4-1 - Formwork
4-1 - Formwork
TECHNOLOGY
CEM 571
1
Temporary Works
1. Formwork
2 2. Shoring & Scaffolding
3. Trench support system
4. Underpinning
Temporary Works
1. Formwork
3 2. Shoring & Scaffolding
3. Trench support system
4. Underpinning
LEARNING OUTCOME
4
FORMWORK
“Is a mould or box into
which wet concrete can be
poured and compacted so
that it will flow and finally
set to the inner profile of the
box or mould”.
5
FORMWORK
Purpose – to contain freshly placed and
compacted concrete until it has gained
enough strength to be self-supporting
to produce a concrete member of the
required shape and size
to produce the desired finish to the
concrete
May be describe as a mould or box
6
General design of formwork
1. sufficiently rigid to prevent undue
deflection during the placing of the
concrete
2. Sufficient strength to carry the working
load and the weight or pressure of the wet
concrete and to withstand incidental
loading and vibration of the concrete
3. Set to line and level within the specified
tolerance and include any camber (bend)7
which may be required
General design of formwork
4. joints should be sufficiently tight to prevent
loss of mortar from the concrete
5. size of panels or units should permit easy
handling
6. design should permit and orderly and simple
method of erection and striking
7. Arrangement of panels should be such that
they are not ‘trapped’ during striking and it
should be possible to strike side from beams
without disturbing the soffit formwork 8
General formwork requirement
14
Timber formwork
Basic standard qualities:-
Reasonable price and availability
Should not be so soft
Should be easily worked by hand or machine
and nailed easily
Should be stiff to avoid deflection
Should be stable when exposed to sun or
rain
Should reduce defects
Not suitable for green timber 15
Moisture content not less than 20%
Advantages of timber formwork
More economic
Easy to handle and formed into required
shape
Maximum re-use
Easy to fix insert
16
Disadvantages of timber
formwork
Not enough strength as compared to
steel formwork to carry large pressure.
Excessive shrinkage due to temperature
changes.
Leakage through joints and apertures.
Easily damage during fixing and
dismantling of formwork.
The pattern of grain, knots, bad flaws will
leave imprint to the face of concrete. 17
PLYWOOD
Strong and light
Supplied in sheets - 1.2m wide
Standard length – 2.4m, 2.7m or 3.m
Thickness – from 3mm to 19mm
Thickness for lining or curved work – 16
mm or less
18
plywood formwork
19
ADVANTAGES OF PLYWOOD
FORMWORK
Large panel
Leakproof
Large level surface
No casting or cupping of surface –
smooth surface
Can be nailed to edges without splitting
High resistance to impact loads
Available in several thickness 20
Disadvantages of plywood
formwork
Grain pattern on concrete face
Less durable
More expensive compared to timber
21
Metal formwork - STEEL
Based on manufacturer pattern
Double uses compare to timber, i.e. 30 or 40 uses
Produce smooth, variable colour concrete surface
ADVANTAGES
Able to carry large concrete weight and pressure.
DISADVANTAGES 22
Limited to the shape of the structure.
23
PLASTIC
rigid form – when form is not suitable
using timber or steel (thermo-formed)
flexible form – for lining material for
mould faces
Provide high quality surface finish
Disadvantages – impermeable and need
special release agent
24
GLASS FIBRE REINFORCED
PLASTIC (GRP)
Strong and light weight
Use to produce a high quality surface
finish, eg. Sculpture profile and repetition
Comprises of polyester resin reinforced
with glass fiber
Thickness varies from 5 to 16 mm
Can be used more than 100 times if
handle with care
Disadvantages similar with plastic 25
formwork
SURFACE TREATMENT
27
Common failures of formwork
Dimensional inaccuracy
Lifting of single faced forms
Inadequate of props
Loss of material –ties or props
incorrectly spaced
Surface blemishes
28
Types of formwork
Foundation
Column
Beam
Slab
Wall
Climbing
Sliding
Permanent
System
Table 29
30
75 mm high
kicker
31
32
33
34
35
36
37
38
39
40
41
42
43
skydeck slab formwork
44
Concrete formwork and column
steel reinforcing
45
Formwork
46
STRIKING OF FORMWORK
The period before striking is depend on:-
Concrete used
Weather and exposure of the site
Any subsequent treatment to be given to the
concrete
The method of curing and other factors
47
STRIKING OF FORMWORK
Only when concrete is strong enough
and able to carry imposed load
Soffit forms to beam and slabs must be
left in place longer than the side forms
Should be with care and slowly to avoid
damage and shock load on the partly
hardened concrete
48
Concrete treatment
Stops Freeze/ Thaw Damage Fills voids and capillaries restricting
moisture travel from both below and
above the slab. Waterproofs concrete
completely.
Improves Overall Strength, Density By filling the internal and surface cavities
and Hardness with an insoluble gel, the sealer increases
the density of the mix and strengthens
the total structure. Additionally the
compound protects the encapsulated re-
enforcing steel from corrosion and
future destruction.
Reduces Maintenance Costs for Aged High traffic surfaces resist abrasion
Concrete damage longer. Top-coated materials
retain their bonding properties for a
greater length of time. Migration of49
corrosive salts are reduced. Life of
flooring adhesives are greatly prolonged
Duration for f/work removing
location Surface or air
temperature of concrete
16°C 17°C
Vertical f/work 12 hrs 18 hrs
Slab soffit (props left under) 4 days 6 days
Removal of props 10 days 15 days
Beam soffit (props left 10 days 15 days
under)
Removal of props 14 days 21 days
50
Curing
Means controlling the moisture content and the
temperature of the concrete after placing
Important to develop concrete strength
Excessive evaporation may cause multiple surface
cracks – wind cracking or plastic cracking
Should start immediately after the removal of f/work
Most effective method of curing – cover with water
proof sheets (building paper, polythene, damp
sand, damp sawdust or wet cloth)
51
General equipments
Standard adjustable steel prop
Consist of two tubular section
One with 150mm square base and other
with slides in it
Fitted with square or beam type head
(braced plate 350 mm long) to give a stable
support
52
53
General equipments
Adjustable hanging bracket
Used to hang a ledger from a beam or wall
Some need to be used with folding wedges
to enable the forms to be set and released
Adjustable steel column/beam clamp
Pins engaging holes through the bracket and
horizontal beam
Fine adjustment by screw clamp
54
General equipments
55