Topic 5 - Optimisation - Graphical Method 1
Topic 5 - Optimisation - Graphical Method 1
SYSTEM OPTIMISATION:
Adrian Bown
• Construct a model
• Derive a solution
• Construct a model
• Derive a solution
Commodity 1, C 1 3 2 2
Commodity 2, C 2 2 4 3
Maximum
7 10
Resources
• If the system were, say, a consulting structural engineering
company, the resources and commodities might be:
Resource
Design1, R 1 Resource 2, R 2
Drawing Profit
Commodity 1, C 1
Retaining wall 3
3 hours 2
2 hours 2
£ 100
Portal frame
Commodity 2, C 2 2
2 hours 4 3
4 hours £ 150
structure
Maximum 7
Resources 7 hours 10 10
hours
There are 5 stages involved in solving any Linear Programming
• Construct a model
• Derive a solution
x 3 2 2
y 2 4 3
Maximum Resources 7 10
x 3 2 2
y 2 4 3
Maximum Resources 7 10
x 3 2 2
y 2 4 3
Maximum Resources 7 10
• 3x 2y 7
R1 R2 Profit
x 3 2 2
y 2 4 3
Maximum Resources 7 10
• 2 x 4 y 10
R1 R2 Profit
x 3 2 2
y 2 4 3
Maximum Resources 7 10
• 2 x 4 y 10
x 3 2 2
y 2 4 3
Maximum Resources 7 10
• 2 x 4 y 10
x 3 2 2
y 2 4 3
Maximum Resources 7 10
• Summary:
– Resource Equation 1: 3 x 2 y 7
– Resource Equation 2: 2 x 4 y 10
• Construct a model
• Derive a solution
3
3x 2y 7
2
0 X
0 1 2 3 4 5 6
The production constraints can be represented graphically by:
– If x = 0, y = 3.5
3 x 2 y 7 3 x 2 y 7 2 y 7 y 3.5
Y
3
3x 2y 7
2
0 X
0 1 2 3 4 5 6
The production constraints can be represented graphically by:
3 x 2 y 7 3 x 2 y 7 2 y 7 y 3.5
3 x 2 y 7 3 x 2 y 7 3 x 7 x 2.33
Y
3
3x 2y 7
2
0 X
0 1 2 3 4 5 6
Y
3
3x 2y 7
2
0 X
0 1 2 3 4 5 6
Y
6
3x 2y 7
5
3
3x 2y 7
2
0 X
3 x 2 y 70 1 2 3 4 5 6
Y
3
Feasible domain
2
for production
0 X
0 1 2 3 4 5 6
The production constraints can be represented graphically by:
are:
– If x = 0, y = 2.5 and, if y = 0, x = 5
Y
0 X
0 1 2 3 4 5 6
Y
0 X
0 1 2 3 4 5 6
• The shaded area that is wholly contained within the
• The objective is to find the profit line that maximises P and remains
0 X
0 1 2 3 4 5 6
Maximum profit _ Method 1 : Profit Line Method
• The objective is to find the profit line that maximises P and remains
0 X
0 1 2 3 4 5 6
Maximum profit _ Method 1 : Profit Line Method
• The objective is to find the profit line that maximises P and remains
0 X
0 1 2 3 4 5 6
• The solution for the maximum profit, Pmax, must be on the
Pmax the co-ordinates of the first intersect between the profit line
and feasible region must be found; this can be read from the
graph
Y
0 X
0 1 2 3 4 5 6
Maximum profit _ Method 2 _ Corner-point Method
0 X
0 1 2 3 4 5 6
• Resource Equation 1: 3 x 2 y 7
• Resource Equation 2: 2 x 4 y 10
0 2.5 7.5
1 2 8
2.33 0 4.66
0 X
0 1 2 3 4 5 6
Example 2 _ Minimising Cost:
• A manufacturer has the choice of two products; x and y
• For the same volume, the two products provide different quantities
of the same three chemicals – see Table below
• Based on the prices given in the table, determine how much of each
product should be used to minimise manufacturing costs
Product x 4 kg / m 3 8 kg / m 3 6 kg / m 3 £ 8 / m3
Product y 8 kg / m 3 6 kg / m 3 7 kg / m 3 £ 4 / m3
Minimum amount
of chemicals reqd. 32 kg / m 3 48 kg / m 3 42 kg / m 3
Chemical A Chemical B Chemical C Cost
Product x 4 kg / m 3 8 kg / m 3 6 kg / m 3 £ 8 / m3
Product y 8 kg / m 3 6 kg / m 3 7 kg / m 3 £ 4 / m3
Minimum amount
of chemicals reqd. 32 kg / m 3 48 kg / m 3 42 kg / m 3
Product x 4 kg / m 3 8 kg / m 3 6 kg / m 3 £ 8 / m3
Product y 8 kg / m 3 6 kg / m 3 7 kg / m 3 £ 4 / m3
Minimum amount
of chemicals reqd. 32 kg / m 3 48 kg / m 3 42 kg / m 3
Product x 4 kg / m 3 8 kg / m 3 6 kg / m 3 £ 8 / m3
Product y 8 kg / m 3 6 kg / m 3 7 kg / m 3 £ 4 / m3
Minimum amount
of chemicals reqd. 32 kg / m 3 48 kg / m 3 42 kg / m 3
– A: x = 0, y = 4 and, if y = 0, x = 8
– B: x = 0, y = 8 and, if y = 0, x = 6
– C: x = 0, y = 6 and, if y = 0, x = 7
Y
0 X
0 1 2 3 4 5 6 7 8
Y
7
Feasible domain
6
0 X
0 1 2 3 4 5 6 7 8
Y
7
Feasible domain
6
0 X
0 1 2 3 4 5 6 7 8
Y
7 ‘cost’ line
6
0 X
0 1 2 3 4 5 6 7 8
The three Resource Equations are:
A: 4 x 8 y 32
B: 8 x 6 y 48
C: 6 x 7 y 42
– A: x = 0, y = 4 and, if y = 0, x = 8
– B: x = 0, y = 8 and, if y = 0, x = 6
– C: x = 0, y = 6 and, if y = 0, x = 7
( C 8 x 4 y ) are: x = 0, y = 10 and, if y = 0, x = 5
Y
7 ‘cost’ line
6
0 X
0 1 2 3 4 5 6 7 8
Y
First value in feasible
8
domain ( x = 0, y = 8 )
0 X
0 1 2 3 4 5 6 7 8
Chemical A Chemical B Chemical C Cost
Product x 4 kg / m 3 8 kg / m 3 6 kg / m 3 £ 8 / m3
Product y 8 kg / m 3 6 kg / m 3 7 kg / m 3 £ 4 / m3
Minimum amount
of chemicals reqd. 32 kg / m 3 48 kg / m 3 42 kg / m 3