Engineering Economy: Other Analysis Techniques
Engineering Economy: Other Analysis Techniques
Engineering Economy
Chapter 9
Other Analysis Techniques
Lecture 11
2
University of Palestine
College of Engineering & Urban Planning
Payback Period
Payback period is the period of time required for the project’s profit or other benefits
to equal the project’s cost.
Warning
1. Payback period is an approximate, rather than an exact, analysis calculation.
2. All costs and all profits, or savings of the investment prior to payback, are included
without considering differences in their timing.
3. Payback period may or may not select the same alternative as an exact economic
analysis method.
3
University of Palestine
College of Engineering & Urban Planning
Payback Period
Example
A firm is buying production equipment for a new plant.
Tempo Dura
Two alternative machines are being considered. Year
machine machine
0 $30,000- $35,000-
1 12,000 1,000
2 9,000 4,000
3 6,000 7,000
4 3,000 10,000
5 0 13,000
6 0 16,000
7 0 19,000
8 0 22,000
PBP analysis would choose Tempo (PBP = 4 yrs.) instead of Dura
(PBP = 5 yrs.).
However, with IRR analysis we can see that Tempo is not a very 0 57,000
attractive investment.
4
Although, Tempo does return its investment more quickly than Dura.
University of Palestine
College of Engineering & Urban Planning
Payback Period
EXAMPLE 9–8
The cash flows for two alternatives are as follows:
You may assume the benefits occur throughout the year rather than just at the end of the year.
Based on payback period, which alternative should be selected?
5
University of Palestine
College of Engineering & Urban Planning
Payback Period
SOLUTION
Alternative A
Payback period is how long it takes for the profit or other benefits to equal the cost of the
investment. In the first 2 years, only $400 of the $1000 cost is recovered. The remaining
$600 cost is recovered in the first half of Year 3. Thus the payback period for Alt. A is 2.5
years.
Alternative B
Since the annual benefits are uniform, the payback period is simply
$2783/$1200 per year = 2.3 years
To minimize the payback period, choose Alt. B.
6
University of Palestine
College of Engineering & Urban Planning
Payback Period
EXAMPLE 9–9 (Example 5-4 revisited)
A firm is trying to decide which of two weighing scales it should install to check a
package-filling operation in the plant. If both scales have a 6-year life, which one should
be selected? Assume an 8% interest rate.
7
University of Palestine
College of Engineering & Urban Planning
Payback Period
9
University of Palestine
College of Engineering & Urban Planning
2. All costs and all profits, or savings of the investment prior to payback, are included
without considering differences in their timing.
3. All the economic consequences beyond the payback period are completely ignored.
4. Payback period may or may not select the same alternative as an exact economic
analysis method.
5. Payback period is used because the concept can be readily understood, the
calculations can be readily made and understood by people unfamiliar with the use
of the time value of money.
Other Factors
1. All facilities will last for 40 years regardless of when they are installed; after 40 years, they will
have zero salvage value.
2. The annual cost of operation and maintenance is the same for both two-stage construction and
full-capacity construction.
3. Assume an 8% interest rate. Plot “age when second stage is constructed” versus “costs for both
alternatives.” Mark the breakeven point on your graph. What is the sensitivity of the decision to
13
second-stage construction 16 or more years in the future?
University of Palestine
College of Engineering & Urban Planning
Two-Stage Construction
If the first stage is to be constructed now and the second stage n years hence, compute the
PW of cost for several values of n (years).
PW of cost = 100,000 + 120,000(P/F, 8%, n)
n =5 PW= 100,000 + 120,000(0.6806) = $181,700
n = 10 PW = 100,000 + 120,000(0.4632) = 155,600
n = 20 PW = 100,000 + 120,000(0.2145) = 125,700
n = 30 PW = 100,000 + 120,000(0.0994) = 111,900
These data are plotted in the form of a breakeven chart in Figure 9-4.
14
University of Palestine
College of Engineering & Urban Planning
15
University of Palestine
College of Engineering & Urban Planning
EXAMPLE 9–12
Example 8-3 posed the following situation. Three mutually exclusive alternatives are
given, each with a 20-year life and no salvage value. The minimum attractive rate of
return is 6%.
In Example 8-3 we found that Alt. B was the preferred alternative at 6%. Here we
would like to know how sensitive the decision is to our estimate of the initial cost of
B. If B is preferred at an initial cost of $4000, it will continue to be preferred at any
smaller initial cost. But how much higher than $4000 can the initial cost be and still
have B the preferred alternative? With neither input nor output fixed, maximizing
net present worth is a suitable criterion.
17
University of Palestine
College of Engineering & Urban Planning