organizational chart
31-Dec-14 Chem Eng Design 54
Example of WBS
Provision of catering service to a wedding party
reception
The objective is to provide catering service to a
wedding party

31-Dec-14 Chem Eng Design 55


31-Dec-14 Chem Eng Design 56
31-Dec-14 Chem Eng Design 57
31-Dec-14 Chem Eng Design 58
31-Dec-14 Chem Eng Design 59
• How far does one go? When do we stop
breaking the tree?
• Continue with the WBS until the first word
is a verb.
• Also, stop at the level of detail where the
resulting activity will not take long and can
be estimated in terms of effort; duration
and cost.
• The WBS is then used to generate the
activity log
31-Dec-14 Chem Eng Design 60
• Note that a huge complexity may arise for
some projects where an activity may be
more than four levels below the top level.
• This may require huge piece of paper for
proper visualization.
• Usually, wall papers are used, which may
enable interchanging and/or deleting
some elements of the WBS where
necessary.

31-Dec-14 Chem Eng Design 61


• Organize the WBS with labels for each
level, numbering sequentially and
chronologically.
• This gives unique identifiers that represent
the position of the activity in the WBS.
• The most detailed levels are used as basis
for activity list while higher levels are used
for summary and reporting.

31-Dec-14 Chem Eng Design 62


• Producing the WBS as team exercise forms
part of initial team building sessions.
• It brings together the depth of experience
from individual team member.
• This leads to proper planning and reduced
levels of risks, leading to a successful
project.

31-Dec-14 Chem Eng Design 63


• Getting the WBS right allows the project
manager to delegate subsequent project
definitions and planning activities with
better clarity.
• At the end of the WBS process, the project
team should feel less overwhelmed and
less worried about the project.
• A clearer vision of what the project will
look like emerges.

31-Dec-14 Chem Eng Design 64


Provision of Catering Service
Activity Log
Activity Description Duration Predecessor
A Assemble working team    
B Meet party owner to agree on menu    
C Meet party owner to agree on budget    
D Brief working team & brain storm    
E Meet working team to assign roles    
F Dispatch working team    
G Purchase food items    
H Purchase drinks    
I Hire service utensils/cutlery, etc.    
J Hire transport van    
K Peel bananas    
31-Dec-14 Chem Eng Design 65
Activity Log (Cont.)
Activity Description Duration Predecessor
L Sort rice    
M Prepare other food items, Irish, etc.    
N Cut meat; fish; spices; etc    
O Cook meat; fish; etc    
P Chill drinks    
Q Fuel van    
R Load the van    
S Transport team, food, etc., to venue    
T Off-load van    
U Dispatch workmen to service points    
31-Dec-14 Chem Eng Design 66
Activity Log (Cont.)
Activity Description Duration Predecessor
V Prepare service points/tables    
W Serve food at service points    
Z Collect & sort all used    
T Load used items onto van    
Z Transport all items back to office    
A1 Off-load used items from van    
B1 Sort, clean & store used items    
C1 Pay team workers    
D1 De-brief: Strengths/weakness    
E1 Celebrate & close    

31-Dec-14 Chem Eng Design 67

You might also like