Lecture 2 A - Contracts Project Delivery Methods-Canadian Forms
Lecture 2 A - Contracts Project Delivery Methods-Canadian Forms
Engineering Management
Principles and Economics
Lecture 2A
Project Delivery Methods and
Contracts
Dr C.J. Willis, CAPM, P.Eng 1
Project Delivery Methods
Traditional
Phased
Fast Track
• Traditional
All build activities start after all design work is
completed
• Phased
Design and build phases overlap, but for each
activity, Build starts after Design ends
• Fast Track
Design and Build phases overlap. For each
activity, Build starts before Design is finalized
Traditional
• Longest overall project duration
• Suitable for using a Single contractor
Phased
• Shorter overall duration
• Suitable for using multiple contractors;
requires PM
Fast Track
• Shortest overall duration
• Suitable for using multiple contractors,
requires PM
• Very difficult to manage
• Inadequate design and schedule